Activity

Hoarding and site set up


Remove topsoil and vegetation
Excavate strip foundations and drainage trenches
Concrete strip foundations
Lay and backfill drainage
Hardcore
Brick below DPC
Concrete slab (GF)
Screed and insulation
Timber frame (GF)
Internal blockwork partitions
Scaffolding
Floor joists to first floor
Chipboard, insulation and staircase to first floor
External blockwork
Timber frame and internal partitions (1st F)
Scaffolding
Floor joists to second floor
Chipboard, insulation and staircase to second floor
External brickwork
Roof trusses and rafters
Insulation at eaves
Pantiles
Loft insulation
Internal partitions
1st fix electrical
1st fix plumbing
Fix doors and windows
Plasterboard
2nd fix electrical
2nd fix plumbing
Rendering
Hang doors, skirting and architrave
Handover

Aprox. QUnit
m
m
m
m
m
266.50 m
m
m
m
m
m
m
m
m
m
m
m
m
n
n
m
n
n
n
m
n
n
m
n

Trade
craftsman
unskilled operative
unskilled operative
semi-skilled operative
semi-skilled operative
unskilled operative
bricklayer and unskilled operative
semi-skilled operative
craftsman
craftsman
bricklayer and unskilled operative

ResoMethod and plant selection


Out
4 OSB on 100x50 frame
2 Cut down trees and remove topsoil
1 excavate trenches 0,80m depth to
3 1 crawler crane, 2 concrete skips
2 hydraulic excavator to make space
2 Tractor loader and vibrating roller
3 the bricks are laid by hand and the
3 1 crawler crane, 2 concrete skips
5
5
3

craftsman
craftsman
bricklayer and unskilled operative
craftsman

5
5 25mm of chipboard, labour hours
3
0 0
5
0 0

craftsman
craftsman
bricklayer and unskilled operative
craftsman
insulation professionals
craftsman
insulation professionals
craftsman
craftsman
craftsman
craftsman
craftsman
craftsman
craftsman
craftsman
craftsman

5
0 0
5 25mm of chipboard, labour hou 0
3
0 0
5
clay tiles
5
2
2
5
5
2
2
2
3

0
0

0
0

Duration (days)
4
1
1
2
1
2
5
2
3
14
10
5
10
10
14
5
10
10
5
10
4
15
15
10
30
7
7
30
30