1 113+000 Approved 7.4X5 Desa Road 41.742 41.742


2 113+131 Approved 2(3X2.5) Drainage Box 98.85 43.3 36.3 35.3 5
3 114+034 Approved 3X3.5 Drainage Box 49.63 46.3 5
4 114+475 Approved 4X2.5 Drainage Box 92.26 35 35
5 115+364 Approved 3X2.5 Drainage Box 105.28 51.15 51.15 51.15 7
6 115+443 Approved 3X3.5 Drainage Box 68
7 116+755 Approved 2(2X2) Drainage Box 51.53 23.7 23.7 5
8 116+818 Approved 2(2X2) Drainage Box 50.14 21.1 21.1 21.1
9 117+645 Approved 1(1.5X1.5) Drainage Box 78.996
10 117+750 Approved 2(3X2) Drainage Box 94.04 50.92 50.92 10
11 118+072 Approved 3X2 Drainage Box 107.43 72.53
12 118+170 Approved 2(3X2) Drainage Box 91.76 34.6
13 0+350 ACCES ROAD Corrected 8X4 Portal Pertamina 64
14 0+750 ACCES ROAD Corrected 7.4X5 Desa Road 41.158
CLASIFICATION
SUMMARY OF PROGRESS FOR BOX CULVERT AT ZONE 1 D (STA112+300 TO STA 118+400)
THE NUMBER OF
MAN POWER
STATUS
DRAWING
ACTUAL LENGTH OF CONCRETING (M)
STA NO
DIMENSION
(M)
TOTAL LENGTH
(M)
installation steel bar for wall 25.00%
Preparation to extend BC 38.46%
installation formwork for wall 23.32%
installation formwork for top slab 28.45%
concreting top slab 48.58%
no activity 0.00%
installation formwork for top slab 32.85%
laying for lean concrete (LC) 42.08%
no activity 0.00%
installation formwork for top slab 38.68%
installation formwork for top slab 16.88%
installation formwork for top slab 10.77%
no activity 0.00%
no activity 0.00%
PROGRESS TILL TO DATE
SUMMARY OF PROGRESS FOR BOX CULVERT AT ZONE 1 D (STA112+300 TO STA 118+400)
PERCENTAGE
(%)