Task
Task Name
Duration
Start
Finish
Mode
1
55 days
24/7/13
25/9/13
10 days
24/7/13
3/8/13
2 days
5/8/13
6/8/13
6 days
7/8/13
13/8/13
2 days
14/8/13
15/8/13
6 days
16/8/13
22/8/13
1 day
7 days
28 days
21 days
3 days
31/7/13
1/8/13
9/8/13
20/8/13
13/9/13
31/7/13
8/8/13
10/9/13
12/9/13
16/9/13
Fabrication Works
17 days
1/8/13
20/8/13
1 day
4 days
1 day
7 days
3 days
1 day
1/8/13
2/8/13
7/8/13
8/8/13
16/8/13
20/8/13
1/8/13
6/8/13
7/8/13
15/8/13
19/8/13
20/8/13
29 days
23/8/13
25/9/13
7
8
9
10
11
12
13
14
15
16
17
18
19
20
1 day
23/8/13
23/8/13
21
Erect Working Platform and Drill anchor holes at TM1 & BT1
1 day
11/9/13
11/9/13
22
Erect Working Platform and Drill anchor holes at TM2, BT2 & Protective
1 day Fence
12/9/13
12/9/13
23
Erect Working Platform and Drill anchor holes at TM3 & BT3
13/9/13
13/9/13
24
14/9/13
25
16/9/13
26
Set up 80Ton mobile crane at Hin Keng Playground; Trial Lift 1and
dayInstall OHL
17/9/13
Mast TM1 17/9/13
27
Lift and Install OHL Mast TM2, TM3 & Protective Fence by use of 80Ton
1 day mobile Crane
18/9/13
18/9/13
28
1 day
19/9/13
19/9/13
29
2 days
20/9/13
21/9/13
30
2 days
23/9/13
24/9/13
31
1 day
25/9/13
25/9/13
Project: Short Term Program for Temporary OHL Mast & Back Tie
Date: 25/7/13
1 day
1 day
16/9/13
22 Jul '13
T
5 Aug '13
S
19 Aug '13
F
2 Sep '13
S
Task
External Tasks
Manual Task
Finish-only
Split
External Milestone
Duration-only
Deadline
Milestone
Inactive Task
Progress
Summary
Inactive Milestone
Manual Summary
Project Summary
Inactive Summary
Start-only
Page
16 Sep '13
F
30 Sep '13
S