Bahan
1
2
3.
4.
5.
6.
7.
8.
9.
10.
Kayu berketam
Kayu berketam
Kayu berketam
Kayu berketam
Kayu berketam
Kayu berketam berlurah
Kayu berketam berlurah
Perspek bewarna
Bod MDF
Paip PVC bewarna
Saiz
Kuantiti
10 x 70 x 120
110 x 10 x 160
10 x 20 x 40
10 x 20 x 180
10 x 20 x 90
10 x 50 x 180
10 x 50 x 120
2 x 60 x 100
3 x 180 x 300
1 x 65
200
100
200
100
300
100
200
100
100
100
Harga seunit
(RM)
1.60
0.40
0.60
1.10
1.20
0.90
1.60
1.50
2.70
0.50
JUMLAH
Jumlah (RM)
320.00
400.00
120.00
110.00
360.00
90.00
320.00
150.00
270.00
50.00
RM 1210.00
KOS UPAH
Kos upah = Bilangan pekerja x jam x Kadar upah sejam
= 3 orang x 20 jam x RM 20.00
= RM 120.00
KOS OVERHEAD
Air = RM 10.00
Elektrik = RM 20.00
JUMLAH = RM 30.00
KOS PENGELUARAN
JUMLAH KOS PENGELUARAN = Kos Bahan + Kos Upah + kos Overhead
= RM 1210.00 + RM 120.00 + RM 30.00
= RM 1360.00
KOS PENGELUARAN (SEUNIT) = JUMLAH KOS PENGELUARAN / JUMLAH PENGELUARAN
= RM 1360.00 / 100
= RM 13.60 SEUNIT