WATER SUPPLY AND DRAINAGE TEST REPORT (PPRC / UPVC / CI / GI)

Project Title: CONSTRUCTION OF INDOOR SPORTS GYMNASIUM AT UNIVERSITY OF ENGINEERING & TECHNOLOGY, TAXILA. Project Code: 3387 Issued To: Resident Engineer, M/s NESPAK (Pvt) Limited, Islamabad. Issued By: Site Engineer, M/s BUILDFAST (Pvt) Limited, Islamabad. Test. No: Date: Day: Re-Submitt: Time:

1. Type of Test (Check One): 1. Area/Location: 2. Floor: 3. Bath/Kitchen/External: 4. Level: 5. Grid Reference: 6. Distance: 7. Test Pressure:

Water Supply Piping:________, Sewerage:_________, Draingae:__________,Rain Water:__________

REMARKS OF THE CONSULTANT

DATE:____________________________

SIGNATURE:(Site Engineer):______________________

DATE:____________________________

SIGNATURE:(Resident Engineer):______________________