Question :
(TCO A) Platypus Building Inc. won a bid for a new office building
contract. Below is info from the project accountant:
Total Construction Fixed Price
Construction Start Date
Construction Complete Date
As of Dec 31
Actual cost incurred
Estimated remaining costs
Billed to customer
Received from customer
$8,000,000
March 3, 2012
December 4, 2013
2012
$2,500,000
$3,750,000
$2,400,000
$2,250,000
2013
$3,150,000
$$5,300,000
$5,400,000
Student Answer:
$2,000,000
$2,350,000
$1,650,000
$940,000
Instructor
Explanation:
Points Received:
5 of 5
Comments:
Question 2. Question :
Student Answer:
$85,000
$100,000
$175,000
$160,000
Instructor
Explanation:
Points Received:
Chapter 18.
5 of 5
Comments:
Question 3. Question :
(TCO A) Blue Suede Construction Corp used the percentage-ofcompletion method of revenue recognition. They were contracted to
build the new amphitheater for $4500000. Additional information was
provided:
As of Dec 31.
Percentage of completion
Estimated total expected costs
Gross profit recognized (Cumulative)
2012
35%
$3,750,000
$225,000
Student Answer:
$975,000
$2,340,000
$825,000
$1,027,500
Instructor
Explanation:
Points Received:
Comments:
Chapter 18
5 of 5
2013
60%
$3,900,000
$300,000
Question 4. Question :
Student Answer:
Instructor
Explanation:
Points Received:
Comments:
Chapter 18
5 of 5