CRONOGRAMA VALORIZADO

REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI


FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

PROG
S/.
PROG
S/.

01.03.00 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS

PROG
S/.

01.04.00 TRAZO Y REPLANTEO

PROG

02.00.00 MOVIMIENTO DE TIERRAS

PROG
S/.

02.02.00 CORTE EN ROCA SUELTA

PROG
S/.

02.03.00 CORTE EN ROCA FIJA

PROG
S/.

02.04.00 CONFORMACION DE TERRAPLENES O RELLENOS

PROG
S/.

02.05.00 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO

2 MES

4,368.10

1 SEMANA

100.00%

100.00%

4,368.10

4368.10

2,410.77

1 SEMANA

100.00%

100.00%

2,410.77

2410.77

4,780.54

1 SEMANA

100.00%

33.33%

33.33%

4,780.54

1593.51

1,593.51

8,062.50

1 SEMANA

2 SEMANA

3 SEMANA

4 SEMANA

100.00%

20.00%

20.00%

20.00%

20.00%

20.00%

8,062.50

1612.50

1,612.50

1,612.50

1,612.50

1,612.50

56,291.53

2 SEMANA

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

25.00%

25.00%

25.00%

25.00%

56,291.53

14,072.88

14,072.88

14,072.88

14,072.88

27,711.32

2 SEMANA

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

25.00%

25.00%

25.00%

25.00%

27,711.32

6,927.83

6,927.83

6,927.83

6,927.83

32,436.42

2 SEMANA

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

25.00%

25.00%

25.00%

25.00%

32,436.42

8,109.11

8,109.11

8,109.11

8,109.11

16,251.38

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

33.33%

33.33%

33.33%

16,251.38

5,417.13

5,417.13

5,417.13

17,029.70

4 SEMANA

5 SEMANA

100.00%

33.33%

33.33%

33.33%

17,029.70

5,676.57

5,676.57

5,676.57

2 SEMANA

5 SEMANA

149,720.35
S/.

02.01.00 CORTE DE MATERIAL SUELTO

1 MES

19,621.91
S/.

01.02.00 CAMPAMENTO, OFICINAS PROVISIONALES Y PARQUE DE EQUIPO

PERIODO

TOTAL

01.00.00 TRABAJOS PRELIMINARES


01.01.00 CARTEL DE IDENTIFICACION DE OBRA 3.60 x 4.80 MTS

771,588.05

PROG

6 SEMANA

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL

03.00.00 PAVIMENTOS

PROG
S/.

03.02.00 AFIRMADO e= 0.15 M

PERIODO
1 MES

2 MES

193,541.00
S/.

03.01.00 PERFILADO Y COMPACTADO EN ZONA DE CORTE

PROG

39,959.33

5 SEMANA

100.00%

50.00%

50.00%

39,959.33

19,979.67

19,979.67

04.01.00 CUNETAS TRIANGULARES 0.50 x 0.50 M

6 SEMANA

100.00%

50.00%

50.00%

153,581.67

76,790.84

76,790.84

18,051.31
S/.
PROG
S/.

04.01.02 CONFORMACION DE CUNETAS EN TIERRA

PROG
S/.

04.01.03 CONFORMACION DE CUNETAS EN ROCA SUELTA

PROG
S/.

04.01.04 CONFORMACION DE CUNETAS EN ROCA FIJA

PROG

04.02.00 ALCANTARILLAS TMC = 36" (07 UND)


04.02.01 EXCAVACION PARA ESTRUCTURAS

PROG
S/.

04.02.02 ENCOFRADO Y DESENCOFRADO

PROG
S/.

04.02.03 SOLADO e= 0.10 M

7,218.63

3 SEMANA

4 SEMANA

100.00%

33.33%

33.33%

33.33%

7,218.63

2,406.21

2,406.21

2,406.21

5,455.08

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

33.33%

33.33%

33.33%

5,455.08

1,818.36

1,818.36

1,818.36

2,902.90

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

33.33%

33.33%

33.33%

2,902.90

967.63

967.63

967.63

2,474.70

3 SEMANA

4 SEMANA

5 SEMANA

100.00%

33.33%

33.33%

33.33%

2,474.70

824.90

824.90

824.90

22,740.29
S/.

PROG

6 SEMANA

153,581.67

04.00.00 OBRAS DE ARTE Y DRENAJE

04.01.01 TRAZO Y REPLANTEO

771,588.05

1,138.93

3 SEMANA

100.00%

100.00%

1,138.93

1,138.93

3,297.94

4 SEMANA

100.00%

100.00%

3,297.94

3,297.94

403.96

3 SEMANA

4 SEMANA

100.00%

50.00%

50.00%

403.96

201.98

201.98

5 SEMANA

7 SEMANA

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL
S/.

04.02.04 ACERO fy = 4200 KG/CM2

PROG
S/.

04.02.05 CONCRETO F'C=175 KG/CM2 + 30% P.M.

PROG
S/.

04.02.06 ALCANTARILLA TMC = 36"

PROG
S/.

04.02.07 EMBOQUILLADO DE PIEDRA e= 0.20 M

PROG

04.03.00 BADEN

PROG
S/.

04.03.02 ELIMINACION DE MATERIAL EXCEDENTE

PROG
S/.

04.03.03 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% P.G., e = 0.30 M

PROG
S/.

04.03.04 ENROCADO Y PROTECCION CON PIEDRA EMBOQUILLADO

PROG
S/.

04.03.05 ENCOFRADO Y DESENCOFRADO

PROG
S/.

04.03.06 JUNTA DE DILATACION ASFALTICA

PERIODO
1 MES

2 MES

2,464.73

5 SEMANA

100.00%

100.00%

2,464.73

2,464.73

7,307.67

5 SEMANA

100.00%

100.00%

7,307.67

7,307.67

7,477.92

5 SEMANA

100.00%

100.00%

7,477.92

7,477.92

649.14

5 SEMANA

100.00%

100.00%

649.14

649.14

35,913.75
S/.

04.03.01 EXCAVACION MASIVA EN CONGLOMERADO SECO

771,588.05

PROG

1,763.85

3 SEMANA

100.00%

100.00%

1,763.85

1,763.85

1,287.06

6 SEMANA

100.00%

100.00%

1,287.06

1,287.06

24,542.19

5 SEMANA

100.00%

100.00%

24,542.19

24,542.19

5,468.22

5 SEMANA

100.00%

100.00%

5,468.22

5,468.22

2,458.53

4 SEMANA

100.00%

100.00%

2,458.53

2,458.53

393.90

5 SEMANA

100.00%

100.00%

393.90

393.90

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL

04.04.00 MURO DE CONTENCION

PROG
S/.

04.04.02 ELIMINACION DE MATERIAL EXCEDENTE

PROG
S/.

04.04.03 RELLENO Y COMPACTACION CON MATERIAL PROPIO

PROG
S/.

04.04.04 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.

PROG
S/.

04.04.05 ENCOFRADO Y DESENCOFRADO

PROG
S/.

04.04.06 TUBERIA DE DRENAJE PVC SAP = 2"

PROG

04.05.00 PONTON (LUZ = 10 M)

PROG
S/.

04.05.02 EXCAVACION PARA ESTRUCTURAS, TERRENO NORMAL

PROG
S/.

04.05.03 EXCAVACION DE MATERIAL BAJO AGUA-MANUAL-SUB ESTRUCTUR

PROG
S/.

04.05.04 RELLENO CON MATERIAL PROPIO COMPACTADO.SUB ESTRUCTUR

2 MES

445.95

3 SEMANA

100.00%

100.00%

445.95

445.95

205.05

6 SEMANA

100.00%

100.00%

205.05

205.05

501.60

5 SEMANA

6 SEMANA

100.00%

50.00%

50.00%

501.60

250.80

250.80

20,199.07

5 SEMANA

100.00%

100.00%

20,199.07

20,199.07

4,253.09

4 SEMANA

100.00%

100.00%

4,253.09

4,253.09

176.22

4 SEMANA

100.00%

100.00%

176.22

176.22

92,314.10
S/.

04.05.01 TRAZO Y REPLANTEO

PERIODO
1 MES

25,780.98
S/.

04.04.01 EXCAVACION MASIVA EN CONGLOMERADO SECO

771,588.05

PROG

239.40

3 SEMANA

100.00%

100.00%

239.40

239.40

656.56

3 SEMANA

100.00%

100.00%

656.56

656.56

461.90

3 SEMANA

100.00%

100.00%

461.90

461.90

1,414.22

5 SEMANA

100.00%

100.00%

1,414.22

1,414.22

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL
S/.

04.05.05 CONCRETO 1:10 PARA SOLADO e= 4" - SUB ESTRUCTURA

PROG
S/.

04.05.06 CONCRETO SIMPLE f?c= 175 KG/CM2 + 30% P.G. - SUB ESTRUC

PROG
S/.

04.05.07 CONCRETO f?c= 210 KG/CM2 (PARAPETO ARMADO)- SUB ESTRU

PROG
S/.

04.05.08 ENCOF. Y DESENCOF. EN ESTRIBOS- SUB ESTRUCTURA

PROG
S/.

04.05.09 ACERO GRADO 60 - SUB ESTRUCTURA

PROG
S/.

04.05.10 SUB DREN DE SUB PRESION - SUB ESTRUCTURA

PROG
S/.

04.05.11 RELLENO CON MATERIAL GRANULAR PARA SUB DREN-SUB ESTR

PROG
S/.

04.05.12 TUBERIA DE EVACUACION DE SUB DREN = 3" - SUB ESTRUCTU

PROG
S/.

04.05.13 FALSO PUENTE - SUPERESTRUCTURA

PROG
S/.

04.05.14 CONCRETO f?c= 210 KG/CM2 -LOSA VIGA SARDENIEL- SUPERES

PROG
S/.

04.05.15 ACERO GRADO 60 - SUPERESTRUCTURA

PROG

771,588.05

PERIODO
1 MES

2 MES

1,246.17

5 SEMANA

100.00%

100.00%

1,246.17

1,246.17

37,123.02

4 SEMANA

100.00%

100.00%

37,123.02

37,123.02

4,229.20

4 SEMANA

100.00%

50.00%

50.00%

4,229.20

2,114.60

2,114.60

2,768.69

3 SEMANA

100.00%

50.00%

50.00%

2,768.69

1,384.35

1,384.35

5 SEMANA

4 SEMANA

2,133.51

4 SEMANA

100.00%

100.00%

2,133.51

2,133.51

49.32

4 SEMANA

100.00%

100.00%

49.32

49.32

145.22

5 SEMANA

100.00%

100.00%

145.22

145.22

42.72

4 SEMANA

100.00%

100.00%

42.72

42.72

6,607.40

5 SEMANA

100.00%

100.00%

6,607.40

6,607.40

9,345.09

5 SEMANA

100.00%

50.00%

50.00%

9,345.09

4,672.55

4,672.55

14,475.08

4 SEMANA

100.00%

100.00%

14,475.08

14,475.08

6 SEMANA

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL
S/.

04.05.16 APOYO FIJO DE NEOPRENE 0.10 CM x 3/4"

PROG
S/.

04.05.17 APOYO MOVIL DE NEOPRENE 0.10 CM x 3/4"

PROG
S/.

04.05.18 JUNTA DE DILATACION- CONTRACCION METALICA SUPERESTRUC

PROG
S/.

04.05.19 TUBERIA DE DRENAJE PVC SAP = 3" - SUPERESTRUCTURA

PROG
S/.

04.05.20 BARANDA DE F G DE 2 1/2" + PERFIL DE ACERO

PROG

05.00.00 SEALIZACION Y SEGURIDAD VIAL

PROG
S/.

05.02.00 FABRICACION DE SEALES PREVENTIVAS

PROG
S/.

05.03.00 FABRICACION DE SEALES REGLAMENTARIAS

PROG
S/.

05.04.00 CONSTRUCCION DE HITOS HILOMETRICOS

PROG

06.00.00 IMPACTO AMBIENTAL

2 MES

1,073.46

5 SEMANA

100.00%

100.00%

1,073.46

1,073.46

776.11

5 SEMANA

100.00%

100.00%

776.11

776.11

724.78

6 SEMANA

100.00%

100.00%

724.78

724.78

40.05

4 SEMANA

100.00%

100.00%

40.05

40.05

8,762.20

7 SEMANA

100.00%

100.00%

8,762.20

8,762.20

2,450.88

PROG

7 SEMANA

100.00%

50.00%

2,450.88

1,225.44

1,771.08

7 SEMANA

100.00%

50.00%

1,771.08

885.54

786.24

7 SEMANA

100.00%

50.00%

786.24

393.12

1,155.04

7 SEMANA

100.00%

50.00%

1,155.04

577.52

16,808.20
S/.

06.01.00 RESTAURACION DE CANTERAS

PERIODO
1 MES

6,163.24
S/.

05.01.00 FABRICACION DE SEALES INFORMATIVAS

771,588.05

2,835.00
100.00%

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

TOTAL
PROG

2,835.00

771,588.05

PERIODO
1 MES

2 MES

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS

PERIODO

TOTAL
S/.

06.02.00 RESTAURACION DE PATIO DE MAQUINAS Y CAMPAMENTO

S/.

2 MES

100.00%
724.00
9,382.45

PROG
S/.

06.04.00 REVEGETACION

1 MES

724.00

PROG

06.03.00 ACONDICIONAMIENTO DE DEPOSITO DE MATERIAL EXCEDENTE

771,588.05

100.00%
9,382.45
3,866.75

PROG

07.00.00 PRUEBA DE ENSAYO

7 SEMANA

100.00%

50.00%

3,866.75

1,933.38

5,079.15
S/.

07.01.00 PRUEBA DE COMPACTACION (PROCTOR MODIFICADO)

PROG
S/.

07.02.00 ENSAYO DE DENSIDAD DE CAMPO

PROG
S/.

07.03.00 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESIO

PROG
S/.

07.04.00 PRUEBA DE DISEO DE MEZCLAS DE CONCRETO

PROG

PROGRAMADO
ACUMULADO

2,410.20

3 SEMANA

100.00%

50.00%

5 SEMANA
50.00%

2,410.20

1,205.10

1,205.10

1,874.40

3 SEMANA

5 SEMANA

100.00%

50.00%

50.00%

1,874.40

937.20

937.20

155.64

5 SEMANA

6 SEMANA

100.00%

50.00%

50.00%

155.64

77.82

77.82

638.91

2 SEMANA

100.00%

100.00%

638.91

638.91

585,734.28

9,984.88

32,954.74

50,591.76

118,048.25

154,371.53

109,665.12

100%

1.70%

5.63%

8.64%

20.15%

26.36%

18.72%

90,568.03
15.46%

585,734.28

9,984.88

42,939.62

93,531.39

211,579.64

365,951.17

475,616.29

566,184.32

100%

1.70%

7.33%

15.97%

36.12%

62.48%

81.20%

96.66%

GASTOS GENERALES

5.70%

568.89

1,877.60

2,882.48

6,725.82

8,795.35

6,248.19

5,160.13

UTILIDADES
SUB TOTAL

5.00%

499.24
11,053.02

1,647.74
36,480.08

2,529.59
56,003.83

5,902.41
130,676.48

7,718.58
170,885.46

5,483.26
121,396.57

4,528.40
100,256.56

IGV

19.00%

2,100.07

6,931.22

10,640.73

24,828.53

32,468.24

23,065.35

19,048.75

CRONOGRAMA VALORIZADO
REHABILITACION CAMINO VECINAL MIRAFLORES-PUCARA-ORCCOHUASI
FECHA: JUNIO DEL 2008
UBICACIN

PRESUPUESTO TOTAL S/.

SAN JUAN BAUTISTA

PARTIDAS
PRESUPUESTO TOTAL

PERIODO

TOTAL
771,588.05

771,588.05

1 MES
13,153.09

43,411.30

66,644.55

2 MES
155,505.02

203,353.70

144,461.92

119,305.31

RAMA VALORIZADO

PERIODO
2 MES

8 SEMANA
33.33%
1,593.51

RAMA VALORIZADO

PERIODO
2 MES

RAMA VALORIZADO

PERIODO
2 MES

RAMA VALORIZADO

PERIODO
2 MES

RAMA VALORIZADO

PERIODO
2 MES

RAMA VALORIZADO

PERIODO
2 MES

8 SEMANA
50.00%
1,225.44
8 SEMANA
50.00%
885.54
8 SEMANA
50.00%
393.12
8 SEMANA
50.00%
577.52

8 SEMANA
100.00%

RAMA VALORIZADO

PERIODO
2 MES
2,835.00

RAMA VALORIZADO

PERIODO
2 MES
8 SEMANA
100.00%
724.00
8 SEMANA
100.00%
9,382.45
8 SEMANA
50.00%
1,933.38

19,549.96
3.34%
585,734.28
100.00%

1,113.86
977.50
21,641.32
4,111.85

RAMA VALORIZADO

PERIODO
2 MES
25,753.17