Saipem LIFTING AND RIGGING OPERATIONS

TRAINING COURSE No. 13

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

PRELIMINARY LIFTING OPERATIONS VERIFICATION: Weight evaluation Sling lifting point Cranes lifting capacity ( diagrams and lifting chart ) Weight ripartition (baricenter concept) Sling lifting point WEIGHT SLINGING VERIFICATION:

LIFTING AND RIGGING OPERATIONS

Lifting gear capacity Use of soft materials between sharp edge and the sling
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 2

LIFTING AND RIGGING OPERATIONS


EQUIPMENT SAFETY MAINTENANCE ASSESSMENT

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

RECOMMENDED SLING ANGLE

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

SLINGING AND LIFTING OF LOADS

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

LIFTING OPERATIONS
PRELIMINARY VERIFICATION: Presence of materials not secured Pay attention to the positions of hands & feet Knowledge of conventional crane signal

The weight must be free from obstruction and not connected to the ground
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 6

LIFTING OPERATIONS
PRELIMINARY VERIFICATION:

Presence of obstacles in the direction of the lifting.


Keep the weight close to the ground level. The chains or slings are to be free from obstacles

Tag controlling line must be used.

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

LIFTING OPERATIONS
PRELIMINARY VERIFICATION:

Horseplay or standing on lifted weight is forbidden.


The crane operator must follow the banksman indication during the lifting operations.

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

LIFTING OPERATIONS
SHIFTING OF LOAD

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

SLINGING AND LOADS LIFTING

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

10

CHOKER HITCH

THE CHOKER HITCH IS OFTEN USED WHEN GRIPPING THE LOAD & WILL IMPROVE LOAD CONTROL.THE THE CAPACITY CAPACITY OF A OF A CHOKER HITCH IS CHOKER HITCH IS 75%TO 80% OF BASED ON THE HITCH THE SINGLE BEING PROPERLY LEG. FORMED. IN OTHER CHAIN, WIRE FOR THE FULL CHOKER ROPE AND CAPACITY TO BE SYNTHETIC SLINGS ARE AVAILABLE, THE ANGLE AFFECTED OF CHOKE FOR ALL TYPE OF SLINGS SHOULD BE AT LEAST 120
11

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

LIFTING OPERATIONS
PRELIMINARY VERIFICATION:

presence of obstruction in the working area.


weight landing area clearly defined. dont keep the load suspended. good stacking position ( pipe). slowly raise the weight.

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

12

LIFTING OPERATIONS
LOWERING OF LOADS

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

13

CALCULATION OF MATERIALS WEIGHT

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

14

CALCULATION OF MATERIALS WEIGHT

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

15

CALCULATION OF MATERIALS WEIGHT


CONVENTIONAL WEIGHT OF MATERIALS
MATERIALS
STEEL WATER AT 4 DEGREE C' ASBESTOS BRONZE CONCRETE ALLUMINIUM IRON CAST IRON WOOD NICHEL BRASS STONE LEAD COPPER SAND TIN ZINC

MEASURAMENT UNIT
ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER ONE CUBIC METER

WEIGHT IN KG.
7600 - 8100 KG. 1000 KG. 2100 - 2800 KG. 7500 - 8300 KG. 2200 - 2500 KG. 2800 KG. 7400 - 7900 KG. 7000 - 7800 KG. 760 - 950 KG. 8900 - 9200 KG. 8500 - 8600 KG. 3000 KG. 11200 - 11300 KG. 8600 - 8900 KG. 2000 KG. 7300 - 7500 KG. 7200 KG.

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

16

CENTER OF GRAVITY AND SLING LOADING


SLING 1 SLING 2

10000kg

WHEN LIFTING VERTICALLY,THE LOAD WILL BE SHARED EQUALLY IF, THE CENTRE OF GRAVITY IS PLACED EQUALLY B/W THE PICK POINTS.IF THE WEIGHT OF THE LOAD IS 10000Kg, THEN EACH SLING WILL HAVE A LOAD OF 5000Kg. EACH SHACKLE AND EYE BOLT WILL ALSO HAVE A LOAD OF 5000Kg.

D1=5m

D2=5m

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

17

CENTER OF GRAVITY AND SLING LOADING


THE LOCATION OF THE CENTRE OF
SLING 1 SLING 2

GRAVITY RELATIVE TO THE PICK POINTS IS A

VERY IMPORTANT
10000kg

CONSIDERATION

D1=5m

D2=5m

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

18

CENTER OF GRAVITY AND SLING LOADING


WHEN THE CENTRE OF GRAVITY IS NOT EQUALLY SPACED B/W THE PICK POINTS, THE SLINGS AND FITTINGS WILL NOT CARRY AN EQUAL SHARE OF THE LOAD. THE SLING CONNECTED TO THE PICK POINT CLOSEST TO THE CENTRE OF GRAVITY WILL CARRY THE GREATEST SHARE OF THE LOAD. SLING 2 IS CLOSEST TO C.O.G,IT WILL HAVE THE GREATEST SHARE OF LOAD: SLING2=10000 X 8/(8+2)=8000kg
D1=8m D2=2m

SLING 1

SLING 2

10000kg

SLING1=10000 X 2/(8+2)=2000kg
19

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

THE RIGGING TRIANGLE AND THE WORKING LOAD LIMITS OF RIGGING GEAR
ALL ADD TO 180 DEGREES

INCLUDED ANGLE
VERTICAL SLING ANGLE

IN MOST LIFTS, ONLY A SINGLE HOOK IS AVAILABLE. THIS MEANS THAT MULTIPLE LEG SLINGS MUST BE COLLECTED AT THE LOAD HOOK. WHEN THIS IS DONE, WE FORM WHAT WE CALL A RIGGING TRIANGLE. THE INCLUDED ANGLE IS CHECKED FOR PROPER CONNECTION OF HOIST HOOK OR COLLECTOR RING. THE SLING ANGLE MUST BE KNOWN TO PROPERLY SELECT SLINGS AND FITTINGS AT THE LOAD CONNECTION.

HORIZONTAL SLING ANGLE

HORIZONTAL SLING ANGLE

LOAD

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

20

THE RIGGING TRIANGLE BASIC FACTS


SIDE LOADING CAN OCCUR AT LOAD. SLING LENGTH AFFECTS HORIZONTAL SLING ANGLE. 30 VERTICAL SLING ANGLE IS BEST, 60 IS WORST. AS VERTICAL SLING ANGLE BECOMES LARGER, THE LOAD IS CRUSHED AND SLINGS WORK HARDER. THE FITTINGS AT LOAD CONNECTION SEE SAME LOAD AS SLING.

WHEN COLECTED AT THE HOOK OR COLLECTOR RING, SLINGS PLACE A SIDE LOAD ON THE EYE BOLT OR LIFTING POINT AT THE LOAD.

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

21

THE RIGGING TRIANGLE 30 DEGREE VERTICAL SLING ANGLE


YOU HAVE A 30 (OR SMALLER) VERTICAL SLING ANGLE WHEN:

LENGTH OF SLING

LENGTH OF SLING (INCLUDES SHACKLE) IS EQUAL TO OR LONGER THAN DISTANCE BETWEEN PICK POINTS

TAPE

AS THE SLING LENGTH IS SHORTENED, THE VERTICAL SLING ANGLE IS INCREASED AS THE SLING LENGTH IS INCREASED, THE SLING ANGLE IS DECREASED.

DISTANCE BETWEEN PICK POINTS 2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 22

DO NOT EXCEED 90 DEGREES.

THE INCLUDED ANGLE HOIST HOOKS


NEVER FOUL THE LATCH OF ANY HOOK, CARE MUST BE TAKEN WHEN PLACING SLINGS INTO HOOK. NEVER FOUL A LATCH BY ALLOWING THE SLING TO BEAR AGAINST THE LATCH.

THE WORKING LOAD DEPENDS ON IT AND THE SLINGS SIT IN THE BASE OF THE HOOK AND CLEAR OF THE

LATCH.

INCLUDED ANGLE: 90 DEGREES MAXIMUM

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

23

THE VERTICAL SLING ANGLE LOAD MULTIPLIER


EACH SLING SEES 1/2 OF WEIGHT. PLUS CRUSHING LOAD

AS THE VERTICAL SLING ANGLE BECOMES GREATER, THE SLINGS AND FITTINGS AT THE LOAD CONNECTION WORK HARDER. THE SLINGS ALSO PLACE MORE CRUSHING FORCE ON THE LOAD.

AS VERTICAL SLING ANGLE BECOMES LARGER, THE CRUSHING LOAD GOES UP.
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 24

THE VERTICAL SLING ANGLE LOAD MULTIPLIER


SLING LOAD= VERTICAL LOAD X FACTOR 30 1.155 45 1.414 60 2.0 80 5.789 ANGLE GREATER AS THE SLING ANGLE APROACHES 60,THE MULTIPLIER INCREASES SIGNIFICANTLY. ABOVE 60 THE MULTIPLIER INCREASES EVEN MORE DRAMATICALLY. NEVER ALLOW A VERTICAL SLING THAN 60.

(1.2)

(1.4)

(2)

(6)

SLING LOAD= VERTICAL LOAD X L/H

10
2/7/2013

30

45

60 DEGREES
25

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

THE VERTICAL SLING ANGLE L/H AND LOAD MULTIPLIER


IN THE RIGGING TRIANGLE, IF YOU TAKE THE LENGTH OF THE SLING,( BEARING POINT TO BEARING POINT) AND DIVIDE BY THE DROP, YOU HAVE THE LOAD MULTIPLIER.

L H

L/H = LOAD MULTIPLIER

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

26

MEASURE THE VERTICAL SLING ANGLE BY USE OF L/H


THE USE OF L/H OFFERS US SEVERAL TOOLS THAT CAN BE USED IN RIGGING. THE MOST BASIC TOOL IS THAT THE SLING ANGLE CAN BE MEASURED BY USE OF A TAPE MEASURE.

IF L/H
1.155 (1.2) 1.414 (1.4) 2

VERTICA ANGLE
30 DEGREES 45 DEGREES 60 DEGREES

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

27

CALCULATE THE LOAD IN EACH LEG BY USE OF L/H


L H
A MORE POWERFUL TOOL IS THE USE OF L/H TO CALCULATE THE LOAD IN EACH SLING LEG AND IN THE FITTING AT THE LOAD CONNECTION. REMEMBER THAT THE LOAD MULTIPLIER INCREASE THE VERTICAL LOAD(THE LOAD IF THE SLINGS WERE PULLING STRAIGHT UP).
28

10000kg
IF L/H 1.2 1.4 2 THEN LOAD 1.2 X 5000=6000 kg 1.4 X 5000=7000kg 2 X 5000=10000kg

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

DETERMINE CAPACITY OF BRIDLE IF ANGLE DIFFERENT FROM THAT ON TAG


IF VERTICAL SLING ANGLE IS GREATER THAN THE ANGLE INDICATED ON THE TAG, THE SLING CAPACITY

MUST BE DERATED

CAPACITY= CAPACITY ON TAG X L/H FOR ANGLE ON TAG L/H FOR ACTUAL ANGLE

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

29

LIFTING CAPACITY VARIATION RELATED WITH THE SLINGS ANGLE

LIFTING AND RIGGING OPERATIONS

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

30

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

31

LIFTING OPERATIONS
METALLIC WIRE AND CABLE

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

32

HOISTS HOOKS LATCH REQUIREMENTS


ANSI\ASME REQUIREMENTS HOOKS SHALL BE EQUIPED WITH LATCHES LATCH EQUIPPED HOOKS SHALL BE USED PERSONNEL BASKETS AND LOCKING LATCHES-OSHA HOOKS SHALL BE OF TYPE THAT CAN BE CLOSED AND LOCKED

HOOKS ON CHAIN FALLS, BLOCKS, BLOCK AND TACKLE AND HOISTING WINCHES MUST HAVE LATCHES.

WHEN USED IN PERSONNEL LIFTING, THE LATCHES LOCKING METHOD MUST BE ENGAGED.
33

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

LIFTING OPERATIONS
SLINGING REMOVAL AND HOOK RAISING

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

34

LIFTING AND RIGGING OPERATIONS


SLINGS, CHAINS & LIFTING GEAR VERIFICATION OF METALLIC SLINGS WHEN IS IT REQUIRED TO REPLACE THE SLING ?

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

35

LIFTING AND RIGGING OPERATIONS


CAUSES OF SLINGS BREAKING: Overloading Bending on shape edge Reductions of resisting sections (wire broken). Wire squeeze Wire eccessively worn
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 36

METALLIC ROPES BREAKING CAUSES AND MAJOR DAMAGE

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

37

LIFTING OPERATIONS
SLINGS, CHAINS & LIFTING GEAR WORK HARDENING WEAR LOOSE WELDING

FLESSION ACTIONS
YIELD
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 38

CHAINS LIFTING CAPACITY REDUCTION RELATED TO THE WORKING ANGLE

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

39

LIFTING OPERATIONS
NYLON AND TEXTILE ROPES

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

40

LIFTING OPERATIONS - HOOKS

2/7/2013

Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH

41

LIFTING OPERATIONS
CLAMPS AND PULLEY SECTION

DISTANCE

DIAMETER OF THE BOLT


2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 42

LIFTING AND RIGGING OPERATIONS


COMMON INJURIES HAPPENED AT THE RIGGERS: Squeeze ( at finger, feet & hands ). Abrasion, cutting, prick. Contusion in some part of the body. Falling from elevation.
2/7/2013 Saipem / HSE DEPARTEMENT / TR SCO / SC / FP / PH 43

LIFTING OPERATIONS