INTRODUCTION Information Technology has changed the way we live. Mining is no exception. Mining information systems have emerged encompassing all aspects of mine planning. Real time analysis of data is now possible that helps the mine administration to function effectively. Software is now available that covers the entire gamut of mine functions. The Singareni Collieries is now ahead in utilizing the computerized mine planning and completed design & scheduling of an opencast project on long term planning module Apollo of Minex software.
FEATURES: Minex is an integrated modular software including Survey, deposit evaluation, mine planning and design, production scheduling and equipment simulation. The user has the flexibility to select modules as per requirement. Generation of Borehole database Generation of reliable Geomodel 3D visualization of seam horizons/faults Generation of Reserves Database Pit Optimisation Open Pit Design and Scheduling Design of Haul roads, Earth works and Spoil dumps Underground mine planning and scheduling Generation of Mine Reserves Database Production Scheduling by target or equipment Generation of Plans, Sections and reports
1. Chief General Manager, 2. Dy. Supdtg. Er, 3. Sr. Survey Officer, The Singareni Collieries Company Limited (A government Company), Kothagudem, Andhra Pradesh., INDIA * 4. Under Manager Now working at Surpac Minex, Hyderabad, INDIA
Singareni Collieries
Page 1 of 18
A project is taken up at Singareni Collieries to design a pit, spoil dump and production scheduling using Apollo & Orion modules of MINEX software, to get the desired pit design and stage wise plans for preparation of feasibility report.
PROJECT DETAILS
The Pit - A is designed upto 150 m depth of Bottom Seam. There are two down throw and one up throw faults in the property.
SUMMARISED DATA Sl. No 1.0 1.1 1.2 1.3 2.0 3.1 INSITU RESERVES MINEABLE RESERVES TOTAL OVERBURDEN AVG.STIPPING RATIO BOREHOLE DENSITY MAXIMUM SURFACE 3.2 4.1 MAXIMUM STRIKE LENGTH ALONG FLOOR MAXIMUM WIDTH OF THE QUARRY ALONG SURFACE 4.2 MAXIMUM WIDTH OF THE QUARRY ALONG FLOOR 5.1 5.2 6.1 6.2 7.0 MINIMUM DEPTH OF THE QUARRY MAXIMUM DEPTH OF THE QUARRY FLOOR AREA OF QUARRY AREA OF EXCAVATION ON SURFACE AVERAGE GRADIENT OF THE SEAM Meters Meters Ha. Ha. 28.00 150.0 21.45 45.15 1 in 3.5 Meters 420 Meters Meters 718 621 STRIKE LENGTH ALONG M.T M.T M.Cu.m Cu.m/T No./Sq.Km Meters 3.497 ----28.872 8.3 35.58 933 Description
Singareni Collieries
Page 2 of 18
8.0 DETAILS OF WORKABLE SECTIONS SECTION MINIMUM - MIDDLE SEAM PARTING - BOTTOM SEAM 4.65 14.63 3.18 PIT-A MAXIMUM 8.53 17.65 4.41
10.0 TECHNOLOGY SELECTED 11.0 INSTALLED CAPACITY 12.0 LIFE OF THE PROJECT
OPENPIT DESIGN
PIT BOUNDARY Quarry surface limit is defined on the basis of quarry floor limits by considering the final slope of 45 degrees from incrop and 150m depth of Bottom seam at highwall side. By considering the geological model of Pit-A, the bottom seam and middle seam model grids are merged with BOW (Base Of Weathering) surface at incrop side to generate benches upto the pit boundary/surface quarry limit.
BENCH DESIGN The bench design is followed as per bench elevation at 10m interval with 70 slope and 6.4m berm. To generate the bench crest and toe at every 10m elevation, SQL (Structured
Query Language) programme is used. The bench grids formed in the pit are restricted upto topography / floor of the bottom seam as per the requirement.
Singareni Collieries
Page 3 of 18
FIG.1
FIG.2
Singareni Collieries
Page 4 of 18
Final pit benches are restricted to the Bottom Seam floor and topography as shown below:
FIG.3 STRIP DESIGN 13 no. of strips with crest and toe in strike direction at 40m interval with 70 degrees of slope and strip berm of 6.4 mtrs are projected on each bench grid.
FIG.4
Singareni Collieries
Page 5 of 18
BLOCKS FORMATION The pit is divided into number of blocks using layout lines across the strips at 40m interval. Each block is assigned a number to report the reserves.
FIG.6
Singareni Collieries
Page 6 of 18
MINE RESERVES Mine Reserves database is created with Codes and Layers validated and loaded. Merge model is created for the Pit - A for the selected layers. Layer wise mine reserves of the pit can be obtained as desired.
FIG.8
Singareni Collieries
Page 7 of 18
FIG.10 Detailed Pit Reserves generated for Pit/Bench/Strip/Block is given at Annexure-1. Also generated the status report along with stripping ratios is shown at Annexure-2. By studying the detailed report of Pit reserves block wise, it is easy to identify the blocks in the designed pit for scheduling.
Singareni Collieries
Page 8 of 18
PRODUCTION SCHEDULING Scheduling is primarily aimed at sequencing mining operations in a pit/ multi strip/multi bench for coal or other layers. Target scheduling option is selected for the purpose.
TARGET SCHEDULING: This is the suitable method of scheduling to obtain a particular coal target over a time period and to generate stage plans. This macro scheduler finds applications in feasibility studies and production of long-range mine plans. Details of Target Scheduling: The project is proposed to extract coal with 0.60M.T per annum as installed capacity. Accordingly a suitable calendar is prepared for the project. For each scheduled block, reserves are reported and extraction of the quarry is planned for each coal seam/waste at every stage. Exposed blocks at the end of 1st year, 3rd year, 5th and final years of Pit-A are converted as exposed grids. In a grid format the pit status can be used for dump design and/or back fill planning.
Reports are generated for the quantity of coal extracted and waste removed at each stage {at the end of 1st year, 3rd year, 5th year and 6th(final) year}. Eg: Annexures-3.
Singareni Collieries
Page 9 of 18
Cumulating End of the Year 1 3 5 6(Final) 0.30 1.50 2.70 3.497 6.233 18.621 26.995 28.872 20.77 12.41 10.00 8.30 Coal (MT) OB (M.cu.m) Str. Ratio
Haul roads are designed at 6.25% gradient with a width of 20m on exposed grids/triangles keeping batter slopes at 57 degrees cut and 36 degrees fill.
Singareni Collieries
Page 10 of 18
SPOIL DUMP DESIGN Proposed area of overburden dumping is digitized. Dump design is made for every stage of the project keeping the dump deck height as 30m, dump slopes at 28 degrees and berm width as 30 mtrs for allowing safe transport.
FIG.13 FINAL EXTERNAL DUMP OF PIT-A TRUCK SIMULATION Truck and Shovel simulation system simulates the movements of a vehicle through a network of roads and ramps and estimates traveling time and truck fleet requirement. It can calculate the truck productivity (bank volume per truck hour). The input to the program is divided into data sets that define the characteristics of segments of routes, vehicle acceleration and deceleration potential at various velocities, and shovel operating parameters (Annexure - 4). The following parameters are considered for truck simulation at a particular stage of excavation. Shovel bucket cubic capacity Truck load by weight Swell factor Insitu density 2.80 25.00 1.20 2.20 14.98 3.94 (say 4) 46
Results are: i) Truck cycle time (minutes) ii) Est. Min truck fleet required iii) Bank volume per truck hour
Singareni Collieries
Page 11 of 18
FIG.15
Singareni Collieries
Page 12 of 18
It is felt very difficult to get the 2D plans output as desired in the form of crest and toe lines shown below.
D IP
DE-COALED AREA
INCROP
How ever, to overcome the problem, the scheduling output at a particular stage is digitized using Vista functions.
Singareni Collieries
Page 13 of 18
CONCLUSION Mine planning, designing and scheduling of an open pit are now made the mining system easy. Saves time in preparing number of alternative pit designs and production schedules with different design and schedule parameters. A best suitable pit design and production schedule can be selected. Quick reporting of reserves of each layer / bench / strip / block is possible. Year/month/day wise reports can be generated for the extracted volume of OB and Coal at the end of each schedule. The authors felt the necessity of 2D plans output to be customized rather than the tedious process of digitizing the position of quarry at every end of the schedule.
ACKNOWLEDGEMENT The Authors are thankful to the Singareni Collieries management for providing the necessary software, hardware and encouragement in achieving the desired outputs through Minex Software at SCCL.
REFERENCES Getting Started with Apollo Mine Design & Reserves, ECS International Pty Ltd, Surpac Minex Group, Australia. Mark Kelly, Peter Alexander, Surpac Minex Group, Australia, Training programmes on Apollo and Orion modules of Minex Software at Singareni Collieries.
Singareni Collieries
Page 14 of 18
Singareni Collieries
Page 15 of 18
Singareni Collieries
Page 16 of 18
Singareni Collieries
Page 17 of 18
Annexure - 4 TRUCK FLEET REQUIREMENT ------------------------------------------MATERIAL PARAMETERS ------------------SWELL FACTOR 1.20 INSITU DENSITY 2.200 SHOVEL PARAMETERS ----------------BUCKET CUBIC CAPACITY BUCKET FILL FACTOR BUCKET LOADS PER TRUCK SAY SPOT TIME SHOVEL CYCLE TIME TRUCK LOAD TIME SHOVEL AVAILABILITY % SHOVEL HOURS PER DAY
TRUCK PARAMETERS ---------------TRUCK LOAD BY WEIGHT 25.0 TRUCK CUBIC LOAD 13.64 TRUCK LOAD TIME 3.80 TRUCK DUMP TIME 0.50 TRUCK HAUL AND RETURN TIME 10.68 TRUCK CYCLE TIME (MINUTES) 14.98 TRUCK AVAILABILITY % 100.0 EST. MIN TRUCK FLEET REQUIRED 3.94 SAY 4 BANK VOLUME PER TRUCK HOUR 46 -------------------------------------------
TRUCK PRODUCTIVITY ------------------------------------------TRUCKS PRODUCTION PRODUCTION (BANK VOL/HR) (BANK VOL/DAY) ------------------------------------------1 46 1093 2 91 2185 3 137 3278 4 179 4306 -------------------------------------------
*****