CODIGO

CODIGO UNIDAD RENDIMIENTO PRECIO/TARIFA TOTALES


Albail H 0.32 5.05 1.616
Pen H 0.64 3.5 2.24
3.856
CODIGO UNIDAD MERMAS RENDIMIENTO PRECIO/TARIFA TOTALES
Encofrado ml 1.2 0.055 7.75 0.5115
Cemento kg 1.1 33 0.16 5.808
Arena m3 1.1 0.06 18 1.188
Ripio m3 1.1 0.055 18.75 1.134375
Soportes U 1.1 1 1 1.1
Lamina de polietileno m2 1.15 1 0.45 0.5175
Malla electro soldada (20x20 cm) diametro 4 mm m2 1.2 1 3.4 4.08
14.339375
CODIGO UNIDAD CANTIDAD PRECIO/TARIFA TOTALES
MAQUINARIA AUXILIAR % 3.856 0.03 0.11568
0.11568
CODIGO UNIDAD RENDIMIENTO PRECIO/TARIFA TOTALES
0
0
0
0
18.311055
C. INDIRECTO 18% 3.2959899
UTLIDAD 6% 0.19775939
21.8048043
JUSTIFICACIN
RENDIMIENTO MANO DE OBRA
1AL + 2P = 25m2 dia
Albail 8h 25m2 x = 0.32
xh 1m2
Albail 16h 25m2 x = 0.64
xh 1m2
Hormigon
Ripio 0.55 m3/m3 X 0.1 0.055
Arena 0.6 m3/m3 X 0.1 0.06
Cemento 330 kg/m3 X 0.1 33
MAQUINARIA/EQUIPO
MANO DE OBRA
TOTAL MANO DE OBRA
Contrapiso de hormign simple fc= 240 kg/cm2, 10 cm de espesor.
MATERIALES
TOTAL MATERIALES
TOTAL MAQUINARIA
TRANSPORTE
TOTAL TRANSPORTE
TOTAL COSTE DIRECTO
TOTAL PRECIO UNITARIO