CHEMICAL CLEANING VENDORS -MINIMUM OPERATIONAL REQUIREMENTS Ensure the commissioning of the following major equipments including their

protections, interlocks, measurements, alarms and annunciations: 1. 2. 3. 4. 5. 6. 7. 8. 9. One ID Fan. FD Fan. Boiler filling system. Oil Firing System. FSSS. Scanner Air System. Soot blower for APH with compressed air. Other system associated to boiler light up shall be ready. Measurements, alarms, ammunitions pertaining to secondary air flue gas, feed water, steam & Boiler metal temp. Ensure free expansion of the furnace, ducts and provision of expansion markers. 10. Blow Down system of Boiler. 11. Proper drainage system of boiler area. 12. Air in leak test of one pass of ESP. 13. Mechanical readiness of two passes of ESP. 14. Adequate quantity of light oil & readiness of light oil handling system. 15. Temporary sampling system along with the cooling arrangement for collecting samples from the header drains during chemical cleaning are ready. 16. Water and steam systems are ready for operation. 17. Air and flue gas system ready for operation. 18. Effluent treatment pit to hold approximately 1500m3 is ready 19. Drainage line to effluent treatment is ready. 20. Drum water sampling system on both sides along with sample cooling arrangement. 21. Fire fighting system of concerned equipments.

22. Equipment cooling water system shall be made ready. 23. Availability of adequate quantity of DM water. 24. Adequate capacity of instrument air and service air system. 25. Availability of HP dozing system. 26. Availability of test coupons & their fixing arrangements. 27. Data logging printer at control room. 28. Available to record the boiler parameters periodically. One BFP for Alkali boil out. .

Anda mungkin juga menyukai