For all Final Tasks, LC = PC Once LC is Determined, LS equals LC minus TD. The LC for all tasks with head [j], is equal to the smallest value of LS for all tasks with tail [j]. At least one Initial Task must have LS = 0; none may be negative.
Determine Total Float (TF): Allowable delay in start of task which will not delay Project Completion
For task with tail [i] and head [j], TF[i,j] = (LC[j] ES[i]) TD[i,j] ES[i] is earliest start for all tasks with tail [i]. LC[j] is latest complete for all tasks with head [j].
Determine Free Float (FF): Allowable delay in start of task which will not delay start of any other task.
For task with tail [i] and head [j], FF[i,j] = ES[j] - ES[i] - TD[i, j] = ES[j] - EC[i,j] If [j] is the final event, use PC for ES[j]
All Tasks with zero Total Float are Critical. Any delay in these Tasks will delay Project Completion. Darken these Tasks to finish CPM Diagram.