H A R I L I NO JENIS PEKERJAAN PIC START KERJA 3 JUNI 2013 JUNI JULI 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun

09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 B R A T A KETERANGAN

SCHEDULE HARIAN PEKERJAAN CIVIL


PROJECT EXPANSION P7

04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

H SELESAI 3 AGUSTUS 2013 U Y U AGUSTUS SEPTEMBER OKTOBER NOFEMBER 29-Jul 30-Jul 31-Jul ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### 07-Oct 14-Oct 21-Oct 28-Oct ##### ##### ##### ##### R A N 57 58 59 60 61 62 63 M A S S A L F I T R I M I D U L 2 0 1 3

I 1

BODY PREPARATION Pembongkaran a..Pembongkaran atap BP b.Pembuangan puing asbes c..Pembongkaran beton existing d. Pembuangan puing e. Pembongkaran Platform f..Perapihan besi bekas bongkaran Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual

Peninggian atap Bodi Prep. a. Pekerjaan konstruksi b. Pabrikasi c. Erection d. Pemasangan Atap e. Pemasangan kleding sisi Barat;Utara dan Selatan f. Rangka kleding g. Pasang seng h. Pemasangan kleding sisi Timur i. Rangka kleding j. Pasang seng Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual

Pembuatan pondasi a. Spray drayer -Pekerjaan persiapan -Galian tanah -Urugan pasir, lantai kerja, dan bekisting -Pasang pembesian -Pasang angkur dan base plat -Pengecoran pondasi b. Mixer 30 M3 -Pekerjaan persiapan -Galian tanah -Urugan pasir, lantai kerja, dan bekisting bataco -Pasang pembesian Lantai -Pasang angkur dan base plat -Pengecoran Lantai -Pasang pembesian Dinding -Bekisting Dinding -Pengecoran Dinding -Bekisting Tutup -Pasang pembesian Tutup -Pengecoran Tutup c. Silo -Pekerjaan persiapan -Galian tanah -Urugan pasir, lantai kerja, dan bekisting -Pasang pembesian -Pasang angkur dan base plat -Pengecoran Tapak -Pengecoran Pedestal d. Ballmill dan Dynamo 60 T (2 unt) -Pekerjaan persiapan -Bongkar platform lama -Angkat body ballmill lama -Bobok pondasi lama (Breaker) -Galian tanah -Buang puing -Urugan pasir, lantai kerja, dan bekisting Tapak -Pasang pembesian -Pengecoran Tapak -Pembesian pedestal dan dudukan Dynamo -Bekisting pedestal dan Dudukan Dynamo -Pasang sparing, angkur dan base plat -Pengecoran Pedestal dan dudukan Dynamo RENCANA PER HARI KOMULATIF RENCANA HARIAN REALISASI PER HARI KOMULATIF REALISASI HARIAN SELISIH Disetujui, PT. IKAD Dibuat oleh, PT. SAHABAT CIPTA ASRI Keterangan = = = = Pembongkaram Pembersihan/Pembuangan puing Persiapan dan pemasukan material Pelaksanaan Pekerjaan Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual 22 July selesai 100% Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual Plan Aktual 22 July selesai 100%

Danny Oetomo SCM Libur M assal dari :

Sape'i Engineering

Radi Civil tanggal 5 s/d 19 Agustus 2013