Anda di halaman 1dari 1

Contract Name

Location
Start Date
Completion Date
Revised Completion Date

:
:
:
:
:
CONSTRUCTION SCHEDULE

ITEM NO.

DESCRIPTION

JANUARY
31
1

0
0

FEBRUARY
15
16

MARCH
29
30

15
45

APRIL
31
61

MAY

15
76

30
91

JUNE

15
106

31
122

15
137

A. FACILITIES FOR THE ENGINEERS


Temporary Facilities for the Engineers

A-2

Provide/furnish furnitures, fixtures, equipment & Appliances for the field office for the engineers

AUGUST

15
167

31
183

15
198

SEPTEMBER
15
30
229
244

31
214

88.00

87.00

Furnish and maintain Survey Instrument

Provision for Health & Safety measures

B-2

Warning Signages and Baricades

PLANNED
REVISED
ACTUAL

C. REPLACEMENT OF SALENG BRIDGE


101(1)19

Removal of Existing Bailey Bridge (L=9m)

103(2) a

Bridge Excavation, Common, Above & Below O.W.L

103 (7) a

Structure Backfill

401 (a)

Concrete Railing

404 (1)

Reinforcing Steel, Grade 40 (Substructure & Superstructure)

405 (1)

Structural Concrete Class "A" (Substructure & Superstructure)

407 (1)

Lean Concrete

412b

Elastomeric Bearing pad (400x350x25mm, Duro 60)

413a

Performed Expansion Joint Filler with Sealants, 12mm thk.

413b

Performed Expansion Joint Filler with Sealants, 25mm thk.

505

Grouted Riprap Class "A" (Side Drain & Slope protection)

507

Rubble Concrete

508

Hand Laid Roack Embankment

SPL-417 (1)b

101(1)

Clearing and Grubbing


Excavation (Common Earth)

102(3)b

Surplus Rock Excavation (Hard)

104 (1) a

Embankment from Roadway Excavation (Common Earth)

200
311 (1) b
505

46.00

47.00

49.00

50.00

98.82 100.00
100.00

95.77
90.00

80.00

75.00
77.25

36.00

52.00

64.60

60.00

54.00
55.47

55.47
50.00

49.87

42.00

40.00

40.80

35.00
34.63

30.00

30.50

25.00
19.00
17.80
13.00

Aggregate Sub-base Course

0.50

Portland Cement Concrete pavement, t=230 mm


Grouted Riprap Class "A"

PREPARED & SUBMITTED BY:

97.46

62.00

48.00

Subgrade Preparation

SCHEDULED

96.10
94.00 100.00

DEC.
13
318

70.00

58.00

D. CONSTRUCTION/IMPROVEMENT OF ROAD APPROACHES

105 (1)

75.00

75.00

Metal drain (150mm x 825mm G.I Pipe)

102(3)a

NOVEMBER
15
30
290
305

31
275

88.07

B. OTHER GENERAL REQUIREMENTS


B-1

OCTOBER
15
259

100.00

95.00

A-1

A-3

JULY
30
152

PLANNED
REVISED
ACTUAL
SLIPPAGE

0.00
0.00

0.00

0.00
1

0.50
2

0.00
0.00
0.00
0.00

APPROVED:

0.50
0.50
0.00
-0.50

13.00

17.80

20.00

17.80

17.80

13.00
10.00 10.00

5.00

10.00

4.00
3
5.00
5.00
4.00
-1.00

0.00
4

13.00
13.00
10.00
-3.00

5
25.00
13.00
10.00
-3.00

6
36.00
17.80
19.00
1.20

7
48.00
17.80
35.00
17.20

8
62.00
17.80
42.00
24.20

9
75.00
17.80
46.00
28.20

10
87.00
30.50
47.00
16.50

11
95.00
34.63
49.00
14.38

12
100.00
40.80
50.00
9.20

13

49.87
52.00
2.13

14

55.47
54.00
-1.47

15

55.47
58.00
2.53

16

64.60
75.00
10.40

17

77.25
75.00
-2.25

18

88.07
88.00
-0.07

19

95.77
94.00
-1.77

20

100.00
96.10
-3.90

21

97.46

22

98.82

23

100.00

Anda mungkin juga menyukai