PT. PLN (Persero) Sektor Pembangkitan Ombilin

ANALISA PERFORMA

BOILER FEED WATER PUMP

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

OUT LINE

PENDAHULUAN PROFIL PT. PLN PERSERO SEKTOR PEMBANGKITAN OMBILIN

DASAR TEORI ANALISA PERFORMA BOILER FEED WATER PUMP

KESIMPULAN

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

PENDAHULUAN
Tujuan : 1. 2. 3. Mempelajari prinsip kerja suatu pembangkit listrik, khususnya PLTU. Mengetahui prinsip kerja alat Boiler Feed Water Pump. Menganalisa performa Boiler Feed Water Pump.

Waktu dan Tempat KP


Waktu Tempat : 24 Januari - 24 Februari 2012 : PT PLN (Persero) Pembangkitan Sumbagsel, Sektor Pembangkitan Ombilin Jl. M. Yamin, SH, Talawi, Sawahlunto Sumatera Barat Batasan Masalah : 1. 2. Penjelasan umum profil PT. PLN (Persero) Sektor Pembangkitan Ombilin Analisa performa Boiler Feed Water Pump

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

PROFIL PT. PLN PERSERO SEKTOR PEMBANGKITAN OMBILIN


Tugas pokok PT.PLN (Persero) Sektor Pembangkitan Ombilin mengoperasikan pembangkit yang terdiri dari PLTU Ombilin unit I dan unit II serta PLTG Pauh Limo, yang semuanya untuk melayani kebutuhan energi listrik sistem kelistrikan SumBagTeng dan SumBagSel.
No. 1. 2. 3. Uraian Peralatan PLTU unit I PLTU unit II PLTG Pauh Limo Kapasitas 100 MW 100 MW 3 x 21,35 MW Mulai Operasi 26 Agustus 1996 18 November 1996 10 September 1983

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

PT. PLN PERSERO SEKTOR PEMBANGKITAN OMBILIN

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

SIKLUS KERJA PLTU OMBILIN

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

DASAR TEORI

Pengertian
Pompa merupakan salah satu jenis mesin fluida yang berfungsi untuk memindahkan zat cair dari suatu tempat ke tempat yang

diinginkan

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Bagian-Bagian Utama Pompa Sentrifugal

Seminar Kerja Praktek

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Head Pompa
Head Suction
2 Ps Ps Zs hls Vs Hs = = g 2g g

Keterangan : Hs Ps Pa Zs Hls Vs = Head Suction (m) = Tekanan suction (N/m2) = Tekanan atmosfer di atas permukaan cairan (N/m2) = Jarak permukaan air dengan nozzle suction pompa (m) = Head loss sisi suction (m) = Kecepatan cairan pada pipa suction (m/s) = Massa jenis cairan (kg/m3)

Seminar Kerja Praktek

10

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Head Discharge Hd = Pd g Pd g Zd hld Vd 2 2g

Keterangan : Hd Pd Pa = Head discharge (m) = Tekanan discharge (N/m2) = Tekanan atmosfer di atas permukaan cairan (N/m2)

Zd
Hld Vd

= Jarak permukaan air dengan nozzle discharge pompa (m)


= Head loss sisi discharge (m) = Kecepatan cairan pada pipa discharge (m/s) = Massa jenis cairan (kg/m3)

Seminar Kerja Praktek

11

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Head Total H = (Pd Ps) + Hz + Hs + Hd g + (Vd2 Vs2) 2g


Keterangan :
Pd Ps Hz Hs Hd Vd Vs = Tekanan discharge (N/m2) = Tekanan suction (N/m2) = Tinggi kenaikan statis (m) = Rugi pada sisi isap = Rugi pada sisi tekan = Kecepatan cairan pada pipa discharge (m/s) = Kecepatan cairan pada pipa suction (m/s) = Massa jenis cairan (kg/m3)

Seminar Kerja Praktek

12

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Daya Pompa
Daya Motor P = 3 VI cos
Keterangan : P V I Cos = Daya pompa (watt) = Tegangan (volt) = Kuat arus (A) = Faktor daya

Seminar Kerja Praktek

13

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Daya Fluida
Pf = g H Q
Keterangan : Pf Q H g = Daya fluida (watt) = Kapasitas yang dihasilkan pompa (m3/s) = Head total (kg/m3) = Percepatan grafitasi

Seminar Kerja Praktek

14

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Efisiensi Pompa Pf = x 100% P

Keterangan :
Pf P = Efisiensi (%) = Daya fluida (watt) = Daya pompa (watt)

Seminar Kerja Praktek

15

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

ANALISA PERFORMA

BOILER FEED WATER PUMP

Seminar Kerja Praktek

16

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Discharge

Suction

Komponen Motor Kopling Pompa

Seminar Kerja Praktek

17

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Spesifikasi Pompa
Manufaktur Serial number Type : Weir Pumps Ltd : 13192-001/006 : Barrel Casing

No of stage
Liquid pump Capacity Suction temperatur Specific grafity

: 8
: Feed Water : 252 m3/h : 1570C : 0.91

Seminar Kerja Praktek

18

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Differential head Efficiency Tekanan suction Tekanan discharge Power absord of duty Speed Laju aliran minimum Diameter Nominal Suction Diameter Nominal Discharge

: 1405 m : 81.5 % : 5 bar : 165 bar : 1125 kW : 2980 rpm : 70 m3/h : 154.08 mm : 139.76 mm

Seminar Kerja Praktek

19

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Spesifikasi Motor Penggerak


Manufacture Serial number Rated Output Electrical Supply No of poles Type Temperature Rise Protection : GEC Alsthom Large Machine Ltd : J74025501-06 : 1300 kW : 6600 V, 3 Ph, 50 Hz :2 : Squirrel Cage : 80oC : IP 56

Full load current

: 147 A

Seminar Kerja Praktek

20

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Perhitungan Spesifikasi
Head Total H = (Pd Ps) g

(165 5) 105 = 1000 x 9.81 = 1630 m

Seminar Kerja Praktek

21

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Daya Fluida Pf =HQg = 1630 x 0.07 x 1000 x 9.81 = 1119 kW

Efisiensi Pompa Pf = P x 100%

= 1119 x 100% = 99% 1125

Seminar Kerja Praktek

22

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Perhitungan Sebelum Overhaul September 2011


Head Total H = (Pd Ps) g

(142.87 5.14) 105 = 1000 x 9.81 = 1403 m

Seminar Kerja Praktek

23

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Daya Fluida Pf =HxQxxg = 1403 x 0.07 x 1000 x 9.81 = 963 kW

Efisiensi Pompa Pf = P x 100%

= 963 x 100% = 85.6% 1125

Seminar Kerja Praktek

24

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Perhitungan Setelah Overhaul September 2011


Head Total H = (Pd Ps) g

(153 5.1) 105 = 1000 x 9.81 = 1507 m

Seminar Kerja Praktek

25

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Daya Fluida Pf =HxQxxg = 1507 x 0.07 x 1000 x 9.81 = 1034 kW

Efisiensi Pompa Pf = P x 100% 1034 = x 100% = 92% 1125

Seminar Kerja Praktek

26

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

Analisa Perhitungan
Dari perhitungan didapat hasil head total boiler feed water pump pada data yang diambil dari comisioning yaitu 1630 m dengan efisiensi sebesar 99%. Hal ini berbeda pada Differential Head pada spesifikasi pompa yang mungkin disebabkan karna pada perhitungan head total, head losses dianggap nol.

Sedangkan head total boiler feed water pump sebelum overhaul September 2011 dapat
diketahui sebesar 1403 m dan efisiensi pompa sebesar 85,6%. Dapat kita lihat terjadi penurunan performa pompa yang mungkin disebabkan oleh kegagalan supply listrik pada motor, vibrasi, kebocoran pada wearing ring dan mechanical seal, serta factor- factor lainnya. Sedangkan head total boiler feed water pump yang didapat setelah dilakukan overhaul adalah 1507 m dengan efisiensi pompa sebesar 92%. Dengan dilakukannya perbaikan pada komponen-komponen pompa serta clearance pompa, maka akan meninkatkan performa dari pompa boiler feed water pump itu sendiri.

Seminar Kerja Praktek

27

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

KESIMPULAN
1. Boiler Feed Water Pump adalah pompa yang digunakan untuk mengalirkan air umpan boiler yang di suplai dari deaerator 2. Dari data yang ada, maka didapat hasil sebagai berikut
Spesifikasi
Head Efisiensi Sebelum Overhaul September 2011 Head Efisiensi Setelah Overhaul September 2011 Head Efisiensi 1507 m 92% 1403 m 85.6% 1630 m 99%

Seminar Kerja Praktek

28

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

3. Pompa mengalami penurunan performa setelah lama digunakan, hal ini disebabkan terjadinya keausan komponen, getaran, kavitasi, dan lain-lain. 4. Performa tersebut dapat dikembalikan dengan dilakukannya overhaul

( penggantian komponen- komponen yang telah aus/ rusak serta perbaikan

clearance)

Seminar Kerja Praktek

29

Mechanical Engineering Department Diponegoro University


Prof. H. Sudarto, S.H Street Tembalang _ Semarang Postcode 50275 Phone. (024) 7460059 Fax. (024) 7460059

PT. PLN (Persero) Sektor Pembangkitan Ombilin

TERIMA KASIH