Anda di halaman 1dari 1

Components of this Cooler shall be suitably marked in the drawing with

reference to corresponding BOM table.

Material description table shall be incorporated.

Following connections shall be included in the list :


- Water box drain connection.
- Water box vent connection.

Please indicate air inlet and outlet connections and identify the same suitably in the drawing.

DEVELOPMENT CONSULTANTS
PRIVATE LIMITED
Reviewed for general conformance with Contract
drawings and specifications.
ACTION :

1 Approved
2

Material of the following shall be included :


- Frames.
- Gasket.

Approved except as
noted. Forward final
drawing.
Approved except as
noted. Resubmission
required.

Disapproved.

For information/reference
only.

Information category with


comments. Resubmission
required.

Approval of Contract documents by the Consultant shall


not relieve the Seller of his responsibility for any errors
and fulfilment of Contract requirements.

Digitally signed by SANDIP


SARKAR
DN: cn=SANDIP SARKAR,
o=DCPL, ou=POWER-B,
email=sandipsarkar@in.dclgroup.
com, c=IN
Date: 2014.06.09 17:13:03 +05'30'
Other relevant design data shall be incorporated suitably, in line
with the format followed in Hydrogen Cooler GA drawing.