Task

Task Name

Duration

Start

Finish

Mode
1

Temporary OHL Mast & Back Tie

55 days

24/7/13

25/9/13

Workshop for Edoc & Operation Team

10 days

24/7/13

3/8/13

First Submission of Edoc & Method Statement

2 days

5/8/13

6/8/13

The Engineer's Review and Comment

6 days

7/8/13

13/8/13

Final Submission of Edoc & Method Statement

2 days

14/8/13

15/8/13

The Engineer's Approval

6 days

16/8/13

22/8/13

Confirmation of CNP Consultant


Application of CNP for Night Works
EPD approve and issue CNP
Tree Fall & Transport (Partial)
Forming Temporay Access for Mobile Crane

1 day
7 days
28 days
21 days
3 days

31/7/13
1/8/13
9/8/13
20/8/13
13/9/13

31/7/13
8/8/13
10/9/13
12/9/13
16/9/13

Fabrication Works

17 days

1/8/13

20/8/13

1 day
4 days
1 day
7 days
3 days
1 day

1/8/13
2/8/13
7/8/13
8/8/13
16/8/13
20/8/13

1/8/13
6/8/13
7/8/13
15/8/13
19/8/13
20/8/13

29 days

23/8/13

25/9/13

7
8
9
10
11
12
13
14
15
16
17
18
19

Confirmation of Fabricator / Sub-Contractor


Purchasing Steel Materials
Sampling and Testing
Fabrication & NDT Test
Hot-Dip Galvanization
QC Inspection and Dimension Checking
Night Works (1:30am to 4:30am)

20

Setting out on Site & The Engineer's Checking

1 day

23/8/13

23/8/13

21

Erect Working Platform and Drill anchor holes at TM1 & BT1

1 day

11/9/13

11/9/13

22

Erect Working Platform and Drill anchor holes at TM2, BT2 & Protective
1 day Fence

12/9/13

12/9/13

23

Erect Working Platform and Drill anchor holes at TM3 & BT3

13/9/13

13/9/13

24

Insert Chemical Anhors On top Existing Retaining Works at TM1, TM2,


1 day
TM3, BT1,14/9/13
BT2 & BT3

14/9/13

25

Install Back Tie BT1, BT2 & BT3

16/9/13

26

Set up 80Ton mobile crane at Hin Keng Playground; Trial Lift 1and
dayInstall OHL
17/9/13
Mast TM1 17/9/13

27

Lift and Install OHL Mast TM2, TM3 & Protective Fence by use of 80Ton
1 day mobile Crane
18/9/13

18/9/13

28

Survey Checking - verticality and position

1 day

19/9/13

19/9/13

29

Fixing formwork for grouting to base plate

2 days

20/9/13

21/9/13

30

Mixing non-shrink grout and grouting to base plates

2 days

23/9/13

24/9/13

31

Removal of Grouting Formwork and general site cleaning

1 day

25/9/13

25/9/13

Project: Short Term Program for Temporary OHL Mast & Back Tie
Date: 25/7/13

1 day

1 day

16/9/13

22 Jul '13
T

5 Aug '13
S

19 Aug '13
F

2 Sep '13
S

Task

External Tasks

Manual Task

Finish-only

Split

External Milestone

Duration-only

Deadline

Milestone

Inactive Task

Manual Summary Rollup

Progress

Summary

Inactive Milestone

Manual Summary

Project Summary

Inactive Summary

Start-only
Page