Anda di halaman 1dari 283

‫للمواصلة مع المؤلف‬

saidnaggar@hotmail.com
said.najjar@dargroup.com
‫البريمافيرا‬

‫تأليف‬

‫م‪ .‬سعيد النجار توفيق‬


‫ماجســـتير إدارة مشـــــــــــــروعات‬
‫انباب‬
‫األول‬

‫انهيكم انتنظيمى ( ‪ )WBS‬انتقارير‬


‫انخاصة بانبرنامج‬

‫‪WBS‬‬

‫‪Report Writer‬‬

‫‪Matrix Reports‬‬

Work Breakdown Structure


WBS
WBS Activity Codes

WBS) 
WBS 



WBS Activity Code 
36 

WBS
Work Breakdown Structure



Planning
Scheduling
Budgeting
Cost Accumulation

Performance Reporting

WBS
20 
10 
48

Period . 1 

WBS

Scope of work 

Organize By WBS 

37  WBS

WBS 
WBS 

Work Breakdown Structure


2 1

Work Package

WBS
1

Subproject 1 - Subproject 2 - Subproject 3 ......etc.)


Work Package 2

4
38 

WBS

WBS
1
2

50

WBS
WBS

Activity ID Activity Description


39  WBS

Activity ID Activity Description


M El-Manar Tower
M.A Soil Works
M.A.01 Excavation
M.A.02 Filling up
M.B P.C.
M.C R.C.
M.C.07 R.C. Foundation
M.C.09 R.C. Columns
M.C.10 R.C. Slab
M.H Handing Over

M
El-Manar Tower

M.A M.B M.C M.H


Soil Works Plain Concrete Reinforced Concrete Handing Over

M.A.01 M.A.02 M.C.07 M.C.09 M.C.10


Excavation Filling Up R.C. Foundtion R.C. Columns R.C. Slab
40 

WBS

WBS Data 1
41  WBS

WBS
dictionary

WBS dictionary

Work Breakdown Structure 2

Width 1 3
1

Separator 1 4
0 1 0
42 

Width 2 5

Work Breakdown Structure 7

WBS Dictionary
Ctrl M.A.01 8
43  WBS

M.A M.A.01
M

Title M 8

El-Manar Tower
Ctrl

Title M.A 9

Ctrl Soil Works


10
44 

M.A.01 11

M.A.02 M.A.01

WBS Dictionary M.A.02 12

Title M.A.02 13

Filling Up
45  WBS

M.A 14

M.B.02 M.B.01 M.B


M.C M.B 15
16
46 
47  WBS

WBS
WBS

WBS Data 1

WBS 2

WBS

3
48 

WBS

WBS

WBS 5

WBS
WBS 1
49  WBS

WBS

WBS 3
50 

Print File 4
51  WBS

Activity From 

WBS Form 
Activity Columns 
Global Change 

WBS
Activity Form

Activity Form F7 1

Type WBS

WBS 2

WBS
52 

M.A.01 3

WBS Formwork For P.C. Foundation


WBS
5

M.B )
WBS 6
53  WBS

WBS
WBS

Activity Detail 2

WBS

WBS 3

WBS
M.A.01 4
54 

WBS 6

WBS
7

M.B
WBS 7 6 5 8

WBS WBS 9

WBS
Close

WBS
Activity Columns
Activity Columns WBS

Activity Columns WBS


Activity Columns WBS
Columns Columns Format 1
55  WBS

WBS 3

WBS

Fill Cell WBS


WBS 1
56 

M.A.01

WBS 4

M.B
Shift 6

WBS

WBS
Copy M.B

Copy M.B Fill Cell Edit 7


57  WBS

WBS 8

M.C.07

Shift 9

Copy M.C.07 Fill Cell Edit 10

11
58 

WBS
Global Change

Global Change Tools 1


59  WBS

2
9

Global Change 3
60 

Reassign WBS Structure 4

Change 5

IF
Data Item 6

Activity data
Item Number

EQ Criteria 7
61  WBS

Data Item /Value 8

07. Values

Then
Data Item 9

WBS
EQ Criteria 10

Data Item /Value 11

M.C.07 Value
62 

GChange 12

13
63  WBS

14

WBS

WBS 15
64 

WBS

WBS

WBS
65  WBS

WBS
Organize Format 1

Activity data Item Organize

WBS Work Breakdown 2


66 

Level 1
Visible 3

( Font) 4

Aerial 14 , B )

Bkgrnd 5

WBS
67  WBS

Text 6

WBS

New Page 7

Total 8

9
68 

Total float Early Start 10

Sort by
TF Early start
Total Float Early Start

12

Total Float Early Start WBS


69  WBS
70 

(Bar)
71  WBS

(Bar)
72 

(Bar)
73  WBS

WBS Activity Code


Transferring Activity Dictionary to WBS Code Dictionary

Activity Code 5
FS = 0 1

Activity Codes Data 2

Activity codes 3
74 

Activity Codes 4
75  WBS

Activity Codes 5

WBS Data 6
76 

WBS 7

WBS Activity Code

Global Global Change Tools 8

Change

Global Change 10
77  WBS

11

Transferring Activity Code To WBS


Change
Change 12

Change

Then
Data Item 
&TMP
EQ Criteria 
COD1 Data Item /Value 
Operation 
&
&
Data Item/Value 
COD2
78 

Data Item 
&TM2
EQ Criteria 
Data Item Value 
&TMP
Operation 
&
&
Data Item/Value 
COD3

13

GChange

14
79  WBS

Global 15

Change
16

17

Columns Format 18

19
80 
81  WBS

Activity Code 10
Activity Codes 9
10

Custom Data Items Data 1

Custom Data Items Dictionary 2

Activity

4
82 

Activity Codes

Global Change
Custom Data Item 8
83  WBS

WBS 9

WBS Activity Code

10
84 

11

Global Change
Columns Format 12

13
85  WBS
86 

Activity Code 10
Activity Codes 5
10

Custom Data Custom Data Items Data 1

Items Dictionary
2

Global Change
87  WBS

Custom Data Item 6

Global Change
Custom Data Item 9
88 

WBS 10

WBS Activity Code

11
89  WBS

12

Global Change
Columns Format 13

14
2

Report Writer

Report Writer 
Report Writer 
Primavera Look 



628 

Report Writer

Report Writer







629  Report Writer

Tabular Reports Tools 1


Report Writer

2
630 

Report Writer Reports

3
14

Add a New Report 4


631  Report Writer

6 5

Arithmetic
632 
633  Report Writer

Selection 
Selection
selection

Pouring and Steelfixing Activities 6

Select If 7
Type of Work

Is 8

EQ

300
634 

Select If 10
Type of Work

Is 11
EQ

12
500
635  Report Writer

Resource Selection 
Resource Selection
Resource Selection

13

Selection
636 


Res Selection

Selection


Res Selection

Selection
637  Report Writer

Content 
Content
Content

Data item 14
Activity data Data Item

ACT

ACT
638 

Column #
15

16

17

18

19
639  Report Writer

Yes

20

Data item 21
Activity data Data Item

OD

22
640 

23

99

24

Data Item
Data Item

Activity Data

Constraints

Resource/ Cost
Data
641  Report Writer

Target data

Comparison Data
(Target) (Current)

(Current) Variances
(Target)

Global Data
642 

Headings 
Heading
Heading

SAID EL- NAGGAR Header 25


643  Report Writer

Row 26

Align 27

L
R
C

28

29
Row

30
Align
R -L -C
644 
645  Report Writer

Format 
Format
Format

31

32
None
646 

Resp

{ } 33

B.O.Q.
647  Report Writer

34

None

35

36
648 

37

None 38
BOQ
649  Report Writer

39

40

Calendar Dates 41

DDMMMYY Calendar Dates

Workperiods
650 

Ordinal Dates

Manufacturing
96-01 Dates

42
500 230 132 80

43
651  Report Writer

44

45

46

TF ES 47
652 

ES
TF

TF Ascend
0

TF Dsecnd
653  Report Writer

Arithmetic 
Arithmetic Arithmetic

IF : THEN : ELSE 48
IF
THEN
IF
ELSE
IF

) TF EQ 0 IF
654 

OD = OD + 2 THEN

OD = OD - 2 ELSE

TF = 0
2 THEN
ELSE

49

50
Primavera Look
655  Report Writer


656 

Primavera Look
Look Save File 1
WW_PS 2
Close File Look 3

Tabular Reports Tools 1


Report Writer

4
Primavera Look
657  Report Writer

Tabular Reports Tools 1


Report Writer

Report Writer Reports 3

4
Transfer 14

6
658 

15 14 7
Soil Works 8
Title Activities

Selection 9

10

11

12
Primavera Look
659  Report Writer


660 

OD

Tabular Reports Tools 1


Report Writer
Report Writer Reports

2
Add a New Report

Content
Data item 3
Activity data Data Item

ACT

OD DES 4
ADUR

) &DV Data item 5

Temporary Variables

4 
ampersand)
3
ELSE or THEN 
661  Report Writer

Arithmetic
&DV Then Item 7
EQ Then Code 8
Then Item/Value 9
Activity
OD data

Then OP 10

Then Item/Value 11
ADUR Activity data
662 

12

13
Primavera Look
663  Report Writer


664 
665  Report Writer


666 

Arithmetic
3

Matrix Reports
Matrix


Activity Matrix Reports 


Resource/Cost 
Matrix Reports

672 

Matrix
Tabular Reports Tools 
Matrix

 

Activity

Resource/Cost
673  Matrix

Activity Matrix Reports

ES-EF
Type of Work
BOQ

Tabular Reports Tools 1


Matrix
Activity
674 

Activity Matrix Reports


675  Matrix

3
10

Add a New Report 4


676 

Content

Plain Text Rich Text


677  Matrix

Content 
Content
Content

6
Early Dates for TOW (Type of Work)Activities

Report on Data Items


Report on Data Items 7
Activity Matrix Reports
Early Dates Activity data
678 

Activity Matrix Reports


Activity Matrix Reports

Activity Data

Constraints

Resource/ Cost data

Target data

Comparison Data
(Target) (Current)

(Current) Variances
(Target)
679  Matrix

Variances

Organization 8
Group Rows by 

BOQ

Subgroups Rows by 
680 

BOQ

BOQ

Group Columns by 

TOW
681  Matrix

Headers
(Column1 (Code Value 9

100 Formwork or Shuttering

(Column1 (Code Value 10


100 Formwork or Shuttering
Formwork or
Shuttering
682 

11

25

12
683  Matrix


684 

Selection 
Selection
selection

13

Select If 
Item Number
Is 
EQ


09.
685  Matrix


2

3
(Description)
Foundation
686 

Format 
Format
Format

14

15
500 132

16

15 5
687  Matrix

17

Left 18

Right 19

20
1000
10000 10 10000
688 

21

Calendar Dates

Ordinal Dates


DDMMMYY
689  Matrix


690 


96-01
691  Matrix

22

23

24

25
Primavera Look
692 

Tabular Reports Tools 1


Matrix
Activity

Activity Matrix Reports 3

4
Transfer 10

10 7
11
693  Matrix

Early Dates For Critical Activities 8


Title

Selection 9

10

11
Primavera Look
694 

ES
4


WWW World Wide Web 
Web Publishing Wizard 


716 

Publishing Reports on the World Wide Web

World Wide Web


Internet World Wide Web
WWW Internet
The Web W3

Internet

Internet
Archie FTP
Wais Gopher
Jurassic Park

Hyperlinks

400
717 

Pink Floyd

World Wide Web

Host Computer

Documents Hypertext

Windows Help
718 

Internet World Wide Web


Internet
Web Server

Internet
links

Home Page

Internet
719 

1989
CERN
Internet
HTML Hypertext Markup Language
HTML Links

World Wide Web


720 

1
Byte 2
721 

Web Publishing Wizard


Web Pages Web Publishing Wizard

Netscape Navigator

Interanet 
WWW

Server
P3 
Hyper Text Markup Language
722 

The Web Publishing Wizard


Wep

Web Publishing Wizard Tools 1

2
723 

Primavera Web Publishing Wizard

Primavera Web Publishing Wizard

Categories
724 

4
725 

6
Said
726 

Cairo Projects
Towers

7
Towers

8
727 

El-Manar Company 9

.IPG .GIF
728 

10

11
729 

12
Towers

13
Towers SAID

14
SAID

15
730 

SAID

16
731 

17

18
5
732 

Classic Schedule 19
Filter

Tabular

Add a p3 Tabular Report 20

Steel Loading Report

.PDF-.TXT-.WAV
733 

21

22

23
734 

24

25
Web Browser
735 

Tower 26

Tower

27

SAID
736 

28
737 

Projects Categories
738 


739 
740 


‫الباب‬
‫الثانى‬

‫إدارة التكلفت‬

Auto cost Rules


Cost Accounts Categories
Cost Reports
1 

delays
accelerations
Extra Works
Claims
4

feed Back )

Process

Aim Or objective 1
2

Progress of works
2 

End forecast 3

control
3 

( Method st, ) 
Feed back ) ( Resources) 

( Revised Bill ) 

( Budget ) 
( Cash Flow) 




4 

Types of Cost

Once-Only costs

Mobilization And Demobilization


Time- Related costs

( Activity-Related )
5 

Cost control

1
2
3
4


( Revised Bill ) B. O. Q

2
( Organization )
( Site Lay- out )
( Method statement )

3
6 

Contract price = Direct Cost ( Contract Items ) + site + Company OH + profit

Cash flow 6
7

End forecast
8

Site Over Head


1

Autocost Rules






2 

Autocost Rules




The Standard Cost To 
Differently Then Complete



ETC = UPT * RD
EAC = ETC + ATD

RD
UPT
ETC
ATD
EAC
3 

Options Tools 
Autocost Rules
4 

Autocost Rules

Autocost Rules
5 

Rule 1

RD

60 % = PCT And 10 = OD

PCT = 60 %
RD = 40/100 * 10 = 4


PCT = 60 %
5 RD

RD
6 

PCT PCT

Rule 2


RD

Quantity to complete = Unit per timeperiod x Remaining duration


or
Unit per timeperiod = Quantity to complete / Remaining duration

Rule 3


EAC
EAC = ETC + ATD ETC ATD

VARIANCE = BUDGET EAC


7 

ETC
ETC = EAC + ATD


ETC

Rule 4
8 

3000 10 Budget

0 0 Actual to Date

3000 10
Estimate to Complete
9 

3000 10 Budget
1800 6 Actual to Date
1200 4 ETC

Unit Price x Budgeted Quantity = Budgeted Cost


Unit Price x Actual Quantity = Actual Cost
Unit Price x Quantity to Complete = ETC
Cost to Date + Cost to Complete = EAC

Rule 5


AQD = PCT * Resource Budget
ACD = PCT * Budget Cost

4 5 4
5
x
Rule 6
10 

Actual This Period Actual To Date


Actual This Actual To Date
Period

Rule 7
11 


EAC 

Budget EAC 10 8
EAC Budget Quantity Quantity

Budget Quantity EAC


12 

Rule 8


Positive Variance = EAC - Budget
Negative Variance = Budget - EAC
13 

P3

P3

Non Linear
Expected Hammocks
Finish Constraint

Apply by Resource 


Apply By Cell 


14 

Autocost Options Tools 1


Rules

2
Transfer
3

5
15 

Autocost Options Tools 1


Rules
Automatic Cost/Resource calculation Rules for Said

3
2

Cost Account & Categories

Cost Account 
Cost Categories 

Activity Table Cost Account 




2 

Cost Account

Cost Categories

Code Category Title

O Others
E Equipment
M Material
S Sub_Contractor
P Purchase Order
T Trends/Division
C Change Order
L Labours
gf

Cost Accounts Data 1


3 

Cost Accounts Dictionary

Cost Accounts Dictionary


4 


Cost Accounts Data 1

Cost Accounts Dictionary

Categories

Titles

Categories 2

Code L
Ctrl
5 

Category Title 3

Ctrl Labours L

Categories 4

Ctrl Code M
M Category Title 5

Material M
Ctrl

Cost Accounts
Dictionary

5 4 6


6 

Account Account Title


#
10 El-Manar Tower
101 Concrete
1011 Concrete - R.C.
10111 Concrete - R.C Foundation
10112 Concrete - R.C . Columns
10113 Concrete - R.C . Slab
1012 Concrete - P.C.
10123 Concrete - P.C. Foundation
102 Soil Works
1021 Soil Works - Filling up
1022 Soil Works - Excavation
103 Handing Overfds

Titles 1

Titles Account #

Ctrl 10 2

Account Title 3

El-Manar Tower
Ctrl

Titles 4

Ctrl 101 5

101 Account Title 6

Concrete
Ctrl
6 4 7
7 

Cost Accounts Data 1

Transefer

3
8 

1
9 

3
10 

Activity Form 
11 

( activity Cost Form ( activity Resource Form


( Activity Budget Form
Activity Columns 
Global Change 

Activity Form

Activity F7 1

Form

Ctrl + R
Resource Activity Detail View
Resources 3
12 

Loader 4

1022
6

Resources

Ctrl Equipment E

Resource 7
13 

Sand 8

M 10123
Ctrl Material

Gravel 10

11

M 10123
Ctrl Material

11 10 12

13
14 

Cost 
Activity Form F7 1

Ctrl + T
Cost Activity Detail View
Resources 3

Loader 4

1022 5
6

Equipment E Resources

Ctrl
7
15 
16 

Budget 
F7 1

Activity Form

Ctrl + B
Budget Activity Detail View
Budget Summary 3

Resource
Units

Cost
17 

Cost

3 Total Units

Total Cost

(Cost Acct/Category) 4

Budget Summary

10123
M 7

Ctrl
(Cost Acct/Category) 8

Budget Summary

9
18 

Change Global

Global Change Tools 1

3
9 4

Global Change 5
19 

Reassign Cost Account 6

Change 7

IF
Data Item 8

Item Number

EQ Criteria 9

Data Item Value 10


20 

“07” Value 11

Then
Data Item Then 12

ACC

EQ Criteria 13

Data Item Value 14


21 

10111 Value 15

GChange 16

17

18

ACC
22 

Activity Table Cost Account


Activity Table Cost Account
Cost Accounts
Columns Columns Format 1

Cost Account 11 4

Cost Account 11

ACC
23 

ACC 7

ACC 8
24 
25 

Global Change

Global Change Tools 1

Global Change

2
9 3

Global Global Change 4

Change
Reassign Cost Category 5

Change
IF
Data Item 6

Resource/Cost Data
Resource

EQ Criteria 7

Data Item Value 8

Value
Steefxr
26 

Carpntr- PourCrew 10

Then
Data Item Then 11

CAT )
27 

EQ Criteria 12

L Value Data Item 13

IF L

GChange 14

15

16

17
28 
29 

4
4 4

4
30 
31 

E 

1
32 

Organizing Activities By Cost Account or


Cost Category

Organize

Organize

Activities Codes - Coding ID -..etc.


Resource / Cost Accounts
Dates
Float
Calendars

Cost Account 12 Cost Account 11

11 Cost Account 11

11 Cost Account 12
12

Organize Format 1
33 

Organize 2
34 
35 

Cost Accounts Data 1

Cost Accounts Dictionary

2
3

4
5

6
7
36 

Global Change
Global Change Tools 1

3
9 4

Global Global Change 5

Change
Delete Cost Categories 6

L
Change
IF
Data Item 7

Resource/Cost data
ACT
37 

EQ Criteria 8

Data Item Value 9

Then
Data Item Then 10

ACT
EQ Criteria 11

Data Item Value 12


38 

GChange 13

14

15

16

(M
39 

(E
40 
41 

Global Change
Global Change Tools 1

3
9 4

Global Global Change 5

Change
Delete Cost Categories 6

Change
IF
Data Item 7

Activity data
Bill of Quantities
42 

EQ Criteria 8

Data Item Value 9

Value 10

C.

Then
Data Item Then 11

ACC
EQ Criteria 12

Data Item Value 13


43 

GChange 14

15

16

17
44 

Selection WR Change
WR
Selection
45 

Change

Cost Account (12


ACX
ACC
46 

Filter)
Primavera Filtration 1

Filter
M
Filter Format 1

Filter 3

( FL-14 ) Filter 4

Filter Specification 5

Material Activities Filter 6

(Selection Criteria) 7

(Schedule Parameters)
8

Cost Account Category


47 

( Is ) 9

EQ - Equal To 10

Low Value 11

12

High Value - Low Value


WR
48 

Filter 13

14

Replace activities shown


in current view
Add activities to the
current view
Remove activities from
the current view
49 

Filter 9

Cost M
L-S-P-E-… Category
M
50 
3
Cost Reports

Cost 

Cost Loading Report

Cost Control Reports 

Earned Value Report 

Cost, Price and Rates Reports
Tabular Cost Report 
Primavera Look 

2 

Cost

Tabular Reports Tools 


Cost
Cost Reports

 

Control

Cost Price and Rates

Earned Value
Tabular
Loading

Cost Loading Report


3 


Tabular Reports Tools 1

Cost
4 

Loading 2

Cost Loading Reports


5 

3
3

Add a New Report 4

Res Selection

5
6 

Text Rich Text Plain


7 

Res Selection 
Res Selection
Res Selection

Steel Cost Loading Report 6

(Res Selection 7

EQ-Equal To

Steel
8 

Res Selection 

Selection 

Selection

NE GT EQ LT 

Res
Selection

Selection

WR NR 

Res Selection
9 

Selection

LOADER CARPNTR
CEMENT - ENGINER - GRAVEL - CARPNTR
LOADER
10 

Wildcard 
1

101

Selection 1

Res Selection 2

1011
1012

Selection 1
11 

Res Selection 2


Wildcards 
EQ 
12 

Selection 
Selection
selection

10112 10113
Select If 10

Cost Account (11)

Is 11

WR

12

10112
13 

13

10113

10113 10112
14 

Format 
Format Format

14

15

Resource 
15 

Activity ID 
Activity ID

Cost Account (11) 


16 

Cost Account Category 

Cost Account (12)


17 


18 

16

Type of Work - Bill -

Type of work
19 

17

18
20 

19

20
500 132

21
15 5

22
1000
8000 8 8000

23

24

Left
21 

Right

TF ES 25
22 

ES

Total Float

0 Ascnd

Dscnd
23 

Timescale 
Timescale
Timescale

26


24 

Total

Peak
Average

27
25 

28

Primavera Look
26 

Primavera Look
Look Save File 1

Steel-CL 2

Close File Look 3

Tabular Reports Tools 1

Cost
2
3

4
5

Primavera Look

Tabular Reports Tools 1

Cost
2

Loading
27 

Cost Loading Reports

Transfer 3 6

SAID 7

4 3 9

Cement Cost-Loading Report 10

Title
28 

Res Selection 11

12

13

14

Primavera Look
29 

Cost Loading - Summary By Cost Accounts

Format
30 

Cost Loading - Detailed by Week

Format

Timescale
31 

Cost Control Reports




Forcasted Actual Budget 

Budget - Actual - Forecast

Tabular Reports Tools 1

Cost

Control 2
32 

10 3

Add a New Report 4


33 

Res Selection 
Res Selection
Res Selection

Steel Cost Control Report 5

(Res Selection 6

EQ-Equal To 7

Steel 9
34 
35 

Selection 
Selection
Selection

10

10111
10112
Select If 11

Cost Account (11)

Is 12

WR

13

10111
36 

14

10112

10111
10112
37 

Format 
Format Format

15


Activity ID 


38 

17

18

TF ES 19

20
39 

21

Primavera Look
40 
41 

Cost Control - Summary By Activity

Format
42 
43 


44 

Cost Control - Detailed by Resource

Format
45 


46 
47 

Cost Control - Summary By Cost Accounts

Format
48 
49 


50 

Cost Control - Detailed Roll Up of Costs

Format
Res Selection
51 


52 

Cost Control - Detailed Roll Up of Costs

Format

Res Selection
53 


54 
55 

Earned Value Report


BCWP
ACWP BCWS

10113 10111


Tabular Reports Tools 1

Cost
56 

Earned Value 2

2 3

Add a New Report 4


57 


58 

Res Selection 
Res Selection
Res Selection

Steel Earned Valur Report - Cost 5

(Res Selection 6

EQ-Equal To 7

Steel
59 


60 

Selection 
Selection
Selection

10

11

Primavera Look
61 


62 

SADT 1

SADT 2

1996 15 Data Date

100 1996 8 1996 1 A.01.000


100 1996 20 1996 7 B.03.100
100 1996 24 1996 20 B.03.500
100 1996 1 1996 30 B.03.700
60 1996 2 C.07.100
40 1996 8 C.70.400

4
63 

Anda mungkin juga menyukai