Metode Pelaksanaan Kolom
Metode Pelaksanaan Kolom
STRUKTUR GRAND
KAMALA LAGOON
EMERALD TOWER
BEKASI
Metode Pelaksanaan
KOLOM
METODE KOLOM
PELAKSANAAN :
Tahap 2
Tahap 1
METODE KOLOM
Tahap 1
Zone 2
AREA PODIUM
AREA TOWER
Zone 1
Zone 2
Zone 1
Zone 3
PERSEDIAAN :
Area Podium :
Zone 1 = 12 unit
Zone 2 = 12 unit
Zone 3 = 0 unit
Kebutuhan 6 unit KP
Dim = 650 x 650
Area Tower
Zone 1 =
6 unit K1
2 unit K2
2 unit K5
Zone 2 =
6 unit K1
1 unit K2
2 unit K5
Kebutuhan 6 unit K1
Dim : 750 x 2500
Kebutuhan 2 unit K5
Dim : 750 x 2500
Kebutuhan 2 unit K2
Dim : 400 x 1950
METODE KOLOM
Tahap 2
Zone
1
AREA
PODIUM
Zone
2
AREA TOWER
Zone 2
Zone 1
Zone
3
Zone
4
PERSEDIAAN :
Area Podium :
Zone 1 = 11 unit
Zone 2 = 15 unit
Zone 3 = 8 unit
Zone 4 = 11 unit
Kebutuhan 6 unit KP
dari TAHAP 1
Area Tower
Zone 1 =
6 unit K3
2 unit K4
2 unit K5
Zone 2 =
4 unit K1
1 unit K4
2 unit K5
Kebutuhan 6 unit K3
Dim : 750 x 2450
Kebutuhan 2 unit K4
Dim : 400 x 2150
Kebutuhan 2 unit K5
Dim : 750 x 2500
METODE KOLOM
TOTAL PERSEDIAAN BEKISTING KOLOM :
Tipe Kolom KP (area Podium)
Tower 1
Dim : 650 x 650 = 6 unit
Tower 2
Dim : 650 x 650 = 6 unit
TOTAL
= 12 unit
Tipe Kolom K1 dan K5
Tower 1 (K1 & K5)
Dim : 750 x 2500
= 8 unit
Tower 2 (K5)
Dim : 750 x 2500
= 2 unit
TOTAL
= 10 unit
Tipe Kolom K2
Tower 1
= 2 unit
Tipe Kolom K3
Tower 2
= 6 unit
Tipe Kolom K4
Tower 2
= 2 unit
PT PP ( PERSERO) TBK
Construction & Investment
Selesai.
Terima kasih