PROJECT TITLE: CONCRETE WORKS


OWNER/S: MR. & MRS. RESTITUTO S. PARAISO
LOCATION: 3160 ABUCAY STREET MANUGUIT TONDO, MANILA CITY
PREPARED BY: BEAS, NOWIE T.
Item to be
Estimated

FOOTINGS

CALCULATIONSCEMENT
FOOTING1 = (1.2m)(1.2m)(0.3m)(1.10m)(6) = 2.8512 m3
FOOTING2 = (1.2m)(1.2m)(0.3m)(1.10m)(6) = 2.8512 m3
TOTAL VOLUME FOR FOOTING = 5.7024 m3

SAND

GRAVEL

40 bags

2.8512 m3

5.7024 m3

78 bags

5.544 m3

11.088 m3

109 bags

9.081535 m3

11.088 m3

20.3740152
m3

40.7480304
m3

CEMENT: 5.7024 m3 x 7.0 = 39.9168 ; 40 bags


SAND: 5.7024 m3 x 0.50 = 2.8512 m3
GRAVEL: 5.7024 m3 X 1 = 5.7024 m3
COLUMN1 = (0.3m)(0.4m)(0.7m)(1.10)(6) = 0.5544 m3
COLUMN2 = (0.3m)(0.4m)(0.7m)(1.10)(6) = 0.5544 m3
COLUMN3 = (0.3m)(0.4m)(6.6m)(1.05)(6) = 4.9896 m3
COLUMN4 = (0.3m)(0.4m)(6.6m)(1.05)(6) = 4.9896 m3
COLUMNS
TOTAL VOLUME FOR COLUMN = 11.088 m

BEAMS

CEMENT: 11.088 m3 x 6.0 = 77.616 ; 78 bags


SAND: 11.088 m3 x 0.50 = 5.544 m3
GRAVEL: 11.088 m3 x 1 = 11.088 m3
BEAM1 = (0.4m)(0.25m)[9m+3.760m(4)+3.823m(2)+
3.474m(4)+3.1m(3)+5.026m(2)](1.05) = 6.81807 m3
BEAM2 = (0.4m)(0.25m)[10.52m(2)+6.574m(4)](1.05)
= 4.97028 m3
BEAM3 = (0.4m)(0.25m)(10.52m)(1.10)(2) = 2.3144 m3
BEAM4 = (0.4m)(0.25m)(3)(1.10) = 0.33 m3
BEAM5 = (0.4m)(0.25m)(3.76m)(1.10) = 0.4136 m3
BEAM6 = (0.4m)(0.25m)(6.575m)(1.10)(2) = 1.4465 m3
BEAM7 = (0.4m)(0.25m)(8.501m)(1.10)(2) = 1.87022 m3
TOTAL VOLUME FOR BEAMS = 18.16307 m3
CEMENT: 18.16307 m3 x 6.0 = 108.97842 ; 109 bags
SAND: 18.16307 m3 x 0.50 = 9.081535 m3
GRAVEL: 18.16307 m3 x 1 = 11.088 m3
SLAB1 = (5.975m)(2.4m)(0.6m)+(6.92m)(5.964m)(0.6m)
(1.05) = 35.0348544 m3
SLAB2 = [(2.874m)(2.4m)+(2.874m)(3.16m)+
(2.874m)(3.16m)+(2.5m)(2.4m)(2)+(4.426m)(3.92m)]
(1.05)(0.1m) = 5.713176 m3

SLAB

245 bags
TOTAL VOLUME FOR SLAB = 40.7480304 m3

CEMENT: 40.7480304 m3 x 6.0 = 244.488 ; 245 bags


SAND: 40.7480304 m3 x 0.50 = 20.3740152 m3
GRAVEL: 40.7480304 m3 x 1 = 40.7480304 m3

Item to be
Estimated

STAIRS

CALCULATIONSCEMENT
TOTAL VOLUME FOR STAIRS
= {[(0.09m2)(7)+(0.045m2)(6)](0.3m)(1.05)(2)}+(0.85)
(2)(0.3)(1.05)(2)
= 1.022175 m3
7 bags

SAND

GRAVEL

0.5110875 m3

1.022175 m3

38.3618377
m3

76.7236754
m3

CEMENT: 1.022175 m3 x 6.0 = 6.13305 ; 7 bags


SAND: 1.022175 m3 x 0.50 = 0.5110875 m3
GRAVEL: 1.022175 m3 X 1 = 1.022175 m3
TOTAL VOLUME:
TOTAL

479 bags
76.7236754 m3

Submitted to:
_ENGR. MARJUN B. MACASILHIG_
INSTRUCTOR

TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES


Ayala Blvd., Ermita, Manila
COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: STEEL WORKS


OWNER/S: MR. & MRS. RESTITUTO S. PARAISO
LOCATION: 3160 ABUCAY STREET MANUGUIT TONDO, MANILA CITY
PREPARED BY: BEAS, NOWIE T.
Item to be
Estimated

FOOTINGS

CALCULATIONS
(1.2m/8)(2) = 0.3 m -> to be subtracted to 1.2
FOOTING1(6 sets)
PER PIECE:
0.9m+2[9(0.016)] = 1.188 m
1.188m x 14 = 16.632 m
PER SET:
16.632m x 6 sets = 99.792 m
99.792m / 6 = 16.632 ; 17pcs.-6m-16mm
FOOTING2(6 sets)
PER PIECE:
0.9m+2[9(0.016)] = 1.188 m
1.188m x 14 = 16.632 m
PER SET:
16.632m x 6 sets = 99.792 m
99.792m / 6 = 16.632 ; 17pcs.-6m-16mm

STEEL BARS

34 pcs.-6m-16mm

TOTAL LENGTH FOR FOOTING = 199.584 m

COLUMNS

TOTAL NUMBER OF STEEL BARS:


34 pcs.-6m-16mm
COLUMN1&3 (6 set) h = 6.6 m , 8 bars
LT = (6.6m)(8)(6) = 316.80 m
316.80m x 1.05 = 332.64 m
332.64m / 6 = 55.44 ; 55pcs.-6m-16mm
COLUMN2&4 (6 set) h = 6.6 m , 8 bars
LT = (6.6m)(8)(6) = 316.80 m
316.80m x 1.05 = 332.64 m
332.64m / 6 = 55.44 ; 55pcs.-6m-16mm
TOTAL LENGTH FOR COLUMNS = 665.28 m

110 pcs.-6m-16mm

TOTAL NUMBER OF STEEL BARS:


110 pcs.-6m-16mm

Item to be
Estimated

LATERAL
TIES
(COLUMNS)

CALCULATIONS
LTIES:
(0.4m)(2)+(0.3m)(2)+(20)(0.01m) = 1.6 m
1(0.001)+3(0.03)+5(0.05)+6(0.1) = 0.95(4 pieces)->15ties
2.6 / 0.2 = 13 ties
1.1 / 0.2 = 5.5 ; 6 ties

STEEL BARS

22 pcs-6m-10mm

TOTAL: 79 ties
LT = (1.6m)(79 ) = 126.4 m
126.4m / 6 = 21.07 ; 22 pcs-6m-10mm

TIE WIRES

BEAMS

Number of intersection:
7 x 7 = 49 int.
LTIE WIRES = 0.3 m
LT = (0.3m)(49) = 14.7 m
14.7m / 53 = 0.28 mg
(0.28kg)(10) = 2.8 kg no. 16 G.I. wire

BEAMS1&3 (4 set) d = 3.6 m , 4 bars


LT = (3.6m)(4)(4) = 57.60 m
57.60m x 1.05 = 60.48 m
60.48m / 6 = 10.08 ; 11pcs.-6m-16mm
BEAMS2&4 (6 set) d = 4 m , 4 bars
LT = (4m)(4)(4) = 64 m
64m x 1.05 = 67.2 m
67.2m / 6 = 11.2 ; 12pcs.-6m-16mm

2.8 kg no. 16 G.I. wire

23 pcs.-6m-16mm

TOTAL LENGTH FOR BEAMS = 127.68 m

LATERAL
TIES
(BEAMS)

TOTAL NUMBER OF STEEL BARS:


23 pcs.-6m-16mm
LTIES:
(0.4m)(2)+(0.2m)(2)+(20)(0.01m) = 1.4 m
1(0.001)+3(0.03)+5(0.05)+6(0.1) = 0.95(4 pieces)->15ties
2.6 / 0.2 = 13 ties
1.1 / 0.2 = 5.5 ; 6 ties
TOTAL: 79 ties
LT = (1.4m)(79 ) = 110.6 m
110.6m / 6 = 18.43 ; 19 pcs-6m-10mm

19 pcs-6m-10mm