Disconnecting switch Erection Installation procedure 1. Name plate details are checked & compare to the specification 2.

Physical visual check of equipment 3. Insulation value of Bushing insulator to be checked 4. Mount the equipment on foundation with all require accessories fitted 5. Earth switches mounting. 6. Check the level, orientation as per drawing. 7. Tightness of bolts , clamps 8. Alignment & connecting terminal to be checked 9. Earth connection are checked for tightness & proper contact 10. Insulators are thoroughly cleaned. 11. All moving plates are checked for lubrication 12. All control wiring termination to be checked 13. A.C. & D.C. Supply to be checked 14. Control protection to be checked

Equipment Testing 1. Insulation resistance 2. Contact resistance 3. Mechanical & Electrical operation