DATOS DE AVANCE

CONST. NVA INFRAEST. DE NIVELES INIC. Y PRIM. CASERIO CEDRO HUARMACA.

INICIO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
SEPTIEMBRE

AVANC PROG AV. EJEC. ACUM.


3.78
5.38
19.63
25.20
15.85
45.14
12.95
63.03
21.42
85.08
26.37
100.00
100.00

SITUACION DE OBRA

AV. PROG.ACUM.
3.78
23.41
39.26
52.21
73.63
100.00

CULMINADA

AVANC EJEC
###
5.38
19.82
19.94
17.89
22.05
14.91

100.00%

CRONOGRAMA DE AVANCE PROGRAMADO VS EJECUTADO


CONSTRUCCION INFRAESTRUCTURA EDUCATIVA CASERIO CEDRO-HUARMACA
100.00

100.00
100.00

90.00
85.08

80.00
73.63

70.00
63.03

60.00

52.21

50.00
45.14

40.00

39.26

30.00
25.20
23.41

20.00

10.00
5.38
3.78

--

INICIO

ABRIL

MAYO

JUNIO

JULIO

AGOSTO

SEPTIEMBRE