Weekly Site Progress Report No.

8
Project Name : Burberry Boutique, Mall of emirates, Dubai
Location : MOE, Dubai
Reporting Period :
Weekly

Client : Burberry
Contractor/Sub Contractor :
From
13/12/14

Bond Interiors
To
18/12/14

Site Progress
No

Zone

Comments

Work

All Zone

wall cladding completed 85 %

G01.G02,G03,GO4,GO8.GO9,,
G011,GO12

Gypsum partition work on progress as per revice layout.

All Zone MEP

Progress as per final layout.

MEP- All Zone.

Fire fitting, Fire Alarm,music system cabling.

MEP All Zone

CCTV Counduting, FAHU Ducting, data Telephone conduting.

6
Major Achievements/Highlights for last week

Plan for the next week

G01 Ceiling suspention.

Ceiling suspension

MEP 2ND Fix.

painting

..

Safety Officer

Supervisor

Plumbers

electrician

mason

Gyps Carpenter

Painter

Helper

Total

Saturday
Sunday
Monday
Tuesday
Wednesday
Thurday
Friday

project Engineer

Day

RFI'S

Project Mgr.

Work Force as of Date

1
1
1
1
1
1
0

1
1
1
1
1
1
0

1
1
1
1
1
1
0

1
1
1
1
1
1
0

5
5
5
5
5
4
0

5
5
5
7
8
10
0

4
4
4
4
4
4
0

7
10
10
10
12
19
0

0
1
0
4
8
4
0

2
2
2
4
4
5
0

27
31
29
38
45
50
0

VN 01 - Fire alarm contract

Mall TVR - Duct & CHW shifting

Mall TVR -DB & Water meter shifting

Issued

..

Returned

Pending

Burberry @ MOE - Weekly site progress photos - Dated 16th December 2014

G01- MEP & Partition work on progress

G02 -Partition work completed

Burberry @ MOE - Weekly site progress photos - Dated 16th December 2014

G01- MEP work on progress

G05- A/C duct & MEP work on progress