Activity ID
Activity Name
17-Oct-12
Original Start
Duration
Finish
2013
Aug
Abutment A1
68 01-Nov-12
21-Jan-13
J.SS8.LS.V5.A1.010
Foundation
15 01-Nov-12*
19-Nov-12
J.SS8.LS.V5.A1.020
Abutment Wall
32 20-Nov-12
27-Dec-12
J.SS8.LS.V5.A1.030
Abutment Cap
21 28-Dec-12
21-Jan-13
97 20-Nov-12
14-Mar-13
Pier P1
J.SS8.LS.V5.P1.010
Foundation
20 20-Nov-12
12-Dec-12
J.SS8.LS.V5.P1.020
Pier (Spl)
56 13-Dec-12
18-Feb-13
J.SS8.LS.V5.P1.030
Pier Cap
21 19-Feb-13
14-Mar-13
113 13-Dec-12
25-Apr-13
Pier P2
J.SS8.V5.LS.P2.010
Foundation
20 13-Dec-12
05-Jan-13
J.SS8.V5.LS.P2.020
Pier (Spl)
72 07-Jan-13
01-Apr-13
J.SS8.V5.LS.P2.030
Pier Cap
21 02-Apr-13
25-Apr-13
91 07-Jan-13
23-Apr-13
Pier P3
J.SS8.V5.LS.P3.010
Foundation
22 07-Jan-13
01-Feb-13
J.SS8.V5.LS.P3.020
Pier (Spl)
48 02-Feb-13
29-Mar-13
J.SS8.V5.LS.P3.030
Pier Cap
21 30-Mar-13
23-Apr-13
84 02-Feb-13
11-May-13
Pier P4
J.SS8.LS.V5.P4.010
Foundation
15 02-Feb-13
19-Feb-13
J.SS8.LS.V5.P4.020
Pier (Spl)
48 20-Feb-13
16-Apr-13
J.SS8.LS.V5.P4.030
Pier Cap
21 17-Apr-13
11-May-13
84 20-Feb-13
29-May-13
Pier P5
J.SS8.LS.V5.P5.010
Foundation
15 20-Feb-13
08-Mar-13
J.SS8.LS.V5.P5.020
Pier (Spl)
48 09-Mar-13
04-May-13
J.SS8.LS.V5.P5.030
Pier Cap
21 06-May-13
29-May-13
69 09-Mar-13
29-May-13
Pier P6
J.SS8.LS.V5.P6.010
Foundation
15 09-Mar-13
26-Mar-13
J.SS8.LS.V5.P6.020
Pier (Spl)
28 02-Apr-13
04-May-13
J.SS8.LS.V5.P6.030
Pier Cap
21 06-May-13
29-May-13
60 27-Mar-13
05-Jun-13
Abutment A2
J.SS8.LS.V5.A2.010
Foundation
15 27-Mar-13
12-Apr-13
J.SS8.LS.V5.A2.020
Abutment Wall
24 13-Apr-13
11-May-13
J.SS8.LS.V5.A2.030
Abutment Cap
21 13-May-13
05-Jun-13
8 11-Sep-13
25-Sep-13
8 11-Sep-13
25-Sep-13
212 01-Dec-12
09-Sep-13
Superstructure
J.SS8.V5.LS.CB.010
Crash Barrier
Span A1-P1
J.SS8.V5.LS.S1.010
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
15 01-Dec-12*
Sep
Oct
01-Nov-12
Nov
Dec
Jan
Feb
Mar
21-Jan-13
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
2014
Feb
Mar
Foundation
Abutment Wall
Abutment Cap
20-Nov-12
14-Mar-13
Foundation
Pier (Spl)
Pier Cap
13-Dec-12
25-Apr-13
Foundation
Pier (Spl)
Pier Cap
07-Jan-13
23-Apr-13
Foundation
Pier (Spl)
Pier Cap
02-Feb-13
11-May-13
Foundation
Pier (Spl)
Pier Cap
20-Feb-13
29-May-13
Foundation
Pier (Spl)
Pier Cap
09-Mar-13
29-May-13
Foundation
Pier (Spl)
Pier Cap
27-Mar-13
05-Jun-13
Foundation
Abutment Wall
Abutment Cap
11-Sep-13
25-Sep-13
Crash Barrier
01-Dec-12
18-Dec-12
PROJECT:
(JAMMU SECTION)
1 of 3
09-Sep-13
Plate Girder Fabrication
CONCESSIONAIRE:
SP JAMMU UDHAMPUR HIGHWAYS (P) LTD
EPC CONTRACTOR:
AFCONS INFRASTRUCTURE LTD
Date
16-Aug-12
26-Mar-12
16-Mar-12
13-Feb-12
26-Dec-11
19-Oct-11
Revision
R4
Addendum-R3
R3
R2
R1
R0
Checked
Approved
Activity Name
17-Oct-12
Original Start
Duration
Finish
Aug
J.SS8.V5.LS.S1.020
J.SS8.V5.LS.S1.030
Slab Casting
Span P1-P2
10 02-May-13*
13-May-13
25 20-Jul-13
09-Sep-13
197 19-Dec-12
09-Sep-13
J.SS8.V5.LS.S2.010
15 19-Dec-12
05-Jan-13
J.SS8.V5.LS.S2.020
10 14-May-13
24-May-13
J.SS8.V5.LS.S2.030
Slab Casting
25 20-Jul-13
09-Sep-13
182 07-Jan-13
09-Sep-13
Span P2-P3
J.SS8.V5.LS.S3.010
15 07-Jan-13
23-Jan-13
J.SS8.V5.LS.S3.020
10 25-May-13
05-Jun-13
J.SS8.V5.LS.S3.030
Slab Casting
25 20-Jul-13
09-Sep-13
167 24-Jan-13
09-Sep-13
Span P3-P4
J.SS8.V5.LS.S4.010
15 24-Jan-13
11-Feb-13
J.SS8.V5.LS.S4.020
10 06-Jun-13
17-Jun-13
J.SS8.V5.LS.S4.030
Slab Casting
25 20-Jul-13
09-Sep-13
152 12-Feb-13
09-Sep-13
Span P4-P5
J.SS8.V5.LS.S5.010
15 12-Feb-13
28-Feb-13
J.SS8.V5.LS.S5.020
10 18-Jun-13
28-Jun-13
J.SS8.V5.LS.S5.030
Slab Casting
25 20-Jul-13
09-Sep-13
137 01-Mar-13
09-Sep-13
Span P5-P6
J.SS8.V5.LS.S6.010
15 01-Mar-13
18-Mar-13
J.SS8.V5.LS.S6.020
10 29-Jun-13
18-Jul-13
J.SS8.V5.LS.S6.030
Slab Casting
25 20-Jul-13
09-Sep-13
25 06-Jun-13
08-Jul-13
25 06-Jun-13
08-Jul-13
58 13-Apr-13
20-Jun-13
Span P6-A2
J.SS8.V5.LS.S7.010
Abutment A1
J.SS8.RS.V5.A1.010
Foundation
15 13-Apr-13
30-Apr-13
J.SS8.RS.V5.A1.020
Abutment Wall
24 13-May-13
08-Jun-13
J.SS8.RS.V5.A1.030
Abutment Cap
10 10-Jun-13
20-Jun-13
96 02-May-13
30-Sep-13
Pier P1
J.SS8.RS.V5.P1.010
Foundation
15 02-May-13
18-May-13
J.SS8.RS.V5.P1.020
Pier (Spl)
60 20-May-13
16-Aug-13
J.SS8.RS.V5.P1.030
Pier Cap
21 19-Aug-13
30-Sep-13
104 20-May-13
30-Oct-13
Pier P2
J.SS8.RS.V5.P2.010
Foundation
15 20-May-13
05-Jun-13
J.SS8.RS.V5.P2.025
Pier (Spl)
68 06-Jun-13
03-Oct-13
J.SS8.RS.V5.P2.030
Pier Cap
21 04-Oct-13
30-Oct-13
108 06-Jun-13
22-Nov-13
Pier P3
J.SS8.RS.V5.P3.010
Foundation
15 06-Jun-13
22-Jun-13
J.SS8.RS.V5.P3.025
Pier (Spl)
72 24-Jun-13
28-Oct-13
J.SS8.RS.V5.P3.030
Pier Cap
21 29-Oct-13
22-Nov-13
96 24-Jun-13
26-Nov-13
Pier P4
J.SS8.V5.RS.P4.010
Foundation
15 24-Jun-13
18-Jul-13
J.SS8.V5.RS.P4.020
Pier (Spl)
60 20-Jul-13
31-Oct-13
J.SS8.V5.RS.P4.030
Pier Cap
21 01-Nov-13
26-Nov-13
80 20-Jul-13
25-Nov-13
Pier P5
J.SS8.RS.V5.P5.010
Foundation
15 20-Jul-13
16-Aug-13
J.SS8.RS.V5.P5.020
Pier (Spl)
44 19-Aug-13
30-Oct-13
J.SS8.RS.V5.P5.030
Pier Cap
21 31-Oct-13
25-Nov-13
49 19-Aug-13
05-Nov-13
Abutment A2
2 of 3
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
2013
May
Jun
Jul
Plate Girder Erection
Aug
Sep
Oct
Nov
Dec
Slab Casting
19-Dec-12
09-Sep-13
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
07-Jan-13
09-Sep-13
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
24-Jan-13
09-Sep-13
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
12-Feb-13
09-Sep-13
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
01-Mar-13
09-Sep-13
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
06-Jun-13
08-Jul-13
Casting of Solid slab
13-Apr-13
20-Jun-13
Foundation
Abutment Wall
Abutment Cap
02-May-13
30-Sep-13
Foundation
Pier (Spl)
Pier Cap
20-May-13
30-Oct-13
Foundation
Pier (Spl)
Pier Cap
06-Jun-13
22-Nov-13
Foundation
Pier (Spl)
Pier Cap
24-Jun-13
26-Nov-13
Foundation
Pier (Spl)
Pier Cap
20-Jul-13
25-Nov-13
Foundation
Pier (Spl)
Pier Cap
19-Aug-13
05-Nov-13
Jan
2014
Feb
Mar
Activity Name
17-Oct-12
Original Start
Duration
Finish
2013
Aug
J.SS8.RS.V5.A2.010
Foundation
15 19-Aug-13
19-Sep-13
J.SS8.RS.V5.A2.020
Abutment Wall
24 21-Sep-13
23-Oct-13
J.SS8.RS.V5.A2.030
Abutment Cap
10 24-Oct-13
05-Nov-13
8 08-Feb-14
17-Feb-14
8 08-Feb-14
17-Feb-14
330 01-Dec-12
07-Feb-14
Superstructure
J.SS8.V5.RS.CB.010
Crash Barrier
Span A1-P1
J.SS8.V5.RS.S1.010
15 01-Dec-12*
18-Dec-12
J.SS8.V5.RS.S1.020
10 01-Oct-13
14-Oct-13
J.SS8.V5.RS.S1.030
Slab Casting
25 10-Jan-14
07-Feb-14
315 19-Dec-12
07-Feb-14
Span P1-P2
J.SS8.V5.RS.S2.010
15 19-Dec-12
05-Jan-13
J.SS8.V5.RS.S2.020
10 31-Oct-13
12-Nov-13
J.SS8.V5.RS.S2.030
Slab Casting
25 10-Jan-14
07-Feb-14
300 07-Jan-13
07-Feb-14
Span P2-P3
J.SS8.V5.RS.S3.010
15 07-Jan-13
23-Jan-13
J.SS8.V5.RS.S3.020
10 23-Nov-13
04-Dec-13
J.SS8.V5.RS.S3.030
Slab Casting
25 10-Jan-14
07-Feb-14
285 24-Jan-13
07-Feb-14
Span P3-P4
J.SS8.V5.RS.S4.010
15 24-Jan-13
11-Feb-13
J.SS8.V5.RS.S4.020
10 05-Dec-13
16-Dec-13
J.SS8.V5.RS.S4.030
Slab Casting
25 10-Jan-14
07-Feb-14
270 12-Feb-13
07-Feb-14
Span P4-P5
J.SS8.V5.RS.S5.010
15 12-Feb-13
28-Feb-13
J.SS8.V5.RS.S5.020
10 17-Dec-13
28-Dec-13
J.SS8.V5.RS.S5.030
Slab Casting
25 10-Jan-14
07-Feb-14
255 01-Mar-13
07-Feb-14
Span P5-A2
3 of 3
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Foundation
Dec
Jan
2014
Feb
Mar
Abutment Wall
Abutment Cap
08-Feb-14
17-Feb-14
Crash Barrier
01-Dec-12
07-Feb-14
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
19-Dec-12
07-Feb-14
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
07-Jan-13
07-Feb-14
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
24-Jan-13
07-Feb-14
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
12-Feb-13
07-Feb-14
Plate Girder Fabrication
Plate Girder Erection
Slab Casting
01-Mar-13
07-Feb-14
J.SS8.V5.RS.S6.010
15 01-Mar-13
18-Mar-13
J.SS8.V5.RS.S6.020
10 30-Dec-13
09-Jan-14
J.SS8.V5.RS.S6.030
Slab Casting
25 10-Jan-14
07-Feb-14
Slab Casting