PERIODO EGRESOS
0
-100,000
1
0
2
0
3
0
4
-60,000
Tasa Costo oportunidad
VAN:
TIR:
PROYECTO B
PERIODO EGRESOS
0
-100,000
1
-35,000
2
-45,000
3
-60,000
4
-60,000
Tasa Costo oportunidad
VAN:
TIR:
INGRESOS
0
0
0
260,000
FLUJO NETO
-100,000
0
0
0
200,000
F.N.Desc.
-100,000
0
0
0
127,104
FLUJO NETO
-100,000
50,000
50,000
50,000
50,000
F.N.Desc.
-100,000
44,643
39,860
35,589
31,776
-100,000
127,104
12.00%
$ 27,104
18.92%
INGRESOS
85,000
95,000
110,000
110,000
12.00%
$ 51,867
34.90%
-100,000
151,867
PROYECTO A
PERIODO EGRESOS
0
-100,000
1
0
2
0
3
0
4
-60,000
Tasa Costo oportunidad
VAN:
TIR:
PROYECTO B
PERIODO EGRESOS
0
-100,000
1
-35,000
2
-45,000
3
-60,000
4
-60,000
Tasa Costo oportunidad
VAN:
TIR:
INGRESOS
0
0
0
290,000
FLUJO NETO
-100,000
0
0
0
230,000
F.N.Desc.
-100,000
0
0
0
146,169
FLUJO NETO
-100,000
50,000
50,000
50,000
50,000
F.N.Desc.
-100,000
44,643
39,860
35,589
31,776
-100,000
146,169
12.00%
$ 46,169
23.15%
INGRESOS
85,000
95,000
110,000
110,000
12.00%
$ 51,867
34.90%
-100,000
151,867
PERIODO EGRESOS
0
1
2
3
4
5
Tasa Costo oportunidad
VAN:
TIR:
INGRESOS
12.00%
$ 61,558
84.5828%
FLUJO NETO
-27,060
23,657
23,534
24,518
25,522
26,546
F.N.Desc.
-27,060
21,122
18,761
17,451
16,220
15,063
-27,060
73,555
PERIODO EGRESOS
0
-1,500,000
1
-300,000
2
-300,000
3
-300,000
4
-300,000
Tasa Costo oportunidad
VAN:
TIR:
INGRESOS
1,000,000
1,000,000
1,000,000
1,000,000
20.00%
$ 312,114
30.6502%
FLUJO NETO
-1,500,000
700,000
700,000
700,000
700,000
F.N.Desc.
-1,500,000
583,333
486,111
405,093
337,577
-1,500,000
1,812,114