Total Total
Production Placement
Average
Capacity, Total Capacity, Total
of pour
of Production of Placement
Description in
Sr.No. Concrete, Capacity, Concrete, Capacity, Remarks
of location Cubic
put to use % age put to use % age
meter
in Cubic utilization in Cubic utilization
per hour
meter per meter per
hour hour
Work
carried
TG Raft
1 110 30.15 60 55.28 33.17 out by
Unit No.5
M/s
GDC
Work
TG Raft carried
2 120 33.93 100 40.72 40.72
Unit No.6 out by
M/s SIL
Work
TG Raft carried
3 120 38.02 100 45.63 45.63
Unit No.8 out by
M/s SIL
Work
Boiler carried
4 Foundation 110 21.11 60 38.70 23.22 out by
Unit No.5 M/s
GDC
Work
Boiler carried
5 Foundation 110 29.72 120 27.24 32.69 out by
Unit No.7 M/s
GDC