Nama : I Made Wiratha Nungrat NIM : 13209057 Tugas Manajemen Proyek Chapter 9 Problem 9.

13 Given the following project to landscape a new building site,

a) Draw a Gantt chart using MSP. b) Find the critical path and project duration in days. c) Given that each resource is assigned 100% to each task, identify the resource constraints. d) Level the resources and determine the new project duration and critical path. e) Identify what alternative solutions can be used to shorten the project duration and not over-allocate the resources. Solusi a. Gantt Chart Using MSP Gantt Task Table

Gantt Chart

b. Critical Path and Project Duration in Days

Project duration = 17 Days c. Resource constraints

Over allocation of resource : - X on 13 November and 22 November - W on 22 November d. Level the Resources After leveling the resources, the critical path of the project is shown below and the duration of the project is 21 days. New critical path

e. alternative solutions More resources can be allocated to this project to finish it on time. Set resource X and W at 200%. In that case the project will be done on time and do not overallocate the resources.