Subject:

Reliability & Redundancy Check

Project:

Prepared by:

DSV

Date:

11/2/1997

UBC 1630.1.1
considering Dual System
For Shearwall (x - direction)
AB = 1058.75 m2

AB = the ground floor area of structure or may be taken as the average


floor area in the upper setback portion of the bldg. where a large

Lw =

8.3

base area exists at the ground floor


Lw = length of wall along x-direction

m.

V = 11087.4 KN

V = base shear

Solving for rmax @ shearwall


Ground floor:
Vw = 26966.8 KN

ri

= (3.05Vw / Lw) / V

0.89

Second floor:
Vw = 8294.79 KN

ri

= (3.05Vw / Lw) / V

0.27

Use rmax

ri

= element story shear ratio

rmax = the maximum element-story shear

= 0.894

(30-3)
SI system:

English system:

= 2-

6.1
rmax AB

But for dual system, the value of

80% x

1.79

For Shearwall (y - direction)


Lw =
3.25
m.

1.79

= 2-

20
rmax AB

need not exceed 80% of (shearwall)

1.43 > 1.0

adopt computed p

= 1.43

Lw = length of wall along y-direction

Solving for rmax @ shearwall


Ground floor:
Vw = 9823.56 KN

ri

= (3.05Vw / Lw) / V

0.83

Second floor:
Vw = 1461.67 KN

ri

= (3.05Vw / Lw) / V

0.12

Use rmax

= 0.831

= 2-

6.1
rmax

AB

= 1.775

Page 1 of 6

266718103.xlsdual system

But for dual system, the value of

80% x

1.775 =

need not exceed 80% of (shearwall)

1.42 > 1.0

= 1.42

adopt computed p

For SMRF (considering 1/3 height)


Solving for rmax along x - direction:
Ground floor:
Vw1 = 630.74 KN
Vw2 = 624.294 KN
%Sw =
25%

Vw1-2 = shear of two adjacent columns in a moment frame bay


%Sw = 25% are used since shearwall carries 75% of baseshear

Ground floor:
Vw1 = 183.854 KN
Vw2 = 121.044 KN
%Sw =
25%
rmax

ri

= (Vw1 + Vw2 )/ (%SW x V)

0.45

ri

= (Vw1 + Vw2 )/ (%SW x V)

0.11

= 0.453 for x-direction

Solving for rmax along y- direction:


Ground floor:
Vw1 = 562.166 KN
Vw2 = 568.854 KN
%Sw =

25%

Use rmax

= (Vw1 + Vw2 )/ (%SW x V)

0.41

ri

= (Vw1 + Vw2 )/ (%SW x V)

0.38

KN

Ground floor:
Vw1 = 538.824 KN
Vw2 = 509.564 KN
%Sw =
25%
KN
rmax

ri

= 0.408 for y-direction


= 0.453

= 2-

6.1
rmax

AB

= 1.586

> 1.25 for SMRF

; use p = 1.25

<1.5 for Dual System


; use p = 1.5
shall not be taken less than 1.0 and need not be greater than 1.5

=
=

shall not exceed 1.25


For structure located in Seismic Zone 0, 1 or 2, shall be taken to 1.0
For SMRF except when used in dual system,

Page 2 of 6

266718103.xlsdual system

therefore:

= 1.50

Page 3 of 6

266718103.xlsdual system

he ground floor area of structure or may be taken as the average

oor area in the upper setback portion of the bldg. where a large

ase area exists at the ground floor

element story shear ratio

he maximum element-story shear

Page 4 of 6

266718103.xlsdual system

= 1.25
= 1.50

Page 5 of 6

266718103.xlsdual system

Page 6 of 6

266718103.xlsdual system