AON Network Diagram for Prefabricated House Building



Path A:
Path B:

Path A also represents the critical path.













William Taylor Pittman 5/23/14



There are two identifiable paths to completion in this process, both of which are acceptable. Path A represents the most efficient path to
completion by performing activity B & C simultaneously. This can only be done if the resources are available however. Path A is also the critical
path representing each task in a logical order. Path B represents an approach taken by completing each activity separately even though B & C
can be performed in parallel. Personally, if the resources were available to perform tasks B & C concurrently, I would chose to go with path A for
the project.