For KUL - Office Bldg, Bandra (E) Excavation & Backfilling Details Arch Dwg - Office Bldg BMC

Dwg 22.05.2013 Podium Excavation Area inside Shore Piles Soil Profile Excess Soil Filling Material Filling Greyish Clay Yellowish Brownish Clay / Murrum
535.2 Sqm

Friday, May 24, 2013

For Bldg Foot Print

For Podium Area

Above 0.00 0.00 to 1.77 1.77 to 3.50 3.50 to 5.50 5.50 to 15.0

0.90 1.77 1.73 2.00

0.60 Gr. Floor Level 0.60 Gr. Floor Level 0.00 Gr. Level 0.00 Gr. Level -8.40 2nd Basement Level (Floor-8.40 Finish) 2nd Basement Level (Floor Finish) -8.50 -8.65 -8.88 -9.18 -10.68 -10.83 -11.06 5.56 11.96 Tremix - 100mm -8.50 Tremix - 100mm PCC - 150mm -8.65 PCC - 150mm Soling - 230mm -8.88 Soling - 230mm Filling - 300mm -10.08 Filling - 1200mm Raft - 1500mm (Bldg Foot -10.68 Print) Raft - 600mm (Podium Area) Raft PCC - 150mm (Bldg -10.83 Foot Print) Raft PCC- 150mm (Podium Area) Raft Soling - 230mm (Bldg -11.06 Foot Print) Raft Soling - 230mm (Podium Area) Depth of Excavation 11.96 Depth of Excavation 0.78 1.68 No. Length Width Height Quantity Quantity 2,676

9.5 Yellowish Brownish Rock

Stubb Columns Sr. No. A Description Excavation 1 Excavation in Filling, Soil, Greyish Clay, Yellowish Brownish Clay From 0.0 to 5.0m Depth Podium Area 2 Excavation in Filling, Soil, Greyish Clay, Yellowish Brownish Clay From 5.0 to 7.0m Depth Podium Area 3 Excavation in Yellowish Brownish Rock From 5.0 to 7.0m Depth Podium Area 4 Excavation in Yellowish Brownish Rock From 7.0 to 9.0m Depth Podium Area 5 Excavation in Yellowish Brownish Rock From 9.0 to 11.0m Depth Podium Area 6 Excavation in Yellowish Brownish Rock From 11.0 to 13.0m Depth Podium Area Car Pits Car Lift Pits Lift Pits Lift Pits 7 Excavation in Yellowish Brownish Rock From 13.0 to 15.0m Depth Car Pits

Unit

Cum

535.16

5.00

2,675.81 749

Cum

535.16

1.40

749.23 321

Cum

535.16

0.60

321.10 1,070

Cum

535.16

2.00

1,070.32 1,070

Cum

535.16

2.00

1,070.32 778

Cum Cum Cum Cum Cum Cum

1 1 1 1 1 1

535.16 15.49 6.50 8.72 4.26 6.50

7.45 4.30 8.38 4.26 4.77

0.96 1.04 1.04 0.94 0.94 0.94

513.75 120.02 29.07 68.69 17.06 29.13 209

Cum Cum

1 1

15.49 6.50

7.45 4.30

1.46 1.46

168.48 40.81 6,874

EXCAVATION - TOTAL IN CUM =

6,874 Cum.

EXCAVATION - TOTAL IN CFT = EXCAVATION - TOTAL IN BRASS = EXCAVATION WITH 20% BULKAGE (FOR ROYALTY) - TOTAL IN BRASS = B Backfilling Between Shore Pile & Retaining Wall Podium Excavation Retaining Wall Area

242,713 Cft 2,427 Brass 2,913 Brass

Cum Cum

1 -1

535.161 452.231

11.060 11.060

5918.881 -5001.675 917.206

BACKFILLING - TOTAL IN CUM =

917 Cum.