Anda di halaman 1dari 48

Presentation to the Danish Society for Construction and Consulting Law

Mark Roe 29 September 2011

Topics covered
The latest developments on the FIDIC form of contract Partnering and Framework contracts using the NEC form

PPP opportunities globally

FIDIC Latest Developments


Latest Contracts Gold Book

Sub Contract Form

MDB Form

The Gold Book

FIDIC published a Guide to the Gold Book this summer Contrary to expectation, the Gold Book was not extended to brownfield sites The Gold Book therefore still applies only to greenfield sites FIDIC has stated its intention to publish a separate document for the brownfield scenario

The Gold Book - Notices


Amendment to Clause 20.1 A dilution of the notice provisions Allows the contractor to refer a notice to the DAB if it has given notice out of time if the Contractor considers there are circumstances which justify the late submission, he may submit the details to the DAB for a ruling. If the DAB considers that, in all the circumstances, it is fair and reasonable that the late submission be accepted, the DAB shall have the authority to overrule the relevant 28-day limit and, if it so decides, it shall advise the Parties accordingly. (extract from Clause 20.1(a))

New Yellow Book


FIDIC are due to publish a new version of the Yellow Book sometime in 2012 So far there are no hints about what form the amendments might take; however It is likely that the Yellow Book 2012 will include the recent change made to the Gold Book; namely the dilution of the notice provisions in Clause 20.1 It might seek to address criticisms that certain provisions do not work in a civil law environment

The Sub Contract Form - 2009


A new form with amendments is to be published in the near future (FIDIC say 2 October 2011 at FIDIC Davos conference) Overall Philosophy is a pass through of risk from Contractor to Sub Contractor Cl 1.1. Definitions in main Contract adopted in Sub Contract

Cl 1.3. Where Main Contract Provisions apply to Sub Contract , Sub Contract Clauses are to be interpreted as if amended appropriately
Cl 1.8 Sub Contract adopts Law and Language of Main Contract

The Sub Contract Form - 2009


Cl 2.1 Sub Contractor deemed to have knowledge of Main Contract Cl 2.2 Sub Contractor assumes all liabilities of Main Contractor, subject to exceptions for matters such as Security Access Services

The Sub Contract Form - 2009


Pass Through Continued

No provision that Sub Contractor will not place Main Contractor in breach in performing its Sub Contract Works

The Sub Contract Form - 2009


Clause 2.4 Contractor will take all reasonable steps to secure for Sub Contractor like Benefits Rights Entitlements That Contractor has under Main Contract But, Pay when Paid Provisions of Cl 14.6 limit its effect

The Sub Contract Form - 2009


Co ordination and Co operation Cl. 3.5 Contractor to co ordinate other Sub Contractor Cl. 6.1Sub contractor has duty to co operate and allow access to others Cl. 8.4 If Sub Contractor is late Contractor can order acceleration at Sub Contractors Cost.

The Sub Contract Form - 2009


Termination Cl 15.1 Optional Termination if Main Contract terminated Sub Contractor entitled to: Contract Value Termination Costs Lost Profit Subcontractor entitled to immediate payment if Contractor terminated for cause unless Sub Contractor caused termination.

The Sub Contract Form - 2009


If Main Contract terminated for Force Majeure, or Continued Suspension

Pay when Paid


Cl 15.6 Contractor may also terminate on any of Main Contract Grounds

The Sub Contract Form - 2009


Clause 20 - Claims Regime Cl. 20.2 - 21 day notice of claim is a precondition Clause 20.1 Sub Contractor must give notice to Contractor and keep records where Contractor required to do so under Main Contract. Cl. 20.3 Failure to comply with cl.20.1 entitles Contractor to set off from sums otherwise due to the Sub Contractor.

The Sub Contract Form - 2009


Claims Regime Contd Cl. 20.4 If Sub Contractor gives notice of dispute Main Contractor may suspend reference to DAB for 112 days Main Contractor may refer related disputes to Main Contract DAB. Sub Contract Arbitration not linked to Main Contract

New MDB Form


Very Similar to First Edition so a very brief reminder of the differences to the Red Book Cl. 2.4Funding Information Cl 6.4 &4.4 Local Labour and Sub Contractors Cl 6.7 Aids Owner risk for riot and insurrection limited to Jurisdiction of the Works Cl 17.6 Employer entitled to indemnity for damage to property unless Contractor can prove Employer fault

What FIDIC Has not done


No Partnering Form No Target Cost Contract New Engineering Contract is becoming a serious Competitor.

Partnering and framework contracts using the NEC form


Partnering as part of the ethos of the NEC generally Partnering as an optional sub-clause NEC framework contracts

NEC Overview
UNDERLYING PRINCIPLES A clear division of functions and responsibility helps accountability and motivates people to play their part Foresight applied collaboratively mitigates problems and risks

CLARITY

STIMULUS TO GOOD MANAGEMENT

FLEXIBILITY

Stimulus to good management a Partnering approach


Modern approach Mutual trust and co-operation The role of the Project Manager Notices and communications

Compensation events

NECs modern approach


Traditional forms of contract: discourage communication and can lead to claims create uncertainty re the final cost until the Final Account process begins no early resolution of claims payments are often on an interim basis cynicism and suspicion surrounding notices and records

NEC approach is very different: encourages early communication entitlements based on forecasts no final account process in NEC
But this requires a very different approach and mindset

Core clause 1
10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract in a spirit of mutual trust and co-operation

What does this mean?


How does it work in practice?

The Project Manager


The role of the PM Pro-active Involved in early warnings, risk reduction, compensation events, ambiguities, subcontractors, accepting programme, programme revisions Costain v Bechtel (2005)
When the project manager comes to exercise his discretion... It would be a most unusual basis for any building contract to postulate that every doubt shall be resolved in favour of the employer and every discretion shall be exercised against the contractor. Upon examining these provisions, I am unable to find anything which militates against the existence of a duty upon the project manager to act impartially in matters of assessment and certification.

Structure - flexibility
Modular Nine Core Clauses Six main options (pricing) Two dispute resolution secondary options Sixteen secondary options Total design flexibility Separate contracts for consultancy services (PSC), term maintenance (TSC), framework agreement, subcontracting

Structure modular form


Core Clauses

Main Option (A)

Main Option (B)

Main Option (C)

Main Option (D)

Main Option (E)

Main Option (F)

Must select one main option Must chose 1 Dispute Option

Dispute Resolution (W1)

Dispute Resolution (W2)

Secondary Option (X1)

Secondary Option (X2)

Secondary Option (X3)

Secondary Option (X15)

Secondary Option (X18)

Secondary Option (Y(UK)2)

Secondary Option (Z)

All secondary options are optional

Contract Data Parts 1 & 2

Essential information

Structure the Core Clauses


1 2 3 4 5 6 7 8 9 General The Contractors Main Responsibilities Time Testing and Defects Payment Compensation Events Title Risks and Insurance Termination

Secondary Option Clauses


Bonds and Guarantees
Construction Act

Retentions Inflation and Currencies


Incentives KPI, DLAD, Bonus, PLAD

Partnering

Design Responsibility

Sectional Completion

Changes in Law

Third Party Rights Act


Disputes

Limitations of Liability
Additional conditions

Secondary Option Clauses


X1 price adjustment for inflation X2 changes in law X4 PCG X5 sectional completion X6 bonus for early completion X7- delay damages (LADs) X12 - partnering X13 performance bond X14 advance payment X15 design liability X16 retention X17 low performance damages X18 limitation of liability X20 KPIs Y(UK)2&3 legislation Z additional conditions

Option Clause X12 - Partnering


Option X12 puts the NEC partnering option into a contract It is used for partnering between more than two parties working on the same project or programme of projects Enables the composition of the partnering team to be changed from time to time as projects evolve Brief set of clauses (4 clauses) Includes agreements for joint pursuit of objectives, & working towards key performance indicators

Framework contract
Introduced in 2005 when the NEC3 contract was launched Can be used in conjunction with any of the contracts from the NEC suite Designed to allow the Employer to invite tenders from suppliers to carry out work on an as instructed basis over a set term. Normally, the Employer will appoint a number of framework suppliers to carry out work within the defined scope.

Framework Contract
The Employer provides data: the framework information Scope Selection procedure Quotation procedure The Employer selects a supplier for a work package under the framework contract The supplier submits a quotation If the quotation is accepted the Employer issues a package order

NEC in general - points to bear in mind


NEC3 is in many ways more contractor friendly than other forms
As the main and subcontract clauses are the same, you need to amend the standard subcontract form if you are subcontracting on NEC3

Emphasis on project management, and successful project outcome, e.g. early warning, programming, communications
You must watch Cl. 13 when giving notices

Time bar provisions in the Comp. Event process


Is it practicable to comply with the CE process in reality? Assessment is based on forecasts which are not revisited if wrong.

NEC in general - points to bear in mind


Complete the contract properly!
Watch the Works Information. NB: the Contract Data. Take care with the secondary option clauses
main and subcontract choices do not need to be the same

The generosity (to the Contractor) of the CE regime


Gear your internal processes so that you take advantage of the deeming provisions in 61.4, 62.6 and 64.4 and watch subcontractors who will try to do the same

Programming obligations - onerous! Read the contract carefully. Its different! Do not make assumptions about what it says! It wording is not always clear and is not tested in the Courts.

Accessing global PPP opportunities to build business


Why does a country need infrastructure?
A sign of economic growth A sign of ability to compete A sign of development Demands of population increase Demands of increasing urbanisation

Opportunities Global expenditure on infrastructure:


Currently US$1 trillion = 2% global GDP per annum Anticipated increase by 2030 to US$41 trillion

Accessing global PPP opportunities to build business


Opportunities (contd) What types of projects are/will be available?
Major developments E.g. Bahrain Pilot Social Housing PPP scheme to build 5,000 housing units Maintenance and improvement E.g. Belmarsh Prison PPP new correctional facility at existing prison in London Replacement E.g. Hounslow Highways PPP repair and replacement of roads and pavements in west London

Accessing global PPP opportunities to build business


An Example of the Current Situation - Western Europe In first half of 2010,138 projects reached financial close
Spain had 46 projects, total value of US$9.87 billion
leading sectors for value: Transport (US$3.5 billion), Oil & Gas (US$3.1 billion)

France had 18 projects, total value of US$7.5 billion


Includes Exeltium Power Purchase Financing agreement

Portugal had 5 projects, total value of US$5.06 billion


Includes High Speed Rail (value: US$2.3 billion)

UK had 25 projects, total value of US$3.35 billion


Leading sector for number of projects: Social Infrastructure (22)

Accessing global PPP opportunities to build business


The Future: Ongoing pipeline of European projects PLUS Impact of emerging markets?
Population increase Demands for higher living standards Need to replace/maintain existing infrastructure Lack of budgetary constraints that will affect developed countries

= opportunities for construction sector!

PPP: the basics important considerations when starting out in PPP


Conventional Public Procurement vs PPP
Public Procurement Short term contract Funded by public sector
Risk shared between public and private sectors Delivery of infrastructure asset = end of contract Payment by public sector for duration of construction period PPP Long term contract (20+years) Funded wholly or largely by private sector Risk allocated to party best suited to manage the risk Delivery of infrastructure asset is usually integrated with ongoing maintenance/operating services Payment by public sector when asset is delivered and operational (unitary charge)

PPP: the basics important considerations when starting out in PPP


Conventional Procurement vs PPP
PROCURING AUTHORITY PROCURING AUTHORITY

PROJECTCO SPV

CONSTRUCTION CONTRACTOR

CONSTRUCTION CONTRACTOR

PPP: the basics important considerations when starting out in PPP


Procedure: Procuring Authority runs pre-contract Competition Competitive dialogue / Negotiated Procedure Preferred Bidder selected Project Company contracts with Procuring Authority Project Company contracts with Construction Contractor Financial Close funding secured by Project Company Construction Period begins

PPP: the basics important considerations when starting out in PPP


PPP Project Structure
PROCURING AUTHORITY

Project/Concession Agreement
HOLDCO

Subscription Agreement

PROJECTCO SPV

Facility and Security Agreements

BANK

Construction Agreement

Operations Agreement

Maintenance Agreement

CONSTRUCTION CONTRACTOR

OPERATING

MAINTENANCE

PPP: the basics important considerations when starting out in PPP


Differences between non-PPP and PPP Construction Agreement PPP Construction Agreement
Will seek to step down (or pass-through) Project Companys construction related obligations to Contractor Therefore will often not be in the form of a FIDIC or NEC contract but will have bespoke clauses Will contain new provisions which are Project Agreement (PA) driven: Termination (with compensation) if PA terminates Procuring Authoritys independent certifier/engineer likely to have influence Project equivalent relief (time/cost)

Lessons learned from recent PPP projects international best practice


Country Analysis:
Country Risk Perception Consider: domestic legal system, financial stability of the country, level of government support offered, query if awards are made at national or state level Government flexibility and willingness Consider: governments willingness to see that the project is completed will it recognise that events may not run according to plan and that some compromise may be needed between the parties?

Lessons learned from recent PPP projects international best practice


Project Selection: Pipeline of projects to encourage investment by private sector Clear and transparent procurement process candidates have confidence that the competition is run fairly

Projects need to be well-structured to be attractive to private sector and to satisfy private sector investors that PPP is the right approach for this project

Impact of role of international funding institutions (IFIs)


Remit of IFIs is consistent with implementation of PPP
International Finance Corporation (part of 'World Bank Group'): "[to] further economic development by encouraging the growth of productive private enterprise in member countries, particularly in the less developed areas" European Bank for Reconstruction and Development (EBRD): "[to] foster the transition toward open market oriented economies and to promote private and entrepreneurial initiative in the Central and Eastern European countries... European Investment Bank (EIB): "[to] contribute...to the balanced and steady development of the common market in the interest of the Community"

Impact of role of international funding institutions


IFIs: investing in PPP projects (contd):

Investment is largely in the form of direct loans to Project Companies (but some grant funding is available too)
Examples of current PPP investment:
Metro de Barcelona Estaciones (Spain) rail loan value EUR400 million Douro Litoral (Portugal) motorway toll concession loan value EUR600 million A2A Servizi Idrici Brescia water/waste loan value EUR70 million

Opportunities in Global PPP


Conclusions: Countries will continue to need infrastructure Rise of emerging markets will be crucial Population growth Replace / build new infrastructure Lack of budgetary constraints Support of IFIs Already active (e.g. Structural Fund )

Working hard to make it easier


LONDON DUBAI BEIJING SHANGHAI HONG KONG SINGAPORE OTHER UK LOCATIONS: BIRMINGHAM BRISTOL EDINBURGH GLASGOW LEEDS MANCHESTER International: T 44 (0)20 7418 7000 UK: T 0845 300 32 32

Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) and regulated by the Solicitors Regulation Authority. The word 'partner', used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the LLP or any affiliated firm who is a lawyer with equivalent standing and qualifications A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP's registered office: 30 Crown Place, London EC2A 4ES, United Kingdom. We use 'Pinsent Masons' to refer to Pinsent Masons LLP and affiliated entities that practise under the name 'Pinsent Masons' or a name that incorporates those words. Reference to 'Pinsent Masons' is to Pinsent Masons LLP and/or one or more of those affiliated entities as the context requires. Further information about us is available at www.pinsentmasons.com. Pinsent Masons LLP 2011

www.pinsentmasons.com

Anda mungkin juga menyukai