Pouring Program for Next week Sr No. Period : 25-06-2015 to 02-07Forcaste Date Activity / Structure Name HRSG Foundation # 1 F3 Combine Raft Finfan Cooler Unit # 2 Blinding HRSG CONTROL BUILDING 5'-8 Elevated Slab Gantry Pedestal Firewall Column Upto Plinth Beam Pouring Program : Unit ELECTRICAL # 01 BUILDING # 02 Date GTP CONTROL # 02 Date HRSG CONTROL BUI
Pouring Program for Next week Sr No. Period : 25-06-2015 to 02-07Forcaste Date Activity / Structure Name HRSG Foundation # 1 F3 Combine Raft Finfan Cooler Unit # 2 Blinding HRSG CONTROL BUILDING 5'-8 Elevated Slab Gantry Pedestal Firewall Column Upto Plinth Beam Pouring Program : Unit ELECTRICAL # 01 BUILDING # 02 Date GTP CONTROL # 02 Date HRSG CONTROL BUI
Pouring Program for Next week Sr No. Period : 25-06-2015 to 02-07Forcaste Date Activity / Structure Name HRSG Foundation # 1 F3 Combine Raft Finfan Cooler Unit # 2 Blinding HRSG CONTROL BUILDING 5'-8 Elevated Slab Gantry Pedestal Firewall Column Upto Plinth Beam Pouring Program : Unit ELECTRICAL # 01 BUILDING # 02 Date GTP CONTROL # 02 Date HRSG CONTROL BUI