ProteksiPenyulang KoordinasiRelaiArusLebihGround PDF
ProteksiPenyulang KoordinasiRelaiArusLebihGround PDF
Penyaji :
Ir. Yanuar Hakim, MSc.
TRANSMISI
SISTEM
GENERATOR
BUS HV
GARDU
INDUK
TRAFO P.S
BUS TM
FEEDER
27-30 Mei 2002
1 2 3 DST
PERLU DIKOORDINASIKAN
RELAI PENGAMAN
OC + GF ANTARA FEEDER TM
DAN INCOMING TM PEMAKAIAN
SENDIRI
GF DI INCOMING TRAFO P.S DAN
PENGAMAN GANGGUAN TANAH DI
TRANSMISI
BUS HV
KOORDINASI PROTEKSI TM
DILAKUKAN DENGAN :
PENYETELAN ARUS TIAP FEEDER
DAN INCOMING BERDASARKAN ARUS
BEBANNYA MASING-MASING
BUS TM
1
2
FEEDER
DST
BUS HV
GANGGUAN TANAH DI TRANSMISI
RELAI TRANSMISI TRIP DENGAN ZONE 1
BUS TM
BETUL !! , TETAPI
RELAI GROUND DI P.S JUGA MENTRIPKAN
INI MENGGANGGU OPERASI KIT
1
2
FEEDER
DST
: PELAYANAN
SPESIFIKASI PMT,KONDUKTOR
RELEASE ...
UNTUK :
V = TEGANGAN SUMBER
Z = IMPEDANSI DARI SUMBER
KE TITIK GANGGUAN,
IMPEDANSI EKIVALENT
BIASANYA
FASA-FASA
FASA
8
SUMBER KIT
BUS
150 KV
DARI SISTEM
150 KV, P3B
AMBIL DATA
SCC LEVEL
HITUNG
Z SUMBER
27-30 Mei 2002
TRAFO
DAYA
DI GARDU
INDUK
AMBIL DATA
IMPEDANSI
MVA, KV dll
AMBIL
DATA Z
100%
BUS
20 KV
HITUNG
25% Z
Z POS.
Z NOL
HITUNG
50% Z
UNTUK
SIMULASI
LOKASI GANG.
HITUNG
75% Z
9
Trafo
unit
transmisi
KIT 1 Trafo
unit
KIT 3
transmisi
Trafo
unit
KIT 2
transmisi
G.I A
transmisi
10
KV 2
DAPAT DIHITUNG IMPEDANSI SUMBER
DENGAN RUMUS
MVA
MISALKAN SHORT CIRCUIT LEVEL DI BUS 150 KV G.I A = 500 MVA
MAKA, XS =
150 2
500
45 OHM
20 KV
20 KV
11
KV2 2
Z2
Z2
=
=
20 KV
0.8 OHM
20
150
2
2
x 45 OHM
12
PERHITUNGAN :
IMPEDANSI DASAR PADA TRAFO (100 % ) SISI 20 KV
ZB =
20 KV
10 MVA
= 40 OHM
REAKTANSI TRAFO = 10 %
XT = 10 % x 40 OHM
=
27-30 Mei 2002
4 OHM
13
= 40 OHM
14
DIHITUNG
DARI TABEL
PER KM
IMPEDANSI FEEDER
PANJANG FEEDER
x Z PER KM
25 %
ATAU
PER
15
50 %
75 %
100 %
16
IMPEDANSI Z0
25 %
50 %
75 %
100 %
17
INGAT HITUNGAN
IMPEDANSI SUMBER
=
INGAT HITUNGAN
IMPEDANSI TRAFO
TERGANTUNG
LOKASI GANG.
= j 4.8 + Z1 FEEDER
U/ %
PANJANG
IMPEDANSI Z1 , Z2 eki
25 %
50 %
75 %
100 %
18
Z0
% panjang x Z0 total
Kursus "Protection of Industrial Power Systems"
19
Z0 T + 3 RN + Z0 FEEDER
INGAT HITUNGAN
Z0 TRAFO
=
U/ %
PANJANG
INGAT TAHANAN
PENTANAHAN
TERGANTUNG
LOKASI GANG.
j 12 + 120 + Z0 FEEDER
IMPEDANSI Z0 eki
25 %
50 %
75 %
100 %
20
V
Z
I =
20.000/ 3
(0.3 + j 5.375)
IMPEDANSI MASIH
DALAM KOMPLEKS
KARENA DIAMBIL MAGNITUTE
I =
20.000/ 3
(0.32 + 5.3752 )
2144.9 AMPER
21
50 %
I =
75 %
I =
100 %
I =
20.000/ 3
(0.32 + 5.3752 )
20.000/ 3
(0.62 + 5.9502 )
20.000/ 3
(0.92
6.5252
20.000/ 3
(1.22 + 7.1002 )
2144.9 AMPER
1930.9 AMPER
1753.06 AMPER
1603.60 AMPER
22
RUMUSNYA : I =
V
Z
I =
20.000
2 x (0.3 + j 5.375)
IMPEDANSI MASIH
DALAM KOMPLEKS
KARENA DIAMBIL MAGNITUTE
I =
20.000
(2x0.3)2 + (2x5.375)2
1857.6 AMPER
23
50 %
I =
75 %
I =
100 %
I =
20.000
(2x0.3)2 + (2x5.375)2
20.000
(2x0.6)2 + (2x5.950)2
20.000
(2x0.9)2
(2x6.525)2
20.000
(2x1.2)2 + (2x7.10)2
1857.6 AMPER
1672.2 AMPER
1518.2 AMPER
1388.8 AMPER
24
I =
V
Z
IMPEDANSI MASIH
DALAM KOMPLEKS
3 x 20.000/ 3
(2x0.3 + 120.45)2 + (2x5.375 + 13.325)2
280.74 AMPER
25
I =
50 %
I =
75 %
I =
100 %
I =
121.35)2
+ (2x6.525 +
15.975)2
3 x 20.000/ 3
(2x1.2 + 121.8)2 + (2x7.10 + 17.3)2
= 280.67 A
= 277.23 A
= 273.79 A
= 270.35 A
26
LIHAT Ibeban
FEEDER 20 KV
SUMBER KIT
DARI SISTEM
150 KV, P3B
BUS
150 KV
TRAFO
DAYA
BUS
20 KV
25% Z
75% Z
50% Z
100% Z
SIMULASI
LOKASI GANG.
27-30 Mei 2002
27
DASAR HITUNG :
0.14 x tms
Ifault
Iset
0.02
- 1
NORMAL INVERSE
.t = WAKTU KERJA (DET)
.tms = TIME MULTIPLE SETTING
Kursus "Protection of Industrial Power Systems"
28
1
RATIO C.T
5
150
= 3.5 AMPER
27-30 Mei 2002
29
0.14 x tms
2144.9
105
0.02
- 1
.tms = 0.13
30
1
RATIO C.T
5
400
= 3.795 AMPER
31
0.14 x tms
2144.9
303.1
0.02
- 1
.tms = 0.2
27-30 Mei 2002
32
RATIO C.T
5
150
= 0.9 AMPER
33
0.14 x tms
280.67
27.04
0.02
- 1
.tms = 0.1
34
= 8% x 270.4 AMPER
= 21.63 AMPER
1
RATIO C.T
5
400
= 0.27 AMPER
27-30 Mei 2002
35
0.14 x tms
280.67
21.63
0.02
- 1
.tms = 0.26
27-30 Mei 2002
36
0.02
- 1
37
0.02
- 1
.t =
27-30 Mei 2002
0.14 x 0.13
2144.9
105
0.3
0.02
- 1
38
0.14 x tms
Ifault
Iset
0.02
- 1
.t =
27-30 Mei 2002
0.14 x 0.2
2144.9
303.1
0.7
0.02
- 1
39
GANGG. DI
% PANJANG
2 FASA 1 FASA
3 FASA
2 FASA
1 FASA
25 %
0.70
0.76
0.70
0.30
0.32
0.30
50 %
0.74
0.80
0.70
0.31
0.33
0.30
75 %
0.78
0.85
0.71
0.32
0.34
0.30
100 %
0.82
0.90
0.71
0.33
0.35
0.30
40
PERLU DILANJUTKAN
BAGIAN DARI I0
PENJELASANNYA ?
41