METHOD STATEMENT FOR

SUPERSTRUCTURAL CONCRETE
ACTIVITIES
Form No: QC-Statement

Rev. No: 00

Date:10/10/2004

Document No:QM
No. of Pages : 3

SCOPE :

THIS METHOD STATEMENT WILL COVER SUPERSTRUCTURAL


CONCRETE ACTIVITIES STARTING FROM BASEMENT FLOOR AND
ABOVE AS FORMWORK STEEL REINFORCING AND CONCRETE
PLACEMENT . BASED ON CONTRACT SPECIFICATIONS, CONTRACT
DRAWINGS, AND APPROVED SHOP DRAWINGS.

CIVILCO WILL PROVIDE ALL REQUIRED MATERIALS AND


CERTIFIED EQUIPMENT FOR CONSULTANT APPROVAL TO CONDUCT
THESE ACTIVITIES .

PROCEDURE :

1)
CIVILCO SHALL SUBMIT SHOP DRAWINGS FOR; FORMWORK,
STEEL REINFORCEMENT AND BARPENDING SCHEDULE SHOWING
THE SIZE, SPACING, LOCATION, QUANTITIES AND DETAILS FOR IT
AND ALL REQUIRED SHUTTERING FOR CONSULTANT APPROVAL.
2)
CIVILCO SHALL SUBMIT SAMPLES OF THE ACCESSORIES TO BE
EMBEDED IN THE CONCRETE SUCH AS; SHEAR DOWELS, WATER
STOPS, WATER BARS, AND / OR INSERT PLATES FOR CONSULTANT
APPROVAL.
3)
THE SURFACE BASE OF COLUMNS AND / OR WALLS SHALL BE
CLEANED AND MADE ROUGH TO MAINTAIN A BOND THE NEW AND
OLD CONCRETE.

4)
THE STEEL REINFORCEMENT FOR THE VERTICAL ELEMENTS
SHALL BE INSTALLED AS PER APPROVED SHOP DRAWINGS AND IT
5)
SHOULD BE SUPPORTED IN SUCH A WAY TO ENSURE THE
SPACING AND COVER IS ACCURATELY MAINTAINED AND IT WILL NOT
BE DISPLACED DURING CONCRETE PLACING.
6)
ALL STEEL BARS WILL BE CLEANED FROM OIL, DUST, AND
DIRT.
7)
LAND SURVEYOR SHALL MARK THE EXCAT LOCATION OF ALL
ELEMENTS OF FORMWORK AS PER APPROVED SHOP DRAWINGS.
8)
ONE SIDE OF THE FORMWORK FOR THE VERTICAL ELEMENTS
SHALL BE KEPT OPENED FOR INSPECTION PURPOSE.
9)
MEP SHOULD INSTALL ALL THEIR ITEMS AND / OR LEAVE THE
REQUIRED OPENING AS PER APPROVED SHOP DRAWINGS AND ITS
TYPICAL DETAILS.
10)
ALL INSERTS SUCH AS; BOLTS, WALL PLATES, ANCHORS, AND
HANGERS AND / OR ANY OTHER KINDS OF FASTNERS REQUIRED TO
BE INSTALLED AT EXACT LEVEL AND LOCATION.
11)
ALL FORMWORK TO BE IN DIRECT CONTACT WITH CONCRETE
SHALL BE TREATED WITH A SUITABLE RELEASE AGENT , ALL
RUBBISH SHOULD BE REMOVED FROM INTERIOR OF THE FORMS .
12)
JOINT INSPECTION BETWEEN CIVILCO & CONSULTANT SHALL
BE CONDUCTED TO APPROVE CLOSING THE SHUTTERING .
13)
FORMWORK SHALL BE CLOSED AND COMPLETED , IT SHOULD
BE RIGID AND STRUCTURALY SAFE , JOINTS SHALL BE CLOSED AND
SECURED TO AVOID ANY BLEEDING OF CONCRETE DURING
CONCRETE PLACEMENT .
14)
JOINT INSPECTION BETWEEN CIVILCO & CONSULTANT SHALL
BE CONDUCTED TO APPROVE PLACING CONCRETE FOR THE
VERTICAL ELEMENTS .
15)
CONCRETE SHALL BE PLACED UP TO THE REQUIRED LEVELS
AS PER APPROVED SHOP DRAWINGS .
16)
CIVILCO WIIL PROVIDE ALLTHE NECESSARY EQUIPMENTS
TO AVOID ANY LOSS OF INGREDIENTS , OR DISPLACEMENT OF
STEEL BARS. .

17)
CIVILCO INSPECTOR AND LABORATORY TECHNICIAN SHALL
CONTROL THE CONCRETE PLACING AND PERFORM ALL TESTS
REQUIRED FOR EACH CONCRETE TRUCK ( AMBIENT TEMP , CONC
TEMP , CONCRETE SLUMP , AND SAMPLES OF CONCRETE AS REQUIRED
IN THE PROJECT SPECIFICATIONS .
18)
AFTER 24 HRS FROM PLACING THE CONCRETE , FORMWORK
SHALL BE STRIKED AND CURING WILL CONTINUE FOR 7 DAYS AS PER
SPECIFICATION.CURING COMPUND MAY PROPOSED AS AN
ALTERNATIVE
19)
CIVILCO INSPECTOR SHALL FOLLOW THE CURING
PROCEDURE.
20)
TOP OF COLUMNS AND / OR WALLS SHALL BE CLEANED AND
MADE ROUGH TO MAINTAIN A GOOD BONDING SURFACE TO
CONCRETE .
21)
THE SCAFFOLDING SYSTEM WILL BE DONE IN SAFE WAY FOR
BEAMS AND FLOOR SLABS.
22)
LAND SURVEYOR SHALL MARK THE EXACT LEVEL OF THE
FORMWORK OF THE BEAMS AND FLOOR SLABS .
23)
THE FORMWORK SHALL BE INSTALLED AS PER APPROVED
SHOP DRAWINGS .
24)
LAND SURVEYOR SHALL CONDUCT A COMPLETE SURVEYING
CHECK TO ENSURE THE DIMENTION FOR THE STRUCTURE BEFORE
INSTALLING THE STEEL REINFORCEMENT AND ANY OTHER ITEMS .
25) CIVILCO WIIL PROVIDE ALLTHE NECESSARY EQUIPMENTS
TO AVOID ANY LOSS OF INGREDIENTS , OR DISPLACEMENT OF
STEEL BARS.
26)
CIVILCO INSPECTOR AND LABORATORY TECHNICIAN SHALL
CONTROL THE CONCRETE PLACING AND PERFORM ALL TESTS
REQUIRED FOR EACH CONCRETE TRUCK ( AMBIENT TEMP , CONC
TEMP , CONCRETE SLUMP , AND SAMPLES OF CONCRETE AS
REQUIRED BY SPECIFICATIONS .
27)
IMMEDIATELY AFTER COMPLETION OF CONCRETE PLACING
AND FINISHING OF CONCRETE SURFACES , CURING SHALL
COMMENCE BY COVERING CONCRETE SURFACES BY POLYTHYLENE
SHEET .CURING COMPUND MAY PROPOSED AS AN ALTERNATIVE