DESCRIPCION
TRAZO Y REPLANTEO
ROCE Y LIMPIEZA
MOVILIZ. Y DESMOVILIZ. EQUIPO
ACONDICIONAMIENTO DE DESVIO
EXCAVACION BAJO EL AGUA
ELIMINACION MAT. EXCEDENTE
ENCOF. Y DESENCOFRADO DE ZAPATAS
ACERO DE REFRUERZO DE ZAPATA
CONCRETO Fc =140 Kg/cm2 P/ZAPATA
ENCOFDO Y DESENCONFRADO DE ESTRIBO
ACERO DE REFZO Fy 4200 Kg/Cm2 ESTRIBO
UNIDAD
Ml
Mt2
Est.
Mt3
Mt3
Mt3
Mt2
Kgs
Mt3
Mt2
Kgs
Mt3
UU
UU
UU
Mt2
METRADO
90.00
450.00
1.00
456.00
850.00
1,000.00
85.00
214.00
100.00
246.00
564.00
260.00
6.00
6.00
12.00
45.00
COSTO UNITARIO
TOTAL
24,013.80
266.82
1.23
553.50
1,440.00
1,440.00
15.96
7,277.76
8.71
7,403.50
14.09
14,090.00
160.27
13,622.95
79.74
17,064.36
343.53
34,353.00
290.67
71,504.82
774.04
436,558.56
676.16
175,801.60
2,143.35
12,860.10
746.72
4,480.32
1557.97
18,695.64
18.09
814.05
COSTOS INDIRECTOS :
PRESUPUESTO
840,533.96
84,053.40
924,587.36
DESCRIPCION
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
hh
0.016
0.016
0.048
98.05
5.48
4.31
1.57
0.09
0.21
1.86
Est.
0.05
1.86
0.09
0.09
Kg
P2
28.00
43.00
4.53
3.21
126.84
138.03
MANO DE OBRA
1.01
1.02
1.03
TOPOGRAFO
CAPATAZ
PEON
HERRAMIENTAS
1.04
5% DE LA MANO DE OBRA
MATERIALES
1.05
1.06
CAL HIDRAULICA
MADERA TORNILLO
COSTO UNITARIO :
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
264.87
266.82
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
0.020
0.240
5.48
4.31
0.11
1.03
1.14
Est.
0.08
1.14
0.09
0.09
MANO DE OBRA
2.01
2.02
CAPATAZ
PEON
HERRAMIENTAS
2.02
8% DE LA MANO DE OBRA
COSTO UNITARIO :
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
1.23
APORTE
P. UNIT
P. ACUMUL
UU
UU
UU
UU
UU
UU
1.00
1.00
1.00
1.00
1.00
1.00
600.00
600.00
150.00
30.00
30.00
30.00
600.00
600.00
150.00
30.00
30.00
30.00
TOTAL
COSTO UNITARIO :
1,440.00
1,440.00
DESCRIPCION
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
0.070
0.070
4.89
4.31
0.34
0.30
0.64
Mts3
0.070
218.46
15.29
15.29
Est.
0.050
0.64
0.03
0.03
MANO DE OBRA
4.01
4.02
OPERARIO
PEON
EQUIPO MECANICO
4.03
HERRAMIENTAS
4.04
5% DE LA MANO DE OBRA
15.96
COSTO UNITARIO :
PARTIDA
DESCRIPCION
UNIDAD
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
0.100
0.100
4.89
4.31
0.49
0.43
0.92
Mts3
0.100
27.82
2.78
2.78
MANO DE OBRA
4.01
4.02
OPERARIO
PEON
MOTOBOMBA 5 HP
COSTO UNITARIO :
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
3.70
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
0.044
0.044
5.48
4.31
0.24
0.19
0.43
Mts3
0.044
187.66
8.26
8.26
Est.
0.050
0.40
0.02
0.02
MANO DE OBRA
5.01
5.02
CAPATAZ
PEON
EQUIPO MECANICO
5.03
HERRAMIENTAS
5.04
5% DE LA MANO DE OBRA
COSTO UNITARIO :
6.00
8.71
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
180 mts3/dia
S/. 14.09
2 das
UNIDAD
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
hh
0.011
0.022
0.044
5.48
4.89
4.31
0.06
0.11
0.19
0.36
Mts3
Mts3
0.044
0.044
187.66
124.10
8.26
5.46
13.72
Est.
0.050
0.36
0.02
0.02
MANO DE OBRA
6.01
6.02
6.03
CAPATAZ
OPERARIO
PEON
EQUIPO MECANICO
6.04
6.05
HERRAMIENTAS
6.06
5% DE LA MANO DE OBRA
COSTO UNITARIO :
14.09
PARTIDA
MANO DE OBRA
7.01
7.02
CAPATAZ
OPERARIO
hh
hh
0.625
1.250
5.48
4.89
3.43
6.11
9.54
Est.
0.050
9.54
0.48
0.48
3.50
3.21
70.00
80.25
150.25
HERRAMIENTAS
7.03
5% DE LA MANO DE OBRA
MATERIALES
7.04
7.05
Kg
P2
20.00
25.00
COSTO UNITARIO :
160.27
PARTIDA
DESCRIPCION
UNIDAD
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
hh
0.266
0.798
0.798
5.48
4.89
4.31
1.46
3.90
3.44
8.80
Est.
0.050
8.80
0.44
0.44
Kg
Kg
4.890
0.266
14.25
3.09
69.68
0.82
70.50
MANO DE OBRA
8.01
8.02
8.03
CAPATAZ
OPERARIO
PEON
HERRAMIENTAS
8.04
5% DE LA MANO DE OBRA
MATERIALES
8.05
8.06
COSTO UNITARIO :
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
79.74
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
hh
0.500
0.500
3.500
5.48
4.89
4.31
2.74
2.45
15.09
20.27
hm
hm
0.400
0.400
32.00
27.00
12.80
10.80
23.60
Bls
Mt3
Lt
Gln
5.250
0.960
6.000
7.230
19.50
19.00
28.50
1.00
102.38
18.24
171.00
7.23
298.85
Est.
0.050
20.27
1.01
MANO DE OBRA
9.01
9.02
9.03
CAPATAZ
OPERARIO
PEON
MATERIALES
9.06
9.07
9.08
9.09
CEMENTO PORTLAN I
ARENA GRUESA
SIKA IV (ACELERANTE)
AGUA
HERRAMIENTAS
9.10
5% DE LA MANO DE OBRA
COSTO UNITARIO :
0.81
343.53
DESCRIPCION
APORTE
P. UNIT
P. ACUMUL
TOTAL
MANO DE OBRA
10.01
10.02
CAPATAZ
OPERARIO
hh
hh
0.020
0.060
5.48
4.89
0.11
0.29
0.40
Est.
0.050
0.40
0.02
0.02
Kg
P2
60.00
25.00
3.50
3.21
210.00
80.25
HERRAMIENTAS
10.03
5% DE LA MANO DE OBRA
MATERIALES
10.04
10.05
COSTO UNITARIO :
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
TIEMPO DE DURACION :
PARTIDA
DESCRIPCION
290.25
290.67
APORTE
P. UNIT
P. ACUMUL
TOTAL
hh
hh
hh
0.266
1.596
1.596
5.48
4.89
4.31
1.46
7.80
6.88
16.14
Est.
0.050
16.14
0.81
0.81
Kg
Kg
42.580
48.65
14.25
3.09
606.77
150.33
MANO DE OBRA
11.01
11.02
11.03
CAPATAZ
OPERARIO
PEON
HERRAMIENTAS
11.04
5% DE LA MANO DE OBRA
MATERIALES
11.05
11.06
COSTO UNITARIO :
757.09
774.04
PARTIDA
MANO DE OBRA
12.01
12.02
CAPATAZ
OPERARIO
hh
hh
0.750
0.750
5.48
4.89
4.11
3.67
12.03
PEON
hh
12.000
4.31
51.72
59.50
hm
hm
0.400
0.400
32.00
27.00
12.80
10.80
23.60
Bls
Mt3
Mt3
Lt
Gln
7.650
0.960
6.665
6.000
7.230
19.50
19.00
37.00
28.50
1.00
149.18
18.24
246.61
171.00
7.23
592.25
Est.
0.050
59.50
2.98
MATERIALES
12.06
12.07
12.08
12.09
12.10
CEMENTO PORTLAN I
ARENA GRUESA
PIEDRA CHAMCADA DE 1/2"
SIKA IV (ACELERANTE)
AGUA
HERRAMIENTAS
12.11
5% DE LA MANO DE OBRA
COSTO UNITARIO :
0.81
676.16
PARTIDA
MANO DE OBRA
13.01
13.02
13.03
CAPATAZ
OPERARIO
PEON
hh
hh
hh
0.040
0.040
0.400
5.48
4.89
4.31
0.22
0.20
1.72
2.14
Hm
Est.
1.000
0.050
45.00
2.14
45.00
0.11
45.11
UU
Mts
UU
UU
2.150
5.000
22.000
2.000
847.35
24.12
1.35
62.00
1,821.80
120.60
29.70
124.00
HERRAMIENTAS
13.04
13.05
MATERIALES
13.06
13.07
13.08
13.09
COSTO UNITARIO :
2,096.10
2,143.35
PARTIDA
TOTAL
MANO DE OBRA
15.01
15.02
15.03
CAPATAZ
OPERARIO
PEON
hh
hh
hh
0.040
0.200
0.200
5.48
4.89
4.31
0.22
0.98
0.86
Hm
1.000
45.00
45.00
HERRAMIENTAS
15.04
2.06
15.05
5% DE LA MANO DE OBRA
Est.
0.050
2.14
0.11
UU
Mts
UU
1.650
4.000
12.000
847.35
24.12
1.35
1,398.13
96.48
16.20
45.11
MATERIALES
15.06
15.07
15.08
COSTO UNITARIO :
1,510.81
1,557.97
PARTIDA
MANO DE OBRA
14.01
14.02
14.03
CAPATAZ
OPERARIO
PEON
hh
hh
hh
0.040
0.080
0.160
5.48
4.89
4.31
0.22
0.39
0.69
1.30
Hm
Est.
1.000
0.050
45.00
2.14
45.00
0.11
45.11
Est.
1.000
187.66
187.66
187.66
UU
0.605
847.35
512.65
512.65
HERRAMIENTAS
14.04
14.05
EQUIPO MECANICO
14.06
MATERIALES
14.07
COSTO UNITARIO :
17.00 APOYO DE VIGAS DE NEOPRENE DE 2"
PARTIDA :
RENDIMIENTO :
COSTO UNITARIO :
S/. 12,691.77
TIEMPO DE DURACION :
2 das
DESCRIPCION
UNIDAD APORTE
P. UNIT
P. ACUMUL
PARTIDA
746.72
TOTAL
MANO DE OBRA
17.01
17.02
17.03
CAPATAZ
OPERARIO
PEON
hh
hh
hh
0.040
0.160
0.160
5.48
4.89
4.31
0.22
0.78
0.69
1.69
Est.
0.050
1.69
0.08
0.08
UU
30.000
423.00
12,690.00
HERRAMIENTAS
17.05
5% DE LA MANO DE OBRA
MATERIALES
17.06
APOYOS DE NEOPRENE
COSTO UNITARIO :
12,690.00
12,691.77
PARTIDA
TOTAL
MANO DE OBRA
16.01
16.02
OPERARIO
PEON
hh
hh
0.015
0.045
4.89
4.31
0.07
0.19
0.27
Est.
0.050
0.03
0.00
0.01
Gln
0.450
37.50
16.88
HERRAMIENTAS
16.03
5% DE LA MANO DE OBRA
MATERIALES
16.04
PINTURA ANTICORROSIVA
16.05
AGUA RAZ
Gln
0.125
7.50
0.94
COSTO UNITARIO :
17.81
18.09
Obra: PUENTE
ACTIVIDADES Y PRECEDENCIA
N/O
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
DESCRIPCION
TRAZO Y REPLANTEO
ROCE Y LIMPIEZA
MOVILIZ. Y DESMOVILIZ. EQUIPO
ACONDICIONAMIENTO DE DESVIO
EXCAVACION BAJO EL AGUA
ELIMINACION MAT. EXCEDENTE
ENCOF. Y DESENCOFRADO DE ZAPATAS
ACERO DE REFRUERZO DE ZAPATA
CONCRETO Fc =140 Kg/cm2 P/ZAPATA
ENCOFDO Y DESENCONFRADO DE ESTRIBO
ACERO DE REFZO Fy 4200 Kg/Cm2 ESTRIBO
CONCRETO Fc =210 Kg/cm2 P/ ESTRIBOS
FABRICACION DE VIGAS Y DIAFRAGMAS
MONTAJE DE SOLDADURA Y DIAFRAGMAS
LANZAMIENTO Y MONTAJEDE VIGAS
PINTURA ESMALTE Y ANTICORROSIVA
A
B
C
D
E
G
H
I
J
K
L
M
N
O
P
Q
1
3
2
1
4
2
5
4
20
3
4
20
10
5
2
1
_
_
_
A
A,B
D,E,C
E,C
E,C
I,H
J
J
L,K
C
N
O,M
P
201369059.xls.ms_office
RECURSOS (ASAP)
DESCCRIPCION
ACTIVIDAD
TIEMPO
P M1 M2 M3 M4 M5
1_2
1 3
TRAZO Y REPLANTEO
1 4
ROCE Y LIMPIEZA
12
2 9
10
F1
2 6
4 6
F2
3 4
3 6
ACONDICIONAMIENTO DE DESVIO
6 8
6 7
6 9
F3
7 8
8 10
20
10 11
10 12
9 13
10
F4
11 12
12 13
20
13 14
14 15
9 10 11 12 13 14 15
0
EXCAVACION BAJO EL AGUA
10
0
1
3
4
0
2
RECURSOS /DIA
CAPATAZ
PERARIO
PEON
MAQUINA 1
MAQUINA 2
2 1 2 2 2 2 4 4 4 3 3
1 2 5 5 5 5 10 10 10 10 10
15 13 17 15 15 15 15 12 12 8 8
1 2
1 1
1 1 1 1 1 1
2 2 2 2
7 6 6 6
5 12 12 12
201369059.xls.ms_office
DIAS CALENDARIOS
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
2 2 2 2 2 2 2
6 6 6 6 6 6 6
12 12 12 12 12 12 12
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
2
4
9
2
4
9
2
4
9
2
4
9
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
6 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
201369059.xls.ms_office
56 57 58 59 60
1 1
6 6
16 16
1
2
4
1
2
4
1
0
3
201369059.xls.ms_office
RECURSOS /DIA
MAQUINA 3
MAQUINQ 4
MAQUINA 5
1
1
1
1
1
1
2
3
2
3
2
3
201369059.xls.ms_office
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
201369059.xls.ms_office
4
6
4
6
201369059.xls.ms_office
RECURSOS (ASAP)
DESCCRIPCION
ACTIVIDAD
TIEMPO
P M1 M2 M3 M4 M5
1_2
1 3
TRAZO Y REPLANTEO
1 4
ROCE Y LIMPIEZA
12
2 9
10
F1
2 6
4 6
F2
3 4
3 6
ACONDICIONAMIENTO DE DESVIO
6 8
6 7
6 9
F3
7 8
8 10
20
10 11
10 12
9 13
10
F4
11 12
12 13
20
13 14
14 15
9 10 11 12 13 14 15
0
EXCAVACION BAJO EL AGUA
10
0
1
3
4
0
2
RECURSOS /DIA
CAPATAZ
PERARIO
PEON
MAQUINA 1
MAQUINA 2
2 1 2 2 2 2 4 4 4 3 3
1 2 5 5 5 5 10 10 10 10 10
15 13 17 15 15 15 15 12 12 8 8
1 2
1 1
1 1 1 1 1 1
2 2 2 2
7 6 6 6
5 12 12 12
201369059.xls.ms_office
DIAS CALENDARIOS
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
2 2 2 2 2 2 2
6 6 6 6 6 6 6
12 12 12 12 12 12 12
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
1
1
7
2
4
9
2
4
9
2
4
9
2
4
9
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
6 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
201369059.xls.ms_office
56 57 58 59 60
1 1
6 6
16 16
1
2
4
1
2
4
1
0
3
201369059.xls.ms_office
RECURSOS /DIA
MAQUINA 3
MAQUINQ 4
MAQUINA 5
GRAFICO DE CAPATACES
6
5
4
3
2
1
1
1
1
1
1
1
GRAFICOS DE OPERARIOS
1_3
GRAFICO DE PEONES
2
3
2
3
2
3
9 10 11 12 13 14 15
6_7
6_88
4_6
2_9
9_13
2_9
9 10 11 12 13 14 15
6_7
6_8
9_13
2_9
3_6
1_2
0
17
16
15
14
13
12
11
10
9
8
7
6
6_9
1_4
12
11
10
9
8
7
6
5
4
3
2
1
9 10 11 12 13 14 15
2_9
1_3
3_6
4_6
1_4
6_9
9_13
6_7
201369059.xls.ms_office
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
2
3
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
4
6
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
9_13
8_10
10_11
10_12
12_13
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
9_13
10_11
8_10
12_13
10_12
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
9_13
10_11
8_10
12_13
201369059.xls.ms_office
4
6
4
6
56 57 58 59 60
14_15
13_14
56 57 58 59 60
13_14
56 57 58 59 60
14_15
4_6
GRAFICO DE
PEONES
201369059.xls.ms_office
2_9
6_7
1_4
5
4
3
2
1
6
5
4
3
2
1
9 10 11 12 13 14 15
9 10 11 12 13 14 15
3_6
1_2
6
5
4
3
2
1
1_2
4_7
6_9
1_2
9 10 11 12 13 14 15
6
5
4
3
2
1
6
5
4
3
6_9
9 10 11 12 13 14 15
201369059.xls.ms_office
12_13
8_10
10_12
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
12_13
8_10
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
12_13
201369059.xls.ms_office
13_14
56 57 58 59 60
56 57 58 59 60
13_14
56 57 58 59 60
56 57 58 59 60
201369059.xls.ms_office
GRAFICOS DE MAQUINA No4
2
1
1_2
6
5
4
3
2
1
1_2
9 10 11 12 13 14 15
201369059.xls.ms_office
12_13
8_10
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
201369059.xls.ms_office
56 57 58 59 60