Task Name
MULTI STOREYED BUILDING, COLOMBO
Duration
Duration(
(Working Calendar
Dates)
Dates)
885 days 1097 days
Start
Finish
5/26
Tue 10/22/13
Sat 10/22/16
June 1
6/9
PROJECT SUMMARY
Tue 10/22/13
Sat 10/22/16
MOBILIZATION
Mon 10/28/13
Sun 5/24/15
12
DEMOBILIZATION
17
PROCUREMENT
Sat 2/1/14
152
CONSTRUCTION
Fri 11/22/13
Sat 10/22/16
Fri 11/22/13
Tue 12/9/14
Fri 11/22/13
Tue 12/9/14
Tue 4/1/14
Sun 1/18/15
Mon 5/19/14
Tue 9/2/14
12 days 43 days
Mon 5/19/14
Mon 6/30/14
46%
Sat 7/5/14
40%
153
154
168
169
21 days 21 days
FOUNDATION/ SUBSTRUCTURE
Level -12000 to -5975 Lift Core/ Sheer Walls
Sat 9/10/16
171
Pile Hacking
8 days 48 days
Mon 5/19/14
172
Pile Testing
3 days 5 days
Thu 7/3/14
Mon 7/7/14
173
4 days 6 days
Fri 7/4/14
Thu 7/10/14
174
2 days 2 days
Wed 7/9/14
175
Screed Concrete
1 day 3 days
Fri 7/11/14
Mon 7/14/14
176
6 days 8 days
Tue 7/15/14
Wed 7/23/14
177
5 days 8 days
Tue 7/22/14
Wed 7/30/14
178
8 days 13 days
Sat 7/26/14
Thu 8/7/14
179
8 days 12 days
Sat 8/2/14
Wed 8/13/14
180
10 days 15 days
Wed 8/6/14
Thu 8/21/14
181
4 days 6 days
Thu 8/21/14
Wed 8/27/14
182
4 days 6 days
Wed 8/27/14
7/21
August 1
8/4
8/18
9/1
September 1
9/15
9/29
October 1
10/13
November
10/27
Fri 7/11/14
Tue 9/2/14
183
Tue 4/1/14
221
Tue 9/23/14
Sun 1/18/15
Wed 12/24/14
236
Wed 10/15/14
Sun 6/12/16
237
Wed 10/15/14
Mon 2/16/15
Critical
July 1
7/7
Wed 12/30/15
6/23
Sat 10/1/16
170
PS : Tue 10/22/13
PF : Sat 10/22/16
Progress Update
Summary
Milestone
Page 1 of 4
Task Name
252
Duration
Duration(
(Working Calendar
Dates)
Dates)
98.2 days 121 days
269
286
301
309
Level 04 to Level 05
330
Start
Finish
5/26
Tue 11/11/14
Wed 3/11/15
Tue 12/30/14
Sun 3/22/15
Mon 2/2/15
Mon 3/23/15
19 days 19 days
Mon 3/9/15
Sat 3/28/15
Tue 3/24/15
Mon 5/4/15
Level 05 to Level 06
Mon 3/30/15
Sat 5/16/15
353
Level 06 to Level 07
Tue 4/28/15
Thu 5/28/15
376
Level 07 to Level 08
Tue 5/12/15
Wed 6/10/15
399
Level 08 to Level 09
Sun 5/24/15
Mon 6/22/15
422
Level 09 to Level 10
Sat 6/6/15
Sun 7/5/15
445
Level 10 to Level 11
Thu 6/18/15
Fri 7/17/15
468
Level 11 to Level 12
Tue 6/30/15
Thu 7/30/15
491
Level 12 to Level 13
Mon 7/13/15
Wed 8/12/15
514
Level 13 to Level 14
Sat 7/25/15
Mon 8/24/15
537
Level 14 to Level 15
Sat 8/8/15
Sun 9/6/15
560
Level 15 to Level 16
Thu 8/20/15
Fri 9/18/15
583
Level 16 to Level 17
Tue 9/1/15
Wed 9/30/15
606
Level 17 to Level 18
Mon 9/14/15
Tue 10/13/15
629
Level 18 to Level 19
Sat 9/26/15
Mon 10/26/15
652
Level 19 to Level 20
Fri 10/9/15
Sun 11/8/15
675
Level 20 to Level 21
Wed 10/21/15
Fri 11/20/15
698
Level 21 to Level 22
Wed 11/4/15
Thu 12/3/15
721
Level 22 to Level 23
Mon 11/16/15
Tue 12/15/15
744
Level 23 to Level 24
Sat 11/28/15
Mon 12/28/15
767
Level 24 to Level 25
Fri 12/11/15
Sun 1/10/16
790
Level 25 to Level 26
Wed 12/23/15
813
Level 26 to Level 27
Wed 1/6/16
Sat 2/6/16
836
Level 27 to Level 28
Tue 1/19/16
Thu 2/18/16
859
Level 28 to Level 29
Sun 1/31/16
Sun 3/6/16
PS : Tue 10/22/13
PF : Sat 10/22/16
Critical
June 1
6/9
6/23
July 1
7/7
7/21
August 1
8/4
8/18
9/1
September 1
9/15
9/29
October 1
10/13
November
10/27
Sat 1/23/16
Progress Update
Summary
Milestone
Page 2 of 4
Task Name
Duration
Duration(
(Working Calendar
Dates)
Dates)
34.8 days 36 days
882
Level 29 to Level 30
905
928
Start
Finish
5/26
Thu 2/18/16
Thu 3/24/16
Tue 3/8/16
Thu 4/28/16
Sat 3/26/16
Mon 5/16/16
951
Thu 4/28/16
Sat 5/28/16
974
31 days 32 days
Thu 5/12/16
Sun 6/12/16
Mon 3/23/15
Sat 10/22/16
997
998
Basement 2
Mon 3/23/15
Fri 2/26/16
1012
Basement 1
Wed 4/29/15
Wed 3/2/16
1026
Ground Floor
Sat 5/16/15
Fri 6/17/16
1050
Level 01 - Parking
Thu 6/11/15
Thu 2/18/16
1072
Level 02 - Parking
Wed 7/1/15
Fri 2/19/16
1094
Level 03 - Parking
Tue 7/7/15
Sat 2/27/16
1116
Level 04 - Office
Thu 5/21/15
Thu 4/7/16
1141
Level 05 - Office
Wed 6/3/15
Thu 4/28/16
1166
Level 06 - Office
Mon 6/15/15
Thu 5/5/16
1191
Level 07 - Office
Sat 6/27/15
Tue 5/10/16
1216
Level 08 - Office
Fri 7/10/15
Sun 5/15/16
1241
Level 09 - Office
Wed 7/22/15
Tue 5/24/16
1266
Level 10 - Office
Wed 8/5/15
Wed 5/25/16
1291
Level 11 - Office
Mon 8/17/15
Mon 5/30/16
1316
Level 12 - Office
Sat 8/29/15
Sun 6/5/16
1341
Level 13 - Office
Fri 9/11/15
Fri 6/10/16
1366
Level 14 - Office
Wed 9/23/15
Wed 6/15/16
1391
Level 15 - Office
Tue 10/6/15
Mon 6/20/16
1416
Level 16 - Office
Sun 10/18/15
Sat 6/25/16
1441
Level 17 - Office
Sat 10/31/15
Sat 6/25/16
1466
Level 18 - Office
Fri 11/13/15
Thu 6/30/16
1491
Level 19 - Office
Wed 11/25/15
Wed 7/6/16
1516
Level 20 - Office
Tue 12/8/15
PS : Tue 10/22/13
PF : Sat 10/22/16
Critical
June 1
6/9
6/23
July 1
7/7
7/21
August 1
8/4
8/18
9/1
September 1
9/15
9/29
October 1
10/13
November
10/27
Mon 7/11/16
Progress Update
Summary
Milestone
Page 3 of 4
Level 21 - Office
Duration
Duration(
(Working Calendar
Dates)
Dates)
187.8 days 215 days
1566
Level 22 - Office
Mon 12/28/15
Thu 7/21/16
1591
Level 23 - Office
Sun 1/10/16
Tue 7/26/16
1616
Level 24 - Office
Sat 1/23/16
Mon 8/1/16
1641
Level 25 - Office
Tue 2/2/16
Sun 8/7/16
1666
Level 26 - Office
Tue 2/16/16
Fri 8/12/16
1691
Level 27 - Office
Fri 3/4/16
1716
Thu 3/24/16
Fri 8/26/16
1755
Sat 4/30/16
Fri 9/9/16
1794
Wed 5/18/16
Sat 10/22/16
1833
Common Finishes
Tue 9/15/15
Wed 8/31/16
Sat 10/24/15
Sat 10/15/16
Sat 10/24/15
Sat 9/3/16
1839
Task Name
EXTERNAL WORKS
Start
Finish
Tue 12/15/15
Sat 7/16/16
5/26
Faade Finishes
1846
60 days 63 days
Sat 5/28/16
Sat 7/30/16
1849
62 days 65 days
Thu 7/7/16
Sat 9/10/16
1851
Thu 7/7/16
Sat 10/15/16
78 days 80 days
Wed 8/3/16
Sat 10/22/16
Critical
June 1
6/9
6/23
July 1
7/7
7/21
August 1
8/4
8/18
9/1
September 1
9/15
9/29
October 1
10/13
November
10/27
Wed 8/17/16
1840
1856
PS : Tue 10/22/13
PF : Sat 10/22/16
Progress Update
Summary
Milestone
Page 4 of 4