Department :

Process :

Project
General / Temporary Work
HAZARD IDENTIFICATION

SEQUENCE OF
JOB STEP

BASIC
HAZARD GROUP

HAZARD

EFFECT

1) Constructing pile cap


2) Installation of J-bolt manually

Physical

1) Struck against J-bolt

1) Hand injury

Ergonomic

2) Lifting heavy object

1) Arm and shoulder pain

Ergonomic
Ergonomic

3) Awkward movement
4) Forceful grip of the J-bolt

1) Muskuloskeletal disorder
1) Inflammation of tendons and / or
tendon sheaths of the fingers

1) Awkward position

1) Muskuloskeletal disorder

2) Hand grip of screw driver machine vibration

1) Inflammation of tendons and / or


tendon sheaths of the fingers

3) Struck by / against screw driver


machine

1) Hand injury

Physical

1) Struck by mast

1) Serious bodily injury

Physical

2) Struck against mast

1) Serious bodily injury

3) Struck by mobile crane

1) Serious bodily injury

Ergonomic

1) Manual handling

1) Hand injury

Ergonomic

2) Awkward movement

1) Muskuloskeletal disorder

Physical

1) Fall from height

1) Death

Physical

2) Struck by falling jib

1) Serious bodily injury


2) Death

Physical

1) Struck by falling counterweight

1) Serious bodily injury

3) Installation of sportlight and warning Ergonomic


light manually using screw driver
machine
Ergonomic

4) Erection of mast using mobile crane

5) Tie up pile cap and J-bolt

6) Install jib

7) Install counterweight

2) Death
8) Install operator room

Physical

1) Struck by falling operator room

1) Serious bodily injury


2) Death

9) Install steel cable to counterweight


and jib

Physical

1) Fall from height

1) Death

10) Jacking up tower crane

Physical

3) Noise

1) Tinnitus

Physical

Psychological

2) Permanent hearing loss

4) Noise (Non-auditory effects)

1) Loss of concentration
2) Stress

Physical

2) Struck by falling crane component

1) Serious bodily injury


2) Death

Physical

3) Fall from height

Physical

4) Struck against hand tools

1) Serious bodily injury


2) Death
1) Hand injury

Task / Activity :
Job Title Analysed :
Analysed by :

Installation of Tower Crane


Site supervisor
Farah Esran
RISK ASSESSMENT

EXISTING
CONTROL

ADEQUATE Y /
N

FREQ

SEV

RISK SCORE

RISK
CLASSIFICATIO
PROPOSED
N
RISK CONTROL

Refer to Pile Cap


1) Safety briefing

2) Safety helmet

3) Gloves
4) Safety shoes

Y
Y

3
3

2
2

6
6

M
M

1) Safety briefing

2) Safety helmet

3) Gloves

16

2) Safety helmet

16

3) Gloves
4) Safety shoes

16

4) Safety shoes

1) Safety briefing

1) Safety briefing

1) Safety briefing

25

4
4

4
5

16
20

H
H

20

25

10

2) Safety helmet
3)Gloves
4) Safety belt
5) Safety shoes

1) Safety briefing

1) Safety briefing

RISK CONTROL

1) Safety briefing

20

1) Safety briefing

2) Barricade area

3) Safety helmet

16

20

4
4
3

4
5
3

16
20
9

H
H
M

4) Safety belt
5) Gloves

6) Safety shoes
Y
Y

RISK CONTROL
PIC

TARGET DATE