Name of the list who will work Eid Holliday of Mechanical Section.
Mechanical Works in Eid Vacation
SL NO NAME OF THE LIST OF EMPLOYEES Designation 01 Belal hossain (mechanical foreman)
02 Sree Liton Kumar Mechanic 03 Md.Rofiquale Islam (Rony) Mechanic 04 Md. Amzad Hossain Mechanic 05 Md. Shafor Ali Mechanic 06 Md. Yousuf Ali (W.T.P). Asst. Mechanic 07 Md.Abdul kader Asst. Mechanic 08 Md. Moinul Islam Mechanic 09 Sree Ronjit Biswas Mechanic 10 Sree Ripon Goir Asst. Mechanic 11 Md.Sohag Hossain Asst. Mechanic 12 Md. Naybul Hossain Asst. Mechanic 13 Md.Sohel Roy Asst. Mechanic 14 Md. Sohorab Hossain Supervisor /m 15 Md.iqbal Hossain Operator WTP 16 Sree Kirsno Kumar Operator WTP 17 Sree Ajit Chandra Operator WTP 18 Md. Mostafizur Rahman Asst.Operator 19 Md . zakir hossain Mechanics SL NO NAME OF THE MACHINE MECHANICAL WORK`S 02 Stenter m/c Major Overhauling 03 Ferraro m/c Maintenance 04 Sliter m/c Maintenance Work 05 All Dyeing M/c Maintenance Work 06 Hydro Extractor Major Overhauling and cable tray making. 07 Boiler Maintenance& inside cleaning Work 08 Tube compacting &Dryer Maintenance 09 All Pipe Line`s Cable Tray And all M/C`S . Cleaning / painting 10 Modification of condensed recovery unit 11 Modification of PR station of steam line 12 Filter press installation 13 Two pcs flow meter installation in water line.
Utility (Boiler) SL NO NAME OF THE EMPOLAY Designation 1 Md.mosharof Boiler operator 2 Md. Amin Sharif Boiler operator 3 Md. momin Sharif Asst. Boiler operator
Boiler Works in Eid Vacation SL NO MECHANICAL WORK`S 1 Refractory wall checking 2 Fire Tube cleaning 3 Steiner and gas valve cleaning 4 Feed pump and water valve servicing 5 Open boiler manhole and inside cleaning 6 Gauge glass cleaning 7 Blower servicing 8 Burner servicing. 9
{N.B For stenter m/c overhauling works, need extra 10 person from production section. all works must be done within 8 days.}