BILL OF QUANTITY (BOQ)

DAFTAR ANALISA HARGA SATUAN

Jenis Pekerjaan
: Pasangan Paving Block K. 225 uk=21.10,5.8 cm
Kuantitas Pekerjaan
: 1 M2
No
URAIAN
SAT.
KUANTITAS
HARGA SAT.
(Rp)

JMLH HARGA
(Rp)

A. TENAGA KERJA
1 Pekerja
2 Mandor
3 Tukang Batu

O/H
O/H
O/H

0.2000
0.0100
0.0150

69,000.00
74,750.00
97,750.00

13,800.00
747.50
1,466.25

B.
1
2
3

BAHAN
Paving Blok K 225 Polos
Paving Blok K 225 Warna
Pasir Kasar

Bh
Bh
M3

39.0000
4.0000
0.1000

2,875.00
3,450.00
174,000.00

112,125.00
13,800.00
17,400.00

C.
1
D.
E.
F.

PERALATAN
Roller Vibro
Jam
JUMLAH (A+B+C)
BIAYA UMUM
HARGA SATUAN PEKERJAAN (D+E)

0.0020

460,000.00

920.00
160,258.75
16,025.88
176,284.63