CABLETRAYANDCABLELAYING Sr.No. 1 2 3 4 5 6 7 ActivityDescription Fixingofstructure&TraylayingatMMsectionbetweenBLine andCLineatEL537 537.50 50 FixingofmodifiedstructureatCLineandtraylayingatEL537.50 FixingofstructureandTraylayingonGeneratorBarrelandfromB LlinetoBarrel Fixingofstructure&TraylayingatEL530 FixingofstructureandTraylayingatEL525.25 FixingofstructureandTraylayingfromCablegallarytoCable trenchat548 Cablelaying Duration(no.

ofdays) 5 5 7 15 10 15 30 87 ManpowerRequired 2Fitter 2Riggers 2Fitter, Riggers,2Helpers 2Fitter,2Riggers,2Helpers 2Fitter,2Riggers,2Helpers 2Fitter,2Riggers,2Helpers 2Fitter,2Riggers,2Helpers 2Fitter,2Riggers,2Helpers 4riggers,4helpers

Asthetargetdateis15Marchtheheldupworkhastobestartedimmidiatelywithadditionalmanpowertomatchthetargetdate date.Plan yourmaterialandmanpoweraccordingly