NJ Office, Belle Mead, NJ HVAC Engineering Dept.

Determine Expansion Tank Size: Application: Hot Water System Known Piping Quantities Location Penthouse and 1st Floor Pipe Size Linear Feet (Inches) 0.75 502 1 214 1.25 195 1.5 523 2 76 2.5 0 3 139 4 6 8 10 12 14 16 18 20 24 Material Type L Type L Type L Type L Type L Schedule 40 Schedule 40 Schedule 40 Schedule 40 Schedule 40 Schedule 40 SW (.375" Wall) SW (.375" Wall) SW (.375" Wall) SW (.375" Wall) SW (.375" Wall) SW (.375" Wall) Gallons of Water 13 9 13 48 12 0 53 0 0 0 0 0 0 0 0 0 0 148

Client Project Location Project# Proj.Area Form By: Check By: Calc.By: Rev. By: 2 3

Bayer Building 36 Renovation West Haven, CT 97182.00 Penthouse P. Bucklen, P.E. M. Butler P. Bucklen, P.E.

17-Mar-98 17-Mar-98 17-Mar-98

Equipment Quantity HX-1 RHC's P-1-1 P-1-2 UH-1-1 UH-1-2 UH-1-3 UH-1-4 AS-1-1 CF-1-1 1 25 1 1 1 1 1 1 1 1

Gallons / Total Gallons of Unit Water 20 20 2 50 2 2 2 2 5 5 5 5 5 5 2 2 10 10 5 5

TOTAL Volume of Water in System, Vs 254 Lower Temperature, T1 50 Higher Temperature, T2 180 Atomspheric Pressure, Pa 14.70 Abs. Pressure @ T1, P1 24.70 Abs. Pressure @ T2, P2 59.38 Specific Volume of Water @ T10.16020 Specific Volume of Water @ T20.16510 Linear Coefficient of Expansion ######### Delta T (T2-T1) 130 Volume of Expansion Tank 20.53 EXPANSION TANK SCHEDULE gallons Deg. F Deg. F psia psia, Lower Pressure psia, Higher Pressure Cu. Ft. / lb Cu. Ft. / lb In / in Deg F for steel Deg. F gallons

TOTAL

106

CLOSED EXPANSION TANK


EQUIP. NUMBER ET-1 LOCATION MANUF./ MODEL No. TYPE

(FURNISHED AND INSTALLED BY CONTRACTOR) CAPACITY SERVICE OPER. WT. (GAL) (LBS.) 25 HOT WATER 75 REMARKS/NOTES

PENTHOUSE B&G/30 NON-DIAPHRAGM

Provide Airtrol Fitting, ATF-12