Objective

Auxbay 1 Main Supports


Auxbay 1 Take Off Supports
Auxbay 2 Take off Supports
CDD Pump house Supports
Platform Bypass Pit
Compressor house North Inside

Objective Completion
Date
30-Oct-14
30-Nov-14
15-Oct-14
15-Oct-14
15-Oct-14
30-Oct-14

Old Acces
Date

2-Sep-14
30-Jul-14

Latest Access
Date

30-Sep-14
30-Oct-14

SVK Schedule
Completion Date
14-Nov-14
26-Nov-14
16-Oct-14
20-Oct-14
10-Oct-14
3-Feb-15

Variance between
Objective completion
& Schedule
Completion Date
-11.79
3.14
-0.79
-3.93
3.93
-75.43

Comments

Installation Put on Hold by ESKOM


Excluding Above Zero Meter
Baseline Completion also 16 Oct 14