RENCANA ANGGARAN BIAYA

JASA KONSULTANSI PENGAWASAN


LANJUTAN PEKERJAAN TANAH
DI BANDARA MOROWALI
NO

URAIAN PEKERJAAN

KLASIFIKASI

A
I

BIAYA LANGSUNG PERSONIL


TENAGA AHLI
1 Team Leader
2 Quantity Engineer
3 Quality Engineer

VOLUME/
MAN MONTH

HARGA SATUAN

JUMLAH BIAYA

1
1
1

x
x
x

5
5
5

Jumlah I

II

TENAGA PENDUKUNG
1 Inspector
2 Surveyor
3 Operator Komputer

2
1
1

x
x
x

5
5
5

Jumlah II

JUMLAH TOTAL A (I + II)

NO

URAIAN PEKERJAAN

KLASIFIKASI

B
I
1

BIAYA LANGSUNG NON PERSONIL


BIAYA MOBILISASI & DEMOBILISASI
Mobilisasi & Demobilisasi Personil

Orang/Trip

VOLUME

HARGA SATUAN

JUMLAH BIAYA

Jumlah I

II

SEWA PERALATAN
1 Sewa Komputer + Printer
2 Sewa Kantor Kerja dan Furniture
3 Sewa Motor + BBM

unit/bulan
unit/bulan
unit/bulan

2
1
5

x
x
x

5
5
5

BUKU PELAPORAN
1 Laporan Harian/Mingguan
2 Laporan Bulanan
3 Laporan Akhir

set
set
set

5
5
5

x
x
x

20
5
1

KOMUNIKASI
1 Telepon/Fax
2 Alat Kantor

unit/bulan
lot/bulan

1
1

x
x

Jumlah III
IV

Jumlah II
III

5
5

Jumlah IV

JUMLAH TOTAL B (I + II + III + IV)

RENCANA ANGGARAN BIAYA


JASA KONSULTANSI PENGAWASAN
LANJUTAN PEKERJAAN TANAH
DI BANDARA MOROWALI

REKAPITULASI :
A
I
II

B
I
II
III
IV

BIAYA LANGSUNG PERSONIL


TENAGA AHLI
TENAGA PENDUKUNG

JUMLAH A

BIAYA LANGSUNG NON PERSONIL


BIAYA MOBILISASI & DEMOBILISASI
SEWA PERALATAN
BUKU PELAPORAN
KOMUNIKASI

JUMLAH B

JUMLAH (A+B)
PPN 10%
JUMLAH TOTAL
DIBULATKAN

Terbilang :