Tel: (802)855-8091 www.engineeringvermont.com March 27 2013 ESVT Project No. 13003
NewBrook Elementary School 14 School Road Newfane, VT 05435
Attn: Christopher A. Pratt, Principal Re: Final-Energy Improvements Study
Dear Christopher:
The following final report has been prepared for new heating system alternatives for the New Brook Elementary School, located in Newfane, Vermont. I have also incorporated the questions and responses generated from the preliminary draft.
Questions and Responses:
1. Based on the figures you provided regarding actual fuel usage, the average fuel usage over the two years listed on pg. 3 is 6,939 gallons (vs. 9,684 gallons as indicated). Could you please help us understand the figure you provided?
Response: There was an error in the spread sheet, the report has been revised to correct this error, this includes revisions to the life cycle analysis.
2. As far as we call tell, alternatives #1 and #2 do not reflect the costs of correcting the current problems with the buildings heating control and distribution systems, which result in uneven distribution of heat. This is an issue that we would like to address, regardless of which alternative we choose. If we are correct in assuming that the figures for options #1 and #2 do not reflect these costs, could you provide us with adjusted figures that include the cost of correcting this problem?
Response: This is correct the cost to correct the current problems with the heating air distribution have not been included in alternative No. 1 and 2. We have included the costs to address these issues in the revised report. The costs included in the report include replacement ventilation and heating equipment and new building controls for both alternatives.
3. Alternative #3: On pg. 8, you recommend hiring a hydro geologist to identify the NewBrook Elementary School Page 2 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 earth thermal conductivity, potential groundwater impacts, and associated permitting issues. How much would you estimate such an assessment would cost?
Response: I would recommend obtaining a proposal for this work, there are several qualified consultants that could provide a proposal for these services. I would prefer not to provide an estimate.
4. Alternative #4:
a. Does the estimate you provided assume a system sized only to meet the additional electrical demand of having a geothermal system or the entire schools estimated electrical needs?
Response: The system utilized in the report is based on the information provided by the schools PV consultant. We utilized this data for a nominal 48 KW system which was projected to produce 62,000 Kwh per year. This system was sized to meet only the current electrical needs.
If it is the former, could you provide revised estimates that reflect a PV system sized to meet the schools overall estimated electrical demand?
The current annual electrical usage for the school is 64,888 Kwh with a peak demand of 30 KW. We project that the annual heat pump system electrical consumption would be 78,757 Kwh and the demand will increase to approximately 80KW. Based on this, the annual electrical energy consumption would essentially double, so for the purposes of this study we have doubled the PV system capacity. If this alternative proves to be something that the School is interested in pursuing in greater detail, then we would recommend more detailed analysis of the PV system alternatives and costs to confirm the costs utilized in this report.
b. What is the anticipated life cycle of the closed loop system vs. the wells?
Response: In our experience the primary effect on the life cycle cost between the two is the first cost. In general, the twenty year life cycle operating costs for a closed loop system is approximately 5% higher than a standing column well system. However, by nature wells are very unpredictable and can dissipate, vanish or reduce capacity during the life cycle. For the purposes of this study we recommend the closed loop system, however the results from the hydro geologist study may change this.
c. As I indicated in a previous email, there seems to be an error in the life cycle cost for this alternative. What is the correct figure?
NewBrook Elementary School Page 3 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Response: there was a typo. in the body of the letter, we have revised the life cycle costs and have increased the capacity of PV system.
5. Alternatives #3 & #4:
a. We understand that you assumed a 15-yr. study period when calculating life cycle costs. However, does this assumption reflect the actual life cycle of the geothermal system (options #3 and #4)? The cost figures cited in the appendix suggest a 15-yr. life cycle for options #1 and #2; it is our understanding that the life cycle of a geothermal system is generally 30 yrs. Is this correct? If so, could you revise your estimates so we are comparing apples to apples? Specifically, if a geothermal system will last 30 yrs. and the other systems 15 yrs., then the life cycle costs should reflect an initial capital investment and then the costs of replacing the boilers and pellet system after 15 yrs. Alternatively, the life cycle costs of the geothermal system could be reduced by 50% so we compare life cycle costs during the same 15 yr. period for all four options.
Response: The life cycle for the earth loop is 30 years however; the life expectancy of the heat pump units is in the 20 year range. Pellet boilers and oil boilers have an expected life of 25 years. Based on this, it is our opinion that the 15 year analysis is valid. We would be willing to run a , 20 or 30 year LLC analysis if requested.
b. It appears that the bore holes would encroach on the existing playground and into the property adjacent to the school. It also looks like they would come precipitously close to the septic system. Are we reading the map correctly? If so, are those concerns that you would have as well about this option?
Response: The bore holes would be completely buried (not exposed in playground), the final position of the bore field would need to be located and configured prior to final design. Please use this as a conceptual arrangement designed to show a potential configuration.
Purpose
The scope of this purpose of this report includes a detailed un-biased analysis of each of these the following heating system alternatives:
1. Replacement of the existing oil fired boilers with new equipment. 2. Installation of a wood pellet boiler system 3. Geothermal HVAC system 4. Geothermal HVAC system coupled with a photovoltaic system to offset the electrical consumption.
NewBrook Elementary School Page 4 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 This report will include conceptual level engineering analysis to identify the following for each alternative:
1. Develop a building heating load using recognized heating load methods. 2. Evaluate the specific details and loads to determine the implementation considerations for each alternative. 3. Develop a conceptual level design with sufficient detail to shown system arrangement capacity and to estimate the construction cost range for each alternative. 4. Prepare life cycle cost analysis for each alterative.
Existing Conditions:
General:
The building is an 18,050 square feet one-story; wood framed building serving approximately 140 students in the Kindergarten through grade 6.
The building consists of the original north part building and the south area of the building which was an addition to original the building. Each area of the building is provided with separate heating systems. The North Area houses a Multi-Purpose Room, Kitchen and approximately seven classrooms. The South Area of the building houses the Library, School Offices, Art and Music Classroom and Toilet Rooms. The two areas of the building are separated by a firewall.
Boiler Systems:
The existing school is provided with two boiler systems, each system acts independently. One serves the north original area of the school and the other serves the south addition
Original Building: The original boiler is a hot water HB Smith 25 Mills Boiler with a peak output capacity of 417,000 BTUH, this boiler provides space heating and includes a domestic water heating coil with an electric back-up water heater for summertime use. Based on our inspection it appears that this boiler is near the end of its useful life. The boiler is currently fired at 3.00 GPH. This system is provided with a three way hot way reset valve which was designed to vary the supply water to the system based on the outdoor air conditions.
Addition: The addition is provided with a Hot Water Peerless Boiler, with a Gross heat output of 286,000 BTUH. This boiler also provides heat for domestic hot water using an indirect fired water heater.
NewBrook Elementary School Page 5 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013
Heating and Ventilation Systems:
The original part of the building is served by a circulator pump, hot water supply and return distribution to all rooms. The classrooms and gymnasium are provided with unit ventilators. All classrooms are provided with exhaust, connected to a common rooftop exhaust fan.
The south addition is served by a single circulator pump with hot water distribution to room heating units. Ventilation is provided by an air to air heat recovery unit located in the attic.
Existing Heating Load and Heating Fuel Usage and Fuel Cost:
Based on Historical Fuel Usage the average annual fuel usage for the building is 6,983.3 gallons. Below is a summary of the historical fuel usage for the heating seasons 2010-2011 and 2009-2010.
Heating Season 2010-2011
Date Gallons
12/16/2011 854
12/16/2011 646
12/11/2011 2490.7
12/6/2011 1500.3
Total 5491
Heating Season 2009-2010
Date Gallons
12/1/2009 3056.4
12/1/2009 2814.4
3/17/2010 2515.8
Total 8386.6
Average Usage 6983.8 Gallons
Based on our calculations the peak heating load for this building is approximately 700,000 BTUH or a peak heating lad of 38.78 BTUH/ square foot.
For the purposes of this report we will be using a fuel oil cost of $3.50 per gallon and an annual heating cost of $24,443.30 per year.
NewBrook Elementary School Page 6 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013
Existing Electrical Usage and Cost:
Based on the 2011 billings provided, the electrical usage was 64,888 KWH, with a peak demand of 30 KW. The annual cost for electricity during the same time period was $10,555.44. The average energy cost for electricity at this school is $0.163/kwh. The electrical usage for this site was 3.594 Kwh/square foot. The following table provides detailed breakdown:
As requested we have prepared the following analysis for four alternatives this analysis includes evaluation of the specific details and loads to determine the implementation considerations, a conceptual level design with sufficient detail to shown system arrangement capacity and to estimate the construction cost range for each alternative. This analysis also includes a life cycle cost analysis for each of the flowing alternatives:
Alternative No. 1 - Replacement of Existing Boilers with New Equipment Alternative No. 2 - Install a Wood Pellet Boiler System Alternative No. 3 - Geothermal HVAC System Alternative No. 4 - Geothermal HVAC System with 96KW PV Array
NewBrook Elementary School Page 7 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Alternative No. 1 Replacement of Existing Boilers with New Equipment:
This alternative involves an analysis for providing two oil fired boilers located in the original boiler room to serve the entire heating load. Refer to Appendix 1 for design concept sketches and supporting construction cost estimate.
Implementation Considerations: Remove both Boilers and Breechings Remove existing three way hot water reset control valve. Provide two (2) oil fired Buderus G315-6 Section Oil Fired Boilers each with an output capacity of 395,000 BTUH each. Provide three new circulators, one for the original, one for the addition and one back up. Provide new boiler combustion and ventilation air system. Provide boiler staging and hot water reset control system. Estimated improved efficiency of 15% in system Replace Existing Ventilation Equipment and controls to correct operational and comfort issues.
Estimated Implementation Cost: $272,000 (Refer Appendix 1 for construction estimate)
Life Cycle Cost-Based on a 15 Year Study Period: $604,110 (Refer to Appendix 5 for detailed Life Cycle analysis)
NewBrook Elementary School Page 8 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Alternative No. 2 Provide Replacement Wood Pellet Boiler System:
This alternative involves an analysis for providing one pellet boiler located in the original boiler room to serve the entire heating load. Refer to Appendix 2 for design concept sketches and supporting construction cost estimate.
Implementation Considerations: Remove both Boilers and Breechings Remove existing three way hot water reset control valve. Provide one (1) 750,000 BTUH Wood Pellet Boiler and 37 ton Wood Pellet Silo Provide four (4) new circulators, one for the pellet boiler, one for the original building, one for the addition and one back up. Provide new boiler combustion and ventilation air system. Provide new wood pellet boiler control system. Replace Existing Ventilation Equipment and controls to correct operational and comfort issues
Estimated Implementation Cost: $402,820 (Refer Appendix 2 for construction estimate)
Estimated Annual Fuel Savings:
Fuel Cost: $240 per Ton Estimated Fuel Cost Savings: $11,742
Simple Payback: 34.3 Years
Life Cycle Cost-Based on a 15 Year Study Period: $610,925 (Refer to Appendix 5 for detailed Life Cycle analysis)
NewBrook Elementary School Page 9 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Alternative No. 3 Provide Geothermal Heat Pump System:
This alternative involves an analysis for providing a geothermal heat pump system with a total heating capacity of 620,000 BTUH or 52 tons of total heating capacity. The most critical part of utilizing this type of system is determining the method of earth coupling or geo-exchanger. The flowing summarizes the three basic methods, although other hybrid methods have been implemented: Closed Loop Slinky Piping and Buried Horizontal Pipe Systems: These systems consist of a horizontal closed loop system that generally require approximately 1,000 feet of piping per ton of capacity buried 4-10 feet deep, these systems typically include 500 foot long trenches with two pipes trenches are typically spaces 6-12 feet apart. The area required is typically in the 2,000 to 3,000 square feet per ton depending on soil properties. Slinky systems utilize approximately 1000 feet of high density polyethylene coiled piping that typical fits in a 100 foot long trench which provides approximately 1 ton of capacity. These systems typically require in the range of 500-800 square feet per ton. So based on the 52 tons of loads a buried horizontal pipe system would require a minimum of 26,000 feet or trench and 52,000 feet of pipe. For the Slinky system 5,200 feet of trench would be required. Closed Loop Vertical Piping: Typically these systems utilize a 300-400 foot deep well per ton of cooling with a capacity of approximately 1 ton per bore hole, so for this building a minimum 52 bore holes would be required. Bore holes are typically spaced approximately 25 feet apart. We have prepared a concept drawing for this layout in Appendix 3. Standing Column Wells-This type of Well systems consist of bore holes cased until bedrock is reached, a central pipe is dropped to form a core which he water in pumped up, water is return at the top around the suction pipe. A typical well would be in the 1,500 foot depth and would provide around 30 tons or 360,000 BTUH each, this site would require at least two 1,500 foot deep standing column wells, spaced at a minimum of 75 feet between the wells. We have prepared a concept drawing for this layout in Appendix 3.
The closed loop systems would require the system to be filled with an environmentally friendly propylene glycol installed within the piping system. These systems also require a grouting material around the pipe which adds to resistance to heat transfer.
Based on the above geo-exchanger alternatives we evaluated the site and determined that either a closed loop vertical system or a standing column well system would be the only feasible alternatives. We evaluated the approximate cost for each of these as follows:
Closed Loop Vertical: ($5,000 per ton) $260,000 Standing Column Wells: ($4,000 per ton) $208,000
Based on the fact that the geo-exchanger has not been sized, we have budgeted $300,000 for the geo-exchanger system. We recommend that a closed loop system be provided for NewBrook Elementary School Page 10 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 this site, unless the hydro geologist study reveals significant benefit to using the standing column well. The closed loop system avoids concerns with well depletion and future capacity concerns.
The well system should be separated from the drinking water well systems to avoid permitting issues related to wells, property and septic system setbacks. It is strongly recommended that before proceeding with the final design and implementation of a geothermal system that the final sizing and arrangement of the geo-exchanger involve a hydro geologist to identify the earth thermal conductivity, and potential ground water impacts and associated permitting issues.
Implementation Considerations: Remove both boilers and breechings and entire existing heating systems Replace all existing hot water unit ventilators in classrooms with geothermal classroom unit ventilators. Provide heat pump unit for Office Area Kitchen, Corridors, and Kitchen Provide new geothermal piping to all units including valves, insulation and balancing.
Estimated Implementation Cost: $789,525 (Refer Appendix 3 for construction estimate, includes geo-exchanger costs)
Estimated Annual Fuel Savings: $14,222
Simple Payback: 55.5 Years
Life Cycle Cost-Based on a 15 Year Study Period: $977,504 (Refer to Appendix 5 for detailed Life Cycle analysis)
NewBrook Elementary School Page 11 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Alternative No. 4 Provide Geothermal Heat Pump System coupled with a Photovoltaic System:
This alternative involves installation of the heat pump system described in Alternative No. 3 along with a photovoltaic system to offset electrical energy consumption.
Based on our estimates the table below shows the projected changes to the building electrical demand due to the installation of the heat pump system.
Existing TOD Demand Projected Increase in Demand Projected Total Demand Month (KW) (KW) KW Dec 26 38 64 Nov 24.8 30 55 Oct 25.2 24 49 Sept 24.4 14 39 Aug 18.4 0 18 July 16.4 0 16 June 24.8 0 25 May 26 18 44 April 28 26 54 Mar 27.6 36 64 Feb 29.2 42 72 Jan 30 45 75
The peak projected building electrical demand will increase from 30 KW to 75 KW with the heat pump system.
This analysis is based on installation of a 96 KW ground mounted non-tracking system with a single point connection to the existing electrical system. According to projections prepared by the solar consultant this system is projected to produce 124,000 Kwh annually. The estimated total annual electrical consumption for this building with the heat pump system is projected to be 125,668 Kwh per year.
Estimated Implementation Cost: Heat Pump System (See Alternative No.3) $789,525 (Refer Appendix 3 for construction estimate, includes geo-exchanger costs)
Solar System Cost Estimate $340,000 (Cost Estimate Provided by PV consultant, Refer to Appendix 4)
Total Estimated Implementation Cost $ 1,129,525
NewBrook Elementary School Page 12 Energy Improvement Study
Engineering Services of Vermont, LLC Final Report 3/27/2013 Estimated Annual Fuel Savings: Heating Fuel Savings $14,222 Electrical Energy Savings (Energy Usage Savings only $0.10/kwh at 124,000 kWh) $12,400
Total Savings $26,622
Simple Payback: 42.4 Years
Life Cycle Cost-Based on a 15 Year Study Period: $1,171,944 (Refer to Appendix 5 for detailed Life Cycle analysis)
Please review the findings of this study and call if you have any questions.
Respectfully, Engineering Services of Vermont
Daniel W. Dupras, P.E. Mechanical Engineer, Principal
Transmitted: Via Email
APPENDIX 1
REPLACE EXISTING BOILERS
JOB 11013 CLIENT NewBrook SHEET NO. 1 OF Project CALCULATED BY CHECKED BY Item Description Units Quantity Material Labor Total Alternative No.1-New Oil Boilers to Replace Existing and Correct Existing Comfort Issues A Preliminary Construction Estimate 1 Mechanical Demolition Ls 2 $0.00 $1,500.00 $3,000.00 New Boilers GB-315-6 Ea 2 $6,000.00 $2,500.00 $17,000.00 Burners Ea 2 $1,500.00 $250.00 $3,500.00 Controls Ea 1 $1,500.00 $1,000.00 $2,500.00 Breechings Ea 2 $1,000.00 $500.00 $3,000.00 Chimney Liner Ea 1 $5,000.00 $2,500.00 $7,500.00 Pumps Ea 3 $750.00 $250.00 $3,000.00 Wiring Ea 3 $250.00 $200.00 $1,350.00 Oil Piping Ea 2 $750.00 $250.00 $2,000.00 Interconnection Piping Lf 500 $15.00 $10.00 $12,500.00 Insulation Ls 1 $2,500.00 $1,500.00 $4,000.00 Boiler Comsbution Air System Ls 2 $1,000.00 $500.00 $3,000.00 Start-Up Ls 2 $0.00 $500.00 $1,000.00 Project Subtotal $63,350.00 2 Corrective Measures to Existing System Replace Unit Ventilators Ea 11 $3,000.00 $2,000.00 $55,000.00 Repiping and valves Ea 18000 $2.00 $1.00 $54,000.00 New Controls Sf 18000 $2.00 $1.00 $54,000.00 Wiring Ea 12 $750.00 $500.00 $15,000.00 Re-Balancing Ls 12 $0.00 $500.00 $6,000.00 Project Subtotal $184,000.00 Estimated MEP Subtotal $247,350.00 Recommended Contigency % 10.00% $24,735.00 ESTIMATED MEP TOTAL $272,085.00 Date: 2013-03-27 DWD DWD NewBrook Elem. School 128 Merchants Row, Suite 209 - PO Box 6562 Rutland, Vermont 05702-6562 (802)855-8091
APPENDIX 2
WOOD PELLET BOILER
ENGINEERING SERVICES OF VERMONT Project NewBrook Elementray School Date 3/27/2013 Prepared By Daniel W. Dupras, P.E. WOOD PELLET ANALYSIS Building Anaylsis Information Calculated Heatloss 620000 BTUH HDD 6800 DD Temp. Difference 85 Delta T CD Factor 0.61 Fuel Pellets Fuel Fuel Oil Pellet Density 40 Lbs/CF Heat Content 138000 BTU/lb Heat Content 8000 BTU/lb System Efficiency 75% System Efficiency 85% Fuel Cost $3.50 per gallon Fuel Cost.Ton $240.00 per Ton Yearly Estimate Use 7015.9 Gallons/Year Yearly Estimate Use 106785.88 Lbs/Year Tons/Year 53.4 Tons/Year Monthly Usage Estimate % Tons Used Cost Monthly Usage Estimate% Gallons Used Cost Jan 18.20% 9.7 $2,332.20 Jan 18.20% 1276.9 $4,469.12 Feb 16.60% 8.9 $2,127.17 Feb 16.60% 1164.6 $4,076.23 Mar 13.70% 7.3 $1,755.56 Mar 13.70% 961.2 $3,364.12 April 8.70% 4.6 $1,114.84 April 8.70% 610.4 $2,136.34 May 4.20% 2.2 $538.20 May 4.20% 294.7 $1,031.33 June 1.60% 0.9 $205.03 June 1.60% 112.3 $392.89 July 0.00% 0.0 $0.00 July 0.00% 0.0 $0.00 Aug 0.00% 0.0 $0.00 Aug 0.00% 0.0 $0.00 Sept 3.30% 1.8 $422.87 Sept 3.30% 231.5 $810.33 Oct 6.60% 3.5 $845.74 Oct 6.60% 463.0 $1,620.67 Nov 10.80% 5.8 $1,383.95 Nov 10.80% 757.7 $2,652.00 Dec 16.30% 8.7 $2,088.73 Dec 16.30% 1143.6 $4,002.56 100.00% 53.4 $12,814.31 100.00% 7015.9 $24,555.59 JOB 11013 CLIENT NewBrook SHEET NO. 1 OF 1 Project CALCULATED BY CHECKED BY Item Description Units Quantity Material Labor Total Alternative No.2 - New Wood Pellet Boiler System to Replace Existing Oil Boilers A Preliminary Construction Estimate 1 Mechanical Demolition Ls 2 $0.00 $1,500.00 $3,000.00 New Wood Pellet Boiler Ea 1 $60,000.00 $30,000.00 $90,000.00 Pellet Silo 37 ton Ea 1 $25,000.00 $7,500.00 $32,500.00 Concrete Pad for Silo Ls 1 $1,500.00 $1,000.00 $2,500.00 Pellet Auger Ls 1 $2,500.00 $1,000.00 $3,500.00 Controls Ea 1 $5,000.00 $2,000.00 $7,000.00 Breechings Ea 1 $1,000.00 $500.00 $1,500.00 UL 103HT chimney Ea 1 $7,500.00 $2,500.00 $10,000.00 Pumps Ea 4 $750.00 $250.00 $4,000.00 Wiring Ea 6 $500.00 $200.00 $4,200.00 Interconnection Piping Lf 500 $15.00 $10.00 $12,500.00 Insulation Ls 1 $5,000.00 $2,000.00 $7,000.00 Boiler Comsbution Air System Ls 1 $1,000.00 $500.00 $1,500.00 Start-Up Ls 2 $0.00 $1,500.00 $3,000.00 Project Subtotal $182,200.00 2 Corrective Measures to Existing System Replace Unit Ventilators Ea 11 $3,000.00 $2,000.00 $55,000.00 Repiping and valves Ea 18000 $2.00 $1.00 $54,000.00 New Controls Sf 18000 $2.00 $1.00 $54,000.00 Wiring Ea 12 $750.00 $500.00 $15,000.00 Re-Balancing Ls 12 $0.00 $500.00 $6,000.00 Project Subtotal $184,000.00 Estimated MEP Subtotal $366,200.00 Recommended Contigency % 10% $36,620.00 ESTIMATED TOTAL $402,820.00 Date: 2013-03-27 DWD DWD NewBrook Elem. School 128 Merchants Row, Suite 209 - PO Box 6562 Rutland, Vermont 05702-6562 (802)855-8091
APPENDIX 3
GEOTHERMAL HEAT PUMP SYSTEM
ENGINEERING SERVICES OF VERMONT Project NewBrook Elementray School Date 3/27/2013 Prepared By Daniel W. Dupras, P.E. GEOTHERMAL HEAT PUMP ANALYSIS Building Anaylsis Information Calculated Heatloss 620000 BTUH HDD 6800 DD Temp. Difference 85 Delta T CD Factor 0.61 Geothermal System Fuel Fuel Oil COP 3.5 Heat Content 138000 BTU/gallon Constant 3413 BTUH/KWH System Efficiency 75% Effciency Factor 350% Fuel Cost $3.50 per gallon Average Energy Cost $0.17 Cost/KWH Yearly Estimate Use 7015.9 Gallons/Year Yearly Estimated Use 60,788.1 KWH/Year Monthly Usage Estimate % KWH Cost Monthly Usage Estimate % Gallons Used Cost Jan 18.20% 11063.4 $1,880.78 Jan 18.20% 1276.9 $4,469.12 Feb 16.60% 10090.8 $1,715.44 Feb 16.60% 1164.6 $4,076.23 Mar 13.70% 8328.0 $1,415.75 Mar 13.70% 961.2 $3,364.12 April 8.70% 5288.6 $899.06 April 8.70% 610.4 $2,136.34 May 4.20% 2553.1 $434.03 May 4.20% 294.7 $1,031.33 June 1.60% 972.6 $165.34 June 1.60% 112.3 $392.89 July 0.00% 0.0 $0.00 July 0.00% 0.0 $0.00 Aug 0.00% 0.0 $0.00 Aug 0.00% 0.0 $0.00 Sept 3.30% 2006.0 $341.02 Sept 3.30% 231.5 $810.33 Oct 6.60% 4012.0 $682.04 Oct 6.60% 463.0 $1,620.67 Nov 10.80% 6565.1 $1,116.07 Nov 10.80% 757.7 $2,652.00 Dec 16.30% 9908.5 $1,684.44 Dec 16.30% 1143.6 $4,002.56 100.00% 60788.1 $10,333.97 100.00% 7015.9 $24,555.59 JOB 11013 CLIENT NewBrook SHEET NO. 1 OF 1 Project CALCULATED BY CHECKED BY Item Description Units Quantity Material Labor Total Alternative No.3 Geothermal System A Preliminary Construction Estimate 1 Mechanical Demoltion Ls 18000 $0.00 $0.75 $13,500.00 Geothemal Well System Ls 1 $200,000.00 $100,000.00 $300,000.00 Unit Ventilators and Heat Pumps Ea 16 $6,000.00 $3,000.00 $144,000.00 3 ton Office Area Heat Pump Ea 1 $12,000.00 $3,000.00 $15,000.00 Piping Ls 18000 $5.00 $3.00 $144,000.00 Insulation Ls 18000 $0.50 $0.25 $13,500.00 Controls Ea 18000 $2.00 $1.00 $54,000.00 Wiring Ea 17 $750.00 $500.00 $21,250.00 Pumps Ea 2 $1,500.00 $500.00 $4,000.00 Start-Up Ls 17 $0.00 $500.00 $8,500.00 Project Subtotal $717,750.00 Estimated MEP Subtotal $717,750.00 Recommended Contigency % 10.00% $71,775.00 ESTIMATED TOTAL $789,525.00 Date: 2013-03-27 DWD DWD NewBrook Elem. School 128 Merchants Row, Suite 209 - PO Box 6562 Rutland, Vermont 05702-6562 (802)855-8091