Flexi EDGE BTS

Commissioning & Integration

For internal use 1 Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 24.09.2007

Legal notice

Intellectual Property Rights All copyrights and intellectual property rights for Nokia training documentation, product documentation and slide presentation material, all of which are forthwith known as Nokia training material, are the exclusive property of Nokia. Nokia owns the rights to copying, modification, translation, adaptation or derivatives including any improvements or developments. Nokia has the sole right to copy, distribute, amend, modify, develop, license, sublicense, sell, transfer and assign the Nokia training material. Individuals can use the Nokia training material for their own personal self-development only, those same individuals cannot subsequently pass on that same Intellectual Property to others without the prior written agreement of Nokia. The Nokia training material cannot be used outside of an agreed Nokia training session for development of groups without the prior written agreement of Nokia.

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Objectives

At the end of this module the participant will be able to: Successfully commission & integrate the Flexi EDGE BTS

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Commissioning Prerequisites 1/2

Before commissioning, the physical installation of the BTS

(modules, cabling, antennas and radios) must be complete. Make sure you have a PC with Nokia Flexi EDGE BTS Manager installed. Make sure you have a 10/100 Mbit/s Ethernet cable available for the connection between the BTS and your PC. You need to have the parameter values available that need to be entered during commissioning. The parameter values are provided by the network planning process. BSC settings: the BTS site must already be created at the BSC for commissioning to be successfully completed.

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Commissioning Prerequisites 2/2

Transmission network setup: the transmission link(s) between the

BSC and the BTS must already be set up so that there is a transmission path from the BSC to the BTS for all the Abis channels. If there are any intermediate transmission hubs between the BSC and the BTS, the cross connections in the hubs should either be set up at the E1/T1 link level, or at the n x 64 kbit/s level for all the channels to the BTS in an E1/T1 link. With the Flexi transmission interface Flexbus sub-module (FIFA), the transmission link will be established during commissioning.

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

IP setup of the local Commissioning PC

If the Transmission unit type is FIFA, the IP settings of the PC should be as follows: IP address: 192.168.255.130 Subnet Mask: 255.255.255.128 Default Gateway: none

In all other cases (IP setup is like for WCDMA BTS / AXC access)

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Local Connection

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Undo Commissioning 1/3

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Undo Commissioning 2/3

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Undo Commissioning 3/3

10

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Commissioning options

11

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Site Specific Information

12

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Hardware Configuration

13

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cabling Configuration 1/4

14

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cabling Configuration 2/4

The following TRX / Sector configurations support RF-CAD (Cable Auto Detection)

Number of TRXs

TX Combining

RX diversity

Number of Dual TRX Modules (EXxA)

Number of Dual Duplexer Modules (ERxA)

Number of Wideband Combiner SubModules (EWxB)

Number of Antennas

1 to 2 2 2 1 2 2 4 1 1 1 1 2 2

By-pass

2UD

0 0 0 1 2 3 6

2 3 4 1 2 1 2

By-pass

2UD

By-pass

2UD

1 to 2

2-way

1UD (no diversity)

3 to 4

2-way

2UD

3 to 4

4-way

1UD (no diversity)

5 to 8

4-way

2UD

15

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cabling Configuration 3/4

The following TRX / Sector configurations support RF-CAD (Cable Auto Detection)

HW Config. Number of DDU Modules (ERxA) Number of Wideband Combiner SubModules (EWxB) Number of System Modules (ESMA) 0 1

TX Combining

RX diversity

Number of Dual TRX Modules (EXxA)

Number of Antennas per sector

Number of Antennas

1+1

By-pass

1UD (no diversity)

16

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cabling Configuration 4/4

17

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Antenna Settings 1/3

18

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Antenna Settings 2/3

19

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Antenna Settings 3/3

20

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Battery Backup Unit

21

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Other Passive Units

22

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Transmission Parameters

23

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Line interface settings

24

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Synchronization

25

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Abis Allocation 1/2

26

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Abis Allocation 2/2

27

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Abis Protection

28

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cross Connections 1/2

29

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Cross Connections 2/2

30

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Q1 Management

31

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

FlexiHub Manager

32

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Site Commissioning File

33

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

SCF Save Dialog

34

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Commissioning Progress

35

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

BTS has been successfully commissioned

36

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Operational Functionality

The Flexi EDGE BTS can be seen as operational, if: Abis interface is connected Operational state is Working (seen from the BSC as WO) Local (BTS Manager) indications are: O&M Link Established BCF operational state: Supervisory all TRXs operational states: Supervisory Abis Loop Tests have run successfully TRX Tests have run successfully Test calls are successful The BTS is free of unexpected alarms Remote Management (BSC / NetAct) is working.

37

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Check operational state: BCF

38

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007

Check operational state: TRX

39

Nokia Siemens Networks

Flexi EDGE BTS Commissioning & Integration / FAs / 08.10.2007