Anda di halaman 1dari 1

No.

Uraian Keterangan
I Pipe Support Tie In " Titik 1 "
1 Concrete Pile Cap f c 30 0.72 m
3
2
Concrete Pedestal f c 30
0.324
m
3
1.044 m
3
3 Rebar D16 Pipe Cap 4 btg
Rebar D16 Pedestal 4 btg
8 btg
4 Anchor Bolt Dia 16mm + Accessories 6 ea
5 Bolt 16mm + accessories 10 ea
6 U-Clamp, plate 15mm thk. 1 Ls
7 HB 300.300 @1.8m 2 Set
No. Uraian Keterangan
II Pipe Support Tie In " Titik 3 "
1 Concrete Pile Cap f c 30 2.316 m
3
2
Concrete Pedestal f c 30
1.0422
m
3
3.3582 m
3
3 Rebar D16 Pipe Cap 11 btg
Rebar D16 Pedestal 4 btg
15 btg
4 Anchor Bolt Dia 16mm + Accessories 2 ea
6 U-Clamp, plate 15mm thk. 1 Ls
No. Uraian Keterangan
II Pipe Support PL37
1 Concrete Pile Cap f c 30 0.648 m
3
2
Concrete Pedestal f c 30
0.1418
m
3
0.7898 m
3
3 Rebar D19 Pipe Cap 6 btg
Rebar D19 Pedestal 2 btg
8 btg
4 Anchor Bolt Dia 16mm + Accessories 4 ea
Volume
Volume
Volume
MTO PIPE SUPPORT TIE IN & PL37