CUSTOMER:
Document
B742-0-VBR-MMT-DES-001
AREA:
MECHANICAL
PIPING -TECHNICAL SPECIFICATION
Issued by:
DESEINs no.:
24.11.0
8
First Issue
Rev.
Date
Object
T.Zhacaria
A.Karmakar
Prepared Checked
T.Zhacaria
Quality
Approved
Assurance
A.Karmakar
Sheet No 2 of 76
OVERALL CONTENT
1.0
2.0
3.0
TECHNICAL SPECIFICATION
MECHANICAL
SECTION-I
ELECTRICAL
SECTION-II
SECTION-III
CIVIL
SECTION-IV
SECTION-V
SECTION-VI
TENDER DRAWINGS
SECTION-VII
Sheet No 3 of 76
TECHNICAL SPECIFICATION
Sheet No 4 of 76
SECTION - I
TECHNICAL SPECIFICATION
(MECHANICAL)
Sheet No 5 of 76
SUB SECTION - M0
GENERAL TECHNICAL SPECIFICATION
Sheet No 6 of 76
Sheet No 7 of 76
3.1.2 For all L.P. piping system covered under this specification, sizing and system design
shall be to the requirements of relevant codes and standard indicated elsewhere. In
addition to this, requirements of any statutory codes as applicable shall also be taken into
consideration.----------------------------------------------------------------------------------18
3.1.3 Inside diameters of piping shall be calculated for the flow requirements of various
systems. The velocities for calculating the inside diameters shall be limited to the
following:--------------------------------------------------------------------------------------19
3.1.4 The pipes shall be sized for the worst (i.e. maximum flow, temp. and pressure values)
operating conditions.--------------------------------------------------------------------------19
3.1.5 Based on the established inside diameter, thickness calculation shall be made as per
ANSI B 31.1 and thickness of pipes shall than be selected as per ANSI B 36.10.-----19
3.1.6 Corrosion allowance of 1.6 mm shall be added to the calculated thickness being
considered.-------------------------------------------------------------------------------------19
3.1.7 Bend thinning allowance/manufacturing allowance etc. shall be as per the requirement of
the design code provision.--------------------------------------------------------------------20
3.1.8 All high points in piping system shall be provided with vents alongwith valves. All low
points shall be provided with drains alongwith valves. Drain lines shall be adequately
sized so as to clear condensate in the lines. Material for drain and vent lines shall be
compatible with that of the parent pipe material.------------------------------------------20
3.1.9 Material of construction for pipes carrying various fluids shall be as specified elsewhere
in this specification.---------------------------------------------------------------------------20
3.1.10 Compressed air pipe work shall be adequately drained to prevent internal moisture
accumulation and moisture traps of adequate capacity and quantity shall be provided at
strategic locations in the piping systems.---------------------------------------------------20
3.1.11 Depending upon the size and system pressure, joints in compressed air pipe work shall
be screwed or flanged. The flange shall be welded with the parent pipe at shop and shall
be hot dip galvanized before despatch to site.----------------------------------------------20
3.1.12 Threaded joints shall be provided with Teflon sealant tapes.-------------------------20
3.1.13 Following types of valves shall be used for the system/service indicated.----------20
3.1.14 Recirculation pipes alongwith valves, break-down orifices etc. shall be provided for
important pumping systems. The recirculation pipe shall be sized for minimum 30%design
Sheet No 8 of 76
flow of single pump operation or the recommended flow of the pump manufacturer
whichever is higher.---------------------------------------------------------------------------20
3.2.1 General----------------------------------------------------------------------------------------20
3.2.2 Pipes and fittings----------------------------------------------------------------------------21
3.2.3 Material---------------------------------------------------------------------------------------22
3.2.5 Piping layout---------------------------------------------------------------------------------23
3.2.6 Slope/Drains and Vents---------------------------------------------------------------------24
3.2.7 Pipe Joints------------------------------------------------------------------------------------24
3.2.8 Bends/elbows/ Tees/ Reducers & other fittings------------------------------------------25
3.2.9 Flanges----------------------------------------------------------------------------------------26
3.2.10 Specific technical requirement of laying buried pipe with anti corrosive treatment26
3.2.11 Cleaning, flushing and blow out ---------------------------------------------------------28
3.2.12 Surface preparation and painting---------------------------------------------------------28
3.2.13 Specification for hangers and supports--------------------------------------------------29
Safety Valves---------------------------------------------------------------------------------------42
Cast Steel Valves-----------------------------------------------------------------------------------43
a. Pressure class------------------------------------------------------------------------------------43
b. Size range----------------------------------------------------------------------------------------43
c. Service--------------------------------------------------------------------------------------------43
d. Construction-------------------------------------------------------------------------------------43
i. Bonnet/cover-------------------------------------------------------------------------------------43
ii. Disc----------------------------------------------------------------------------------------------43
- Gate valves---------------------------------------------------------------------------------------43
- Globe valves-------------------------------------------------------------------------------------43
- Check valves-------------------------------------------------------------------------------------43
iii. Ends---------------------------------------------------------------------------------------------43
iv. Stem---------------------------------------------------------------------------------------------43
Sheet No 9 of 76
Sheet No 10 of 76
1.0
PURPOSE OF DOCUMENT
1.01
1.02
It is not the intent to completely specify all details of design and construction
herein. Nevertheless, the equipment and installation shall conform to high
standard of engineering, design and workmanship in all respects and shall be
capable of performing in continuous satisfactory commercial operation in a
manner acceptable to the Purchaser or end client.
1.03
The purchaser reserves the right to place separate order for any of the specified
items without assigning any reason whatsoever. The decision of the purchaser in
this regard will be final.
2.0
2.1
2.2
Bidder shall submit along with the offer customer's certificates as documentary
evidence in support of their previous experience. Systems as above, involved in
such earlier projects, shall be clearly mentioned in the offer.
2.3
3.0
GENERAL INFORMATION
3.01
The entire Piping System shall be designed and engineered by the bidder who
shall be responsible for smooth, trouble free, safe and efficient operation of the
system and the contract shall be dealt as Lump-sum Contract.
3.02
Equipment and services to be covered under this specification and the conditions
therein are detailed in the various sections/sub-sections, drawings and documents
of the specification.
Sheet No 11 of 76
The international transport & site delivery price must be quoted as an option.
Bidder shall quote in the price tabulation sheet
4.0
SITE CONDITION
Please refer General Condition Of Contract (GCC) & Particular Condition Of
Contract (PCC)
In continuation to the GCC & PCC further the following Conditions shall be used
for System / Equipment design and sizing:
: 30.50C
: 85%
: 400C
: 500C
: 450C
.
5.0
6.0
SYSTEM DESCRIPTION
The Piping System comprises of all main and interconnecting pipe work along with
,valves, fittings and related specialties as specified in the specification below.
Pipe works for instrument air, service air, DM water lines, portable and service
water lines are covered under this system.
Pipes , valves and other fittings shall be pre-fabricated, of reputed make.
The operation of the system shall be in any combination of Auto/Manual and
Remote/ local type.
7.0
SCOPE OF SUPPLY
Please refer General Condition Of Contract & Particular Condition Of Contract.
The Bidders scope of supply shall be based on the technical specification and
BOQ of various BOP packages
8.0
Sheet No 12 of 76
SCOPE OF SERVICES
Please refer General Condition Of Contract & Particular Condition Of Contract
9.0
WORKS BY OTHERS
Please refer General Condition Of Contract & Particular Condition Of Contract
10.0
SPARES
Please refer General Condition of Contract & Particular Condition Of Contract
List of such tools and tackles shall be furnished in the relevant schedule of
Proposal exhibit sheets under section VI along with their prices.
11.0
12.0
12.1
13.0
13.1
14.0
15.0
15.1
Sheet No 13 of 76
damage. Shop coats of rust inhibiting paints, lacquers, etc. shall be applied to
various parts as necessary.
15.2
The scope of work under this specification includes supply and site application of
paints suitable for marine environment. A detailed painting schedule shall have
to be submitted to the Purchaser for approval.
16.0
16.1
following
specific
16.1.2
16.2
16.2.1
16.2.4
Detailed list of Instruments showing make, size, range, tag nos. etc.
16.2.8
Bill of material indicating tag nos., type, sizes, working pressure, material of
construction, quantity etc.
16.3
ii)
iii)
B742-0-VBR-MMT-DES-001-0-A4-.PDF.English
Sheet No 14 of 76
v)
Instruction and part list shall be legible and prepared on good quality paper.
vi)
vii)
viii)
The Instruction Manual shall include list of all special tools and tackle
furnished with complete drawing and instruction for use of such tools and
tackle.
WORK SCHEDULE
Supply and delivery, complete erection, final check-up, testing and
commissioning of the complete piping system along with all accessories as
specified shall be within two (2) months from the date of issue of Notice to
Proceed. The Bidder in his proposal shall indicate the phase-wise design,
engineering, manufacturing, supply, erection, testing and commissioning of the
equipment, as specified, in the form of a bar- chart/ PERT network.
18.0
19.0
20.0
INSTRUCTION MANUALS
Refer General Condition Of Contract & Particular Condition Of Contract
21.0
GUARANTEE
Refer General Condition Of Contract & Particular Condition Of Contract
Sheet No 15 of 76
Sheet No 16 of 76
SUB SECTION M1
PARTICULAR
TECHNICAL SPECIFICATION
MECHANICAL
Sheet 17 of 76
1.0
Sheet 18 of 76
GENERAL REQUIREMENT
This Sub section covers general requirements of design, construction features,
manufacture, inspection and testing of all pipe work for various BOP packages
and the associated equipment. The specific requirements are given in the
technical data sheets enclosed separately:
2.0
3.0
BS-5155
BS-5154
BS-5152
BS-5153
ANSI B 16.34
API-594
API-600
ANSI-B-16.10
API-598
ANSI-B-31.1
ANSI-B-36.10
ANSI-B-36.19
SIZING CRITERIA
3.1.1 All the piping systems supplied under this package shall be designed
to operate without replacement and with normal maintenance for a plant
service life of 25 years, and shall withstand the operating parameter
fluctuations and cycling which can be normally expected during this period.
3.1.2 For all L.P. piping system covered under this specification, sizing and
system design shall be to the requirements of relevant codes and standard
indicated elsewhere. In addition to this, requirements of any statutory codes as
applicable shall also be taken into consideration.
Sheet 19 of 76
3.1.3 Inside diameters of piping shall be calculated for the flow requirements
of various systems. The velocities for calculating the inside diameters shall be
limited to the following:
(a)
Water Application
Water Velocity in m/sec
Pipe Size
(a)
Pump suction
(b)
Pump discharge
and recirculation
Pipeline
(c)
Below
50 mm
------
50-150 mm
1.2-1.5
200 mm
& above
1.2-1.5
1.2-1.8
1.8-2.4
2.1-2.5
------
1.5-2.4
2.0-2.4
100
140
For calculating the required pump head for pump selection, atleast
10% margin shall be taken over the pipe friction losses and static head
shall be calculated from the minimum water level of the tank/ sump/
reservoir from which the pumps draw water.
(b)
3.1.4 The pipes shall be sized for the worst (i.e. maximum flow, temp. and
pressure values) operating conditions.
3.1.5 Based on the established inside diameter, thickness calculation shall
be made as per ANSI B 31.1 and thickness of pipes shall than be selected as
per ANSI B 36.10.
3.1.6 Corrosion allowance of 1.6 mm shall be added to the calculated
thickness being considered.
Sheet 20 of 76
TYPES OF VALVES
Globe
Check
Butterfly
Gate
Air
Water
Plug
Technical Specification
3.2.1
General
Specific technical requirements of low pressure piping and fittings have been
covered under this Sub-section. It includes details pertaining to design and
material of construction, cleaning/surface preparation/ application of primer
and painting on overground piping. It also includes detailed technical
requirement of laying underground/buried piping including water proofing/anti
corrosive protection. It also covers design, engineering, manufacturing,
fabrication, details of valves, specialities, piping hangers/supports, tanks etc.
THIS DOCUMENT IS PROPERTY OF ISOLUX CORSAN. COPY IS FORBIDDEN
B742-0-VBR-MMT-DES-001-0-A4-.PDF.English
3.2.2
Sheet 21 of 76
3.2. 2.1
All low pressure piping systems shall be capable of withstanding the maximum
pressure in the corresponding lines at the relevant temperatures. However, the
minimum thickness as specified in the following clauses and or respective
codes for pipes and fittings shall be adhered to. The bidder shall furnish the
pipe sizing/ thickness calculation as per the criteria mentioned in the Technical
Specification.
3.2.2.2
3.2.2.3
Bends, loops, off sets, expansion or flexible joints shall be used as required in
order to prevent overstressing the piping system and to provide adequate
flexibility. Flexibility analysis (using software packages such as Caesar-II etc)
shall be carried out for sufficiently long piping (straight run more than 300M).
3.2.2.4
3.2.2.5
Flexibility analysis shall be carried out for pipelines which have considerable
straight run as indicated above and necessary loops/expansion joint etc. shall
be provided as may be necessary depending on layout.
3.2.2.6
3.2.2.7
3.2.2.8
For large size pipes/ducts, at high point and bends/change of direction of flow,
air release valves shall be provided. Sizing criteria for air release valves shall
be generally on the basis of valve size to pipe diameter ratio of 1:8.
Requirement shall be decided as per relevant code.
Transient analysis /surge analysis where ever specified and required shall be
conducted in order to determine the location, number and size of the Air-
Sheet 22 of 76
Material
3.2.3.1
3.2.3.2
3.2.3.3
All materials shall be new and procured directly from the manufacturers.
Materials procured from traders or stockists are not acceptable.
3.2.3.4
All materials shall be certified by proper material test certificates. All material
test certificates shall carry proper heat number or other acceptable references
to enable identification of the certificate that certifies the material.
3.2.3.5
Oil piping
API 5L
Sheet 23 of 76
3.2.3.6
3.2.3.7
3.2.3.8
Instrument air, Plant (service) air lines and Drinking water lines shall be to
ASTM A 53 type E grade B/ANSI B 36. 10, ANSI B 36.10 Schedule numbers
shall be followed). The material of the pipes shall be to ASTM A 53 type E Gr.
B. Heavy. The fittings shall be either same as parent material.
3.2.3.9
Spiral welded pipes as per API-5L are also acceptable for pipe of size above
150 NB. However minimum thickness of the pipes shall be as elaborated in
above clauses.
3.2.4
Wall Thickness
The calculation of wall thickness required for pipelines subject to internal and/or
external pressure shall be based on the formulae and recommendations as
given in the applicable codes. Adequate allowances shall be made towards
thinning due to bending, weakening at branch connections, threading,
commercial tolerances on pipe wall thickness, corrosion and erosion, etc., and
the same shall be subject to approval by Purchaser. In any case a minimum
corrosion allowance of 1.6 mm shall be considered while selecting the
thickness.
3.2.5
Piping layout
3.2.5.1
3.2.5.2
Piping routing shall be such as to provide sufficient clearance for removal and
maintenance of equipment, easy access to valves, instruments and other
accessories. The piping shall not encroach on the withdrawal space of various
equipments.
3.2.5.3
Over head piping shall have a normal minimum vertical clearance of 2.5
meters above walkways and working areas and 8 M above roadways. When
several pipe lines are laid parallel, flanged joints must be staggered. Welded
and flanged joints should as far as possible be located at one third span from
supports. If the support is situated right under the welded joints this joint must
be reinforced with a strap. Flanged and welded joints must be avoided in the
middle of the span. Valves should be located in such a manner so as to
ensure their convenient operation from the floor or the nearest platform.
3.2.5.4
Pipe lines of NB 50 size and below are regarded as field run piping. It is
Bidders responsibility to plan suitable layouts for these system insitu. Bidder
shall prepare drawings indicating the layout of field run pipe work. These
Sheet 24 of 76
All piping shall be routed so as to avoid interference with other pipes and their
hangers and supports, electrical cable trays, ventilation ducting, structural
members, equipment etc. Adequate clearance shall be ensured with respect to
the above to accommodate insulation and pipe movements, if any.
3.2.5.6
3.2.5.7
Sufficient up stream and down stream lengths shall be provided for flow
measuring devices, control valves and other specialities.
3.2.5.8
3.2.5.9
Openings provided in the wall for pipelines must be closed with bricks and
mortar with 10-12 mm clearance between brick work and pipe after taking care
of insulation and thermal movement, if any. The clear space must be filled with
felt or asbestos or approved filling compound.
3.2.6
3.2.6.1
Suitable slope shall be provided for all pipelines towards drain points. It is
Bidder responsibility to identify the requirements of drains and vents, and
supply the necessary pipe work, valves, fittings, hangers and supports etc. In
addition to the system requirement all low points in the pipelines shall be
provided with suitable draining arrangement and all high points shall be
provided with vent connections where air or gas pockets may occur. Vent
connections provided, for use during hydrostatic test shall be plugged after the
completion of the test. Vent shall not be less than 15mm size. Drains shall be
provided at low points and at pockets in piping such that complete drainage of
all systems is possible. Drain shall not be less than 15mm for line size upto
150mm.
3.2.6.2
Air piping shall be sloped so that any part of the system can be drained
through the shut-off drain valve or drain plugs.
3.2.7
Pipe Joints
3.2.7.1
In general all water lines 50mm and below are to be joined generally by socket
welding unless mentioned otherwise specifically. All air lines shall be of
screwed connection.
3.2.7.2
Screwed
3.2.7.3
Sheet 25 of 76
(a)
(b)
Teflon tapes shall be used to seal out screwed joints and shall be
applied to the male threads only. Threaded parts shall be wiped clean
of oil or grease with appropriate solvent if necessary and allowing
proper time for drying before applying the sealant. Pipe ends shall be
reamed and all chips shall be removed. Screwed flanges shall be
attached by screwing the pipe through the flange and the pipe and
flange shall be refaced accurately.
Welded
For making up welded joints (butt weld or socket weld) the welding shall be
performed by manual shielded metal arc process in accordance with the
requirements specified elsewhere in the spec. Any welder employed for
carrying butt welding shall be qualified as per ASME section IX for the type of
joints he is going to weld. Jointing by butt weld, or socket weld shall depend
upon the respective piping material specifications.
3.2.7.4
Flanged
(a)
Flanged connections are to be kept to the minimum and used only for
connections to vessel, equipments, flanged valves and other fittings
like strainer/traps/orifices etc. for ease of connection and maintenance
etc.
(b)
All flanged valves intended for installation on steel piping system, shall
have their flanges drilled to ANSI B 16.5 (or equivalent) and according
to the pressure class stated in their respective piping material
specification.
(c)
3.2.8
3.2.8.1
3.2.8.2
For pipe sizes upto 65 NB, long radius forged elbows or seamless pipe bends
shall be used. Pipe bends, if used, shall be cold bent to a radius measured to
the centre line of pipe of 3 to 5 times the pipe diameter.
3.2.8.3
For steel pipes 80 NB and above, seamless long radius forged elbows shall be
used.
3.2.8.4
For pipe fittings such as reducers and tees, the material shall be to ASTM-A234 Gr. WCB up to 300 NB. Provision of compensation pads shall be kept as
Sheet 26 of 76
per ANSI B 31.1. The fitting shall conform to the dimensional standard of ANSI
B-16.9.
3.2.9
Flanges
3.2.9.1
3.2.9.2
3.2.10.1
3.2.10.2
Trenching
(a)
The trench shall be cut true to the line and level and shall follow the
gradient of the pipeline. The width of the trench shall be sufficient to
give free working space on each side of the pipe.
(b)
(c)
(d)
Prior to lowering and laying pipe in any trench, the Bidder shall backfill
and compact the bottom of the trench or excavation to provide an
acceptable bed for placing the pipe.
(e)
The pipeline shall be thoroughly cleaned of all rust, grease, dirt, weld
scales and weld burrs etc. moisture or other foreign matter by power
cleaning method such as sand blasting, power tool cleaning,
etc..Grease or heavy oil shall be removed by washing with a volatile
solvent such as gasoline. Kerosene will not be permitted for cleaning.
This cleaning operation shall be immediately followed by priming with
the mechanical priming machine.
(b)
(c)
3.2.10.3
The cleaning and priming operation shall be carried out at site. The
entire pipe length shall be cleaned but the ends of the pipes shall be
left without coating for a distance of 230mm for joints, which shall be
coated manually at site after laying, welding and testing the pipe.
(b)
(c)
(d)
3.2.10.4
Sheet 27 of 76
Bond/adhesion test
Holiday test
The anti-corrosive protection can consist of anti-corrosive protection
Coal-tar tapes. material and application of tapes shall conform to
AWWA-C-203. These-tapes shall be applied hot over the cold coal tar
primer. The total thickness of the finished protective coating shall be
4mm minimum.
Rocky Soil.
Sandy/silty soil (including non-expansive clay).
Expansive soil (including water logged/ marshy soil).
The bidder shall note that the cross-country raw water piping as well as other
in-plant pipings may travel underground through all types of soils and
combination of soils described above.
3.2.10.5
Sheet 28 of 76
Primer painting
After the surface is prepared in a manner acceptable to the Project Manager
two coats of red oxide (zinc chromate) primer conforming to BS shall be
applied. Primer shall be applied by brushing to ensure a continuous film
without holidays. Primer shall be immediately applied without any time lag
after the surface preparation.
Any equipment which has been given the shop coat of primer shall be carefully
examined after its erection in the field and shall be treated with a touch up coat
of red oxide primer wherever the shop coat has been abraded, removed or
damaged during transit/erection, or defaced during welding.
3.2.12.2
Finish painting
(a)
(b)
(c)
The primed surface shall be cleaned of dust/ dirt/ grease etc. without
scratching or in any way damaging the primer coat. Over this dry
Sheet 29 of 76
3.2.12.3
3.2.12.4
(d)
(e)
(f)
(g)
The dry film thickness (DFT) after the painting shall not be less than
150 microns.
Other requirements
(a)
(b)
The colour of the finish paint shall be as per approved colour coding
scheme
(c)
If finish paint was applied in shop, one coat of finish paint shall be
applied at site.
(d)
(e)
The pipes shall be colour painted/ banded for identification as per the colour
coding scheme approved by the Owner. These sheets shall be furnished
during detail engineering stage for approval.
3.2.13 Specification for hangers and supports
3.2.13.1
All supports and parts shall conform to the requirement of power piping code
ANSI B 31.1 or approved equivalent.
3.2.13.2
While designing supports for rubber lined pipes, special consideration should
be given. Any kind of welding on these pipes is not allowed after rubber lining.
Sheet 30 of 76
3.2.13.3
Hanger for piping 65mm NB and larger and all spring support assemblies
regardless of size shall be completely engineered in conformance with the
provision of power piping code ANSI B 31.1.
3.2.13.4
Hangers, saddles, supports etc. shall be capable of carrying the sum of all
concurrently acting loads and shall be fabricated from plates/ pipes sections
conforming to ASTM A 53 or equivalent. They shall be designed to provide the
required supporting effects and allow pipe line movements as necessary. The
structural steel work shall be as per IS:800/ BS:4360. Insulation protection
saddles shall be used at support point of all insulated piping.
3.2.13.5
3.2.13.6
3.2.13.7
Painting
All components of hangers/ supports shall be provided with two coats of
primer (red oxide paint) at shop before dispatch to site. After erection they
shall be given finish coat of Long oil synthetic enamel of total DFT 100 to 140
micron. CLH & VLH shall be primed with Epoxy Zinc Rich primer followed by
finish painting of Aliphatic Acrylic Polyurethane or equivalent of DFT 65
micron.
3.2.14
3.2.14.1
General
(a)
All valves shall be suitable for the service conditions i.e flow,
temperature and pressure, at which they are required to operate.
(b)
(c)
(d)
All rising stem valves shall be provided with back seat to permit
repacking (of glands) with valves in operation. All valves shall
preferably be of outside screw and yoke type.
Sheet 31 of 76
(e)
All valves shall be closed by rotating the hand wheel in the clockwise
direction when looking at the face of the handwheel. In case where the
handwheel is not directly attached to the valve spindle suitable gearing
shall be introduced.
(f)
All valves shall have indicators or direction clearly marked on the handwheel so that the valves opening/closing can be readily determined.
(g)
(h)
Gate/sluice valves shall be used for isolation of flow. Gate valves shall
be provided with the following accessories in addition to other standard
items:
1)
Hand wheel
2)
Position indicator
3)
(i)
(m)
Check valves shall be used for non-return service. They shall be swing
check type or Dual plate check type with a permanent arrow inscription
on the valve body indicating the fluid flow direction. In long distance
pipes lines with possibility of surge-occurrence, dual plate check valves
are preferable for its spring controlled opening/ closing of flaps/doors
against flow reversals.
(n)
All gate and globe valves shall be provided with back seating
arrangement to enable on line changing of gland packing.
(o)
All gate and globe valves shall be rising stem type and shall have limit
switches for full OPEN and full CLOSED indication wherever required.
This will include motor-operated valves also wherever required. In such
cases the limit switches shall form an integral part of the valve. Stopgap arrangement in this respect is not acceptable.
(p)
All valves shall be provided with embossed name plate giving details
such as tag number, type, size etc.
(q)
Sheet 32 of 76
3.2.14.2
All valves except those with rising stems, shall be provided with
continuous mechanical position indicators; rising stem valves shall
have only visual indication through plastic/metallic stem cover
End Connections
The end connections, shall comply with the following :
Socket welding (SW) - ANSI B 16.11
Butt Welding (BW) - ANSI B 16.25.
Threaded (SC) - ANSI B 2.1
Flanged (FL) - ANSI B 16.5& AWWA-C-207(steel flanges), ANSI B 16.1 (Cast
Iron flanges)
All cast iron\ ductile-Ni iron body valves (gate, globe and non-return) shall
have flanged end connections, (screwed ends for cast iron body valves are not
acceptable).
All steel and stainless steel body valves of sizes 65 mm and above shall have
flanged or butt weldings ends. Valves of sizes 50 NB and below shall have
flanged or socket welded ends. Compatibility of welding between valve body
material and connecting pipe material is a pre-requisite in case of butt-welded
joints.
All gun metal body valves shall have screwed ends.
Sheet 33 of 76
Check Valves
Check valves shall comply with the following characteristics:
(a)
For bore greater than 50 mm the valves must be swing check type or
dual plate check type suitable for installation in all positions (vertical
and horizontal);
(b)
(c)
In the case of swing check valves, the body seat shall be inclined at
such an angle from the vertical as will facilitate closing and prevent
chatter.
Globe Valves
The globe valves shall have the following characteristics:
Straight conveyed flow.
Right angle preferably, the valves shall be of the vertical stem type.
Globe valves shall preferably have spherical seating and discs shall be free to
revolve on the spindle.
The pressure shall preferably be under the disc of the valve. However, globe
valves, with pressure over the disc shall also be accepted provided (i) no
possibility exists that flow from above the disc can remove either the disc from
stem or component from disc (ii) manual globe valves can easily be operated
by hand. If the fluid load on the top of the disc is higher than 40-60 KN, bypass
valve shall be provided which permits the downstream system to be
pressurised before the globe valve is opened.
Sheet 34 of 76
Gate valves
All gate valves shall be of the full-way type, and when in the full open position
the bore of the valve shall not be constricted by any part of the gate.
Gate valves shall be of the solid/elastic or articulated wedge disc and rising
stem type.
3.2.14.7
3.2.14.8
The air release valves shall be of automatic double air valve with two
orifices and two floats. The float shall not close the valve at higher air
velocities. The orifice contact joint with the float shall be leak tight joint.
(b.)
(c.)
(d.)
Air release valves shall not have any integral isolation device within
them. Each Air release valve shall be mounted, preceded by a
separate isolation gate valve.
ASTM A 105
Disc
SS 410
Stem
SS 410
(b.)
Disc
Trim.
(c)
Sheet 35 of 76
Trim.
(e.)
(f.)
3.2.15
BS 1452 Gr. 14
BS 1452 Gr. 14
AISI 316
Back seat
13 % chromium steel
Trim.
-do-
Cast iron body valves shall have stainless steel stem and seat.
3.2.15.1
Sheet 36 of 76
Design of all vertical atmospheric storage tanks containing water, acid, alkali
and other chemical shall conform to API 650.
Design of all horizontal atmospheric storage tanks containing water, acid,
alkali and other chemicals shall conform to IS:2825 as regards to fabrication
and general construction taking care of combined bending, shear & hoop
stresses developed due to supporting arrangement.
Design temperature of vessels shall be 10 deg.C higher than the maximum
temperature that any part of the vessel is likely to attain during the course of
operation.
Tank shall be made from mild steel plates to BS 4360 (or equivalent).
The joint efficiency factors to be adopted for design calculations shall be in
accordance with the specified design code.
Tank shall be provided with suitable supporting joints. All vessels shall be
provided with lifting lugs, eye bolts etc. for effective handling during erection.
The material for flanges shall be of ASTM A 105.
For cylindrical tanks, the plates shall be cold rolled through plate bending
machine by several number of passes to true curvature.
Vessel seams shall be so positioned that they do not pass through vessel
connections. For cylindrical vessel consisting of more than two sections
longitudinal seams shall be offset.
Tanks shall be provided with float operated level indicators/level gauges/level
transmitters and level switches, as required, with complete assembly. Suitable
flanged pads for level switches mounting shall also be provided. The level
indicator can be top or side mounted as the case may be.
In addition to inlet and outlet nozzles, the tanks shall be provided with vents,
overflow, drain nozzles complete for various connections on tanks. Drains &
overflow lines from storage tanks shall be routed to the nearest surface
drains/plant drains. For tanks containing DM water, Alkaline water or Power
cycle water, the vent to atmosphere shall be through carbon-di-oxide absorber
vessel suitably mounted on the tank. CO2 absorber vessel shall be provided
with the initial fill of chemicals. Similarly for equipment cooling water overhead
tank, the overflow & drain from tank shall be combined together and shall be
led to nearest drain (at zero level) via. a seal-trough so as not to come directly
in contact with atmosphere.
Tanks shall have suitable stairs/ladders on inside and outside of the tanks,
manholes/inspection covers as required and also platform suitably located.
Sheet 37 of 76
3.2.15.3
Sheet 38 of 76
Outside surfaces of all other vessels shall be provided with two coats of primer
with three(3) coats of epoxy resin based paint of approved colour.
3.2.16
Strainers
3.2.16.1
Simplex Strainers
The strainers shall be basket type and of simplex construction. The strainer
shall be provided with plugged drain/blow off and vent connections. The free
area of the strainer element shall be at least six (6) times the internal area of
the connecting pipe lines. The strainer element shall be 20 mesh at full flow.
Strainers basket shall be suitably reinforced, to avoid buckling under
operation. Strainer shall have screwed blow off connection fitted with a
removable plug. The material of construction of various parts shall be as
follows:
3.2.16.2
(a)
Body
(b)
Strainer
(c)
End
connection
Duplex Strainers
The strainers shall be basket type and of duplex construction. The strainer
shall be provided with plugged drain/blow off and vent connections. The free
area of the strainer element shall be at least ten (10) times the internal area of
the connecting pipe. The mesh of strainer element shall be commensurate
with the actual service required.
Strainers shall be suitably reinforced. The material of construction of various
parts shall be as follows.
Body
50 NB & below
: ASTM A 105
65 NB & above : CI Gr. FG 260/MS to IS:2062 Gr.B
Strainer
End
connection
The strainer shall have a permanent stainless steel tag fixed on the strainer
body indicating the strainer tag number and service and other salient data.
Sheet 39 of 76
The size of the strainer and the flow direction shall be indicated on the strainer
body casting.
Thickness of the strainer element should be designed to withstand the
pressure developed within the strainer due to 100% clogged condition exerting
shut-off pressure on the element.
Two shop coats of paint preceded by two coats of primer shall be applied to all
exposed surfaces as required to prevent corrosion. All parts shall be
adequately protected for rust prevention. The use of grease or oil other than
light grade mineral oils for corrosion protection is prohibited.
3.2.16.3
Cleaning
Prior to factory inspection, all manufacturing waste such as metal chips,
fillings, debris and foreign matters shall be removed from the interior. All rust,
oil, grease, chalk, crayon, paint marks shall be removed from interior and
exterior surfaces.
3.2.16.4
Painting
Two shop coats of paint shall be applied to all exposed surfaces as required to
prevent corrosion, after release has been given for painting and despatch. All
parts shall be adequately protected for rust prevention. The use of grease or
oil other than light grade mineral oil for corrosion protection is prohibited.
4.0
ELECTRICAL ITEMS
Refer section II of the document.
5.0
6.0
CIVIL WORKS
Refer section IV of the document.
Sheet 40 of 76
SUB SECTION M2
TECHNICAL DATASHEET
MECHANICAL
Sheet 41 of 76
b. Fittings material
c. Flanges
i.
Pressure
range
ii. Construction
1. Bonnet/cover
2. Disc
- Gate valves
- Globe valves
- Check valves
iii. Ends
Sheet 42 of 76
vi. Hinge
pin/backseat/ ASTM A 182 Gr. F6a
stem guide
vii. Gland packing
F.
Safety Valves
a. Pressure class
150 # ASA
b. Service
c. Construction
i.
General
ii. Bonnet/cover
iii. Ends
on
seat
vii. Spring
viii. Nuts/bolts
H.
Sheet 43 of 76
Pressure class
b.
Size range
c.
d.
Service
150 # ASA
65 NB & larger
Raw water; filtered water
Construction
i. Bonnet/cover
ii. Disc
-
Gate valves
Solid wedge
Globe valves
Plug type
Check valves
Swing disc
iii. Ends
Flanged to ANSI-B16.5
iv. Stem
Stainless steel
v. Hinge pin/back
seat/stem guide
Bronze
Asbestos
Sheet 44 of 76
SECTION - II
TECHNICAL SPECIFICATION
(ELECTRICAL)
Sheet 45 of 76
NOT APPLICABLE
Sheet 46 of 76
SECTION - III
TECHNICAL SPECIFICATION
(CONTROL & INSTRUMENTATION)
Sheet 47 of 76
NOT APPLICABLE
Sheet 48 of 76
SECTION - IV
TECHNICAL SPECIFICATION
(CIVIL AND ARCHITECTURE)
Sheet 49 of 76
NOT APPLICABLE
Sheet 50 of 76
SECTION - V
APPENDICES TO SPECIFICATION
Sheet 51 of 76
NOT APPLICABLE
Sheet 52 of 76
SECTION - VI
PROPOSAL EXHIBIT SHEETS
Sheet 53 of 76
PROPOSAL PARTICULARS
SCHEDULE-II
TECHNICAL PARTICULARS
SCHEDULE-III
GUARANTEED DATA
SCHEDULE-IV
SCHEDULE-V
SCHEDULE-V I
SCHEDULE-VII
PART 2 (Commercial)
SCHEDULE-VIII
SCHEDULE-IX
SCHEDULE-X
SCHEDULE-XI
SCHEDULE-XII
SCHEDULE-XII
SCHEDULE-XIV
DECLARATION SHEET
Sheet 54 of 76
Sheet 55 of 76
PROPOSAL PARTICULARS
(SCHEDULE-1)
1.
2.
3.
4.
5.
6.
b) If so, give :
i) Registration Number
7.
8.
Terms of Payment
9.
a)
b)
c)
d)
10.
11.
12.
Sheet 56 of 76
Conformance
a) Is the equipment offered strictly in
conformance with the Purchasers Specification ?
b)
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 57 of 76
TECHNICAL PARTICULARS
(SCHEDULE-II)
This Performa is to be filled in by the Bidder of the piping system. Without these filled in
sheets, offers are liable to be rejected.
1.0
S.No
2.0
S.No
3.0
S.No
4.0
S.No
PIPE
Size (DN)
Material
Thickness (mm)
Quantity(M)
Pressure
Class
VALVES
Type
Size
(DN)
Material
Quantity
Pressure
Class
Cover
Construction
Disc
Stem
End
BENDS
Type
Size (DN)
Material
Quantity(M)
Pressure Class
Material
Quantity(M)
Pressure Class
REDUCERS/TEES/ENDS
Description
Size (DN)
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 58 of 76
GUARANTEED DATA
(SCHEDULE-III)
The guaranteed data, if any, shall be indicated by the bidder.
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :.......................
Sheet 59 of 76
Sl. No.
Description
Quantity Offered
1.
2.
3.
4.
5.
6.
7.
8.
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 60 of 76
Drawings
1.
2.
3.
4.
5.
6.
7.
The Bidder shall prepare this list separately for Approval and Reference category.
The Bidder shall also furnish the time in weeks for resubmission of reviewed/ commented
drawings from Purchaser from the date of receipt.
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 61 of 76
DEVIATION SHEET
PART A
(SCHEDULE-VI)
If the proposal has got any deviation from the Technical Specification, the Bidder shall
tabulate those deviations clause by clause in this Schedule. Add more sheets, if required.
Clause No.
Deviations
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 62 of 76
DEVIATION SHEET
PART B
(SCHEDULE-VII)
If the proposal has got any deviation from the tendering conditions and the Conditions of
Contract, the Bidder shall tabulate those deviations clause by clause in this Schedule. Add
more sheets, if required.
Clause No.
Deviations
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 63 of 76
Sheet 64 of 76
2.
3.
4.
5.
6.
7.
EURO/USD.
EURO/USD.
EURO/USD
EURO/USD.
EURO/USD.
EURO/USD.
(i) FOB
(ii) FOR
c) Insurance for all the
equipment as specified.
(i)
(ii)
FOB
FOR
8.
Sheet 65 of 76
EURO/USD
EURO/USD.......
9.
EURO/USD.
10.
11.
FOB Price
FOR Price
12.
13.
14.
EURO/USD....
FOB Price
FOR Price
EURO/USD....
EURO/USD....
15.
EURO/USD
:
:
b) If not, state:
i)
ii)
Sheet 66 of 76
15.
16.
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 67 of 76
Description
Price
(USD/EURO.)
F.O.B.
A.
F.O.R.
Amount
Description
(USD/EURO.)
F.O.B
F.O.R
CIF Position
SERVICES
Excise
Duty (USD/
EURO.)
SUPPLIES
Sl.
No.
B.
Sales
Tax
(USD/EURO.)
1)
Signature of Bidder
: ..........................................
Date : .......................
Designation :
Company Seal
The proposal price (Ex-factory price) shall include all taxes except VAT, custom duties if applicable and all other levies
already paid or payable on raw materials, components, sub-assemblies and other items used for manufacture of assembly
2)
3)
Sheet 68 of 76
of the item.
Regarding Sl. No. 3 and 4 of `A the prices of same shall not be considered for the tender evaluation.
Also bidder to quote separately the unit price of individual equipment for adjustment purposes.
Sheet 69 of 76
Description
Quantity
Unit Price
(Rs.)
FOB
A.
Total Price
(Rs.)
FOR
FOB
MANDATORY SPARES
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
FOR
Sheet 70 of 76
B. RECOMMENDED SPARES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 71 of 76
Sl. No.
Description
Quantity
Unit Price
(Rs.)
FOB
Total Price
(Rs.)
FOR
FOB
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
FOR
Sheet 72 of 76
Deviation, if any
Decrease
(Rs.)
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 73 of 76
Work Details
Name of
Purchaser &
Address
Order
Value
Date of
Commissioning
Signature
: .......................
Name
: .......................
SEAL OF COMPANY
Designation :........................
Sheet 74 of 76
DECLARATION SHEET
(SCHEDULE-XIV)
I, ........................................................... Certify
that all the above typed-in data and
information pertaining to this specification are
correct and are true representation of the
equipment covered by our formal Proposal
dated ................................
I, hereby certify that I am duly authorized
representative of the Bidder whose name
appears above my signature.
Bidders Name
.....................................................................
Authorized Representatives
Signature
.....................................................................
Authorized Representatives
Name (Typed)
.....................................................................
Manufacturers Intent
Authorized Representatives
Signature
.....................................................................
Sheet 75 of 76
SECTION - VII
TENDER DRAWING
Sheet 76 of 76
NOT APPLICABLE