Minggu :
Tanggal :
Type 90/60
Blok / Nomor : A06
Mandor
KAMAL
No
A
Satuan
1 Bowplank
50
Type
150,000
0.72%
2 Galian
20
m3
310,000
1.50%
12
m3
480,000
2.32%
50
m'
125,000
0.60%
ls
400,000
1.93%
15
m3
52,500
0.25%
Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25
8.00
bh
1,600,000
7.73%
2 Sloof Beton
2.90
m3
580,800
2.81%
1.43
m3
214,200
1.03%
1.45
m3
218,025
1.05%
1.51
m3
226,800
1.10%
3.67
m3
550,800
2.66%
2.90
m3
435,600
2.10%
8 Balok beton15/25
5.07
m3
761,063
3.68%
1.34
m3
200,475
0.97%
2.29
m3
343,200
1.66%
7.43
m3
1,039,500
5.02%
6.60
m3
990,000
4.78%
0.26
m3
39,600
0.19%
14 Tangga beton
1.68
m3
420,000
2.03%
15 Dak beton t : 12 cm
6.00
m3
1,200,000
5.80%
16 Plat beton t : 10 cm
1.62
m3
243,000
1.17%
Pekerjaan Dinding
1 Dinding Bata
128.65
m2
1,929,750
9.32%
187.72
m2
2,252,640
10.88%
11.06
m2
221,200
1.07%
3 ban-ban pembatas
11.01
m2
990,900
4.79%
58
m2
406,000
1.96%
m'
54,000
0.26%
20
m'
180,000
0.87%
54
m2
216,000
1.04%
54
m2
216,000
1.04%
Pekerjaan Kayu
1 Pasang Genteng plat
2 Nok / Karpusan
Bobot
Pekerjaaan Pondasi
5 Galian Septictank
B
Pembulatan
Kontrak
230,000
Volume
Keramik
91
m2
1,183,000
5.71%
m2
240,000
1.16%
m2
100,000
0.48%
m2
250,000
1.21%
Bh
200,000
0.97%
5 Closed duduk
Bh
30,000
0.14%
Bh
180,000
0.87%
7 Saringan Air
Bh
30,000
0.14%
49
m'
367,500
1.78%
49
m'
367,500
1.78%
Bh
404,947
1.96%
ls
300,000
1.45%
20,700,000
100%
Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook
NILAI KONTRAK
Retensi Pekerjaan ( 100 Hari ) = 5%
Prestasi
lapangan
Jumlah
( Rp )
100
150,000
100
310,000
100
480,000
-
100
1,600,000
-
Jumlah :
2,540,000
127,000
2,413,000
2,413,000
minggu lalu =
minggu ini =
11.66
aktual =
11.66
PROGRESS LAPANGAN
Minggu :
Tanggal :
Type 90/60
Blok / Nomor : A07
Mandor
KAMAL
No
A
Satuan
Bobot
1 Bowplank
50
Type
150,000
0.72%
2 Galian
20
m3
310,000
1.50%
12
m3
480,000
2.32%
50
m'
125,000
0.60%
5 Galian Septictank
ls
400,000
1.93%
15
m3
52,500
0.25%
Pekerjaaan Pondasi
Pembulatan
Kontrak
230,000
Volume
Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25
8.00
bh
1,600,000
7.73%
2 Sloof Beton
2.90
m3
580,800
2.81%
1.43
m3
214,200
1.03%
1.45
m3
218,025
1.05%
1.51
m3
226,800
1.10%
3.67
m3
550,800
2.66%
2.90
m3
435,600
2.10%
8 Balok beton15/25
5.07
m3
761,063
3.68%
1.34
m3
200,475
0.97%
2.29
m3
343,200
1.66%
7.43
m3
1,039,500
5.02%
6.60
m3
990,000
4.78%
0.26
m3
39,600
0.19%
14 Tangga beton
1.68
m3
420,000
2.03%
15 Dak beton t : 12 cm
6.00
m3
1,200,000
5.80%
16 Plat beton t : 10 cm
1.62
m3
243,000
1.17%
Pekerjaan Dinding
1 Dinding Bata
128.65
m2
1,929,750
9.32%
187.72
m2
2,252,640
10.88%
11.06
m2
221,200
1.07%
3 ban-ban pembatas
11.01
m2
990,900
4.79%
58
m2
406,000
1.96%
m'
54,000
0.26%
20
m'
180,000
0.87%
Pekerjaan Kayu
1 Pasang Genteng plat
2 Nok / Karpusan
3 Pasang ListPlank 2/20
54
m2
216,000
1.04%
54
m2
216,000
1.04%
91
m2
1,183,000
5.71%
m2
240,000
1.16%
m2
100,000
0.48%
m2
250,000
1.21%
Bh
200,000
0.97%
5 Closed duduk
Bh
30,000
0.14%
Bh
180,000
0.87%
7 Saringan Air
Bh
30,000
0.14%
49
m'
367,500
1.78%
49
m'
367,500
1.78%
Bh
404,947
1.96%
ls
300,000
1.45%
20,700,000
100%
Keramik
1 Keramik Lantai 40x40
Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook
NILAI KONTRAK
Retensi Pekerjaan ( 100 Hari ) = 5%
Prestasi Jumlah
lapangan
( Rp )
100
150,000
100
310,000
100
480,000
-
100
1,600,000
-
Jumlah :
2,540,000
127,000
2,413,000
2,413,000
11.66
obot aktual =
11.66
PROGRESS LAPANGAN
Minggu :
Tanggal :
Type 90/60
Blok / Nomor : A07
Mandor
KAMAL
No
A
Satuan
1 Bowplank
50
Type
150,000
2 Galian
20
m3
310,000
12
m3
480,000
50
m'
125,000
5 Galian Septictank
ls
400,000
15
m3
52,500
Pekerjaaan Pondasi
Pembulatan
Kontrak
230,000
Volume
Pekerjaan Beton
1 Pondasi beton cakar ayam 120x120x25
8.00
bh
1,600,000
2 Sloof Beton
2.90
m3
580,800
1.43
m3
214,200
1.45
m3
218,025
1.51
m3
226,800
3.67
m3
550,800
2.90
m3
435,600
8 Balok beton15/25
5.07
m3
761,063
1.34
m3
200,475
2.29
m3
343,200
7.43
m3
1,039,500
6.60
m3
990,000
0.26
m3
39,600
14 Tangga beton
1.68
m3
420,000
15 Dak beton t : 12 cm
6.00
m3
1,200,000
16 Plat beton t : 10 cm
1.62
m3
243,000
Pekerjaan Dinding
1 Dinding Bata
128.65
m2
1,929,750
187.72
m2
2,252,640
11.06
m2
221,200
3 ban-ban pembatas
11.01
m2
990,900
58
m2
406,000
m'
54,000
20
m'
180,000
Pekerjaan Kayu
1 Pasang Genteng plat
2 Nok / Karpusan
3 Pasang ListPlank 2/20
54
m2
216,000
54
m2
216,000
91
m2
1,183,000
m2
240,000
m2
100,000
m2
250,000
Bh
200,000
5 Closed duduk
Bh
30,000
Bh
180,000
7 Saringan Air
Bh
30,000
49
m'
367,500
49
m'
367,500
Bh
404,947
ls
300,000
Keramik
1 Keramik Lantai 40x40
Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook
NILAI KONTRAK
Retensi Pekerjaan ( 100 Hari ) = 5%
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
20,700,000
-
Bobot
Prestasi Jumlah
lapangan
( Rp )
0.72%
100
150,000
1.50%
100
310,000
2.32%
100
480,000
0.60%
1.93%
0.25%
7.73%
100
1,600,000
2.81%
1.03%
1.05%
1.10%
2.66%
2.10%
3.68%
0.97%
1.66%
5.02%
4.78%
0.19%
2.03%
5.80%
1.17%
9.32%
10.88%
1.07%
4.79%
1.96%
0.26%
0.87%
1.04%
1.04%
5.71%
1.16%
0.48%
1.21%
0.97%
0.14%
0.87%
0.14%
1.78%
1.78%
1.96%
1.45%
100%
Jumlah :
2,540,000
127,000
2,413,000
2,413,000
11.66
Bobot aktual =
11.66
Jenis Kontrak
Nilai Kontrak
(Rp)
Bobot s.d
minggu ini
Total Tagihan
Retensi 5%
Pembayaran s\d
Minggu lalu
1 KAMAL
1 RUKO A06
20,700,000
11.66
11.66
2,540,000
127,000
2 RUKO A07
20,700,000
11.66
11.66
2,540,000
127,000
3 RUKO A08
20,700,000
11.66
11.66
2,540,000
127,000
Di Setujui
Di Ajukan
Ujang C
Mursidi
AGUS
Pembayaran s/d
hari ini
2,413,000
2,413,000
2,413,000
2,413,000
2,413,000
2,413,000
Rp
AGUS
7,239,000
PROGRESS LAPANGAN
Minggu :
Tanggal :
Type 90/60
Blok / Nomor : ruko
Mandor
No
Pekerjaaan Pondasi
1 Bowplank
50
Type
2 Galian
20
m3
12
m3
50
m'
5 Galian Septictank
ls
15
m3
8.00
bh
2 Sloof Beton
2.90
m3
1.43
m3
1.45
m3
1.51
m3
3.67
m3
2.90
m3
8 Balok beton15/25
5.07
m3
1.34
m3
2.29
m3
7.43
m3
6.60
m3
0.26
m3
14 Tangga beton
1.68
m3
15 Dak beton t : 12 cm
6.00
m3
16 Plat beton t : 10 cm
1.62
m3
1 Dinding Bata
128.65
m2
187.72
m2
11.06
m2
3 ban-ban pembatas
11.01
m2
58
m2
m'
Pekerjaan Beton
Pekerjaan Dinding
Pekerjaan Kayu
1 Pasang Genteng plat
2 Nok / Karpusan
20
m'
54
m2
54
m2
91
m2
m2
m2
m2
Bh
5 Closed duduk
Bh
Bh
7 Saringan Air
Bh
49
m'
49
m'
Bh
ls
Keramik
1 Keramik Lantai 40x40
Pekerjaan Tambahan
1 Plesteran + Acian Dinding hook
NILAI KONTRAK
Retensi Pekerjaan ( 100 Hari ) = 5%
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot aktual =
mg6
mg7
Jumla