Following programme for relay commissioning test.

Following Actions are within protection panel 02(INCOMER 01).

Connect SMRT Voltage Output:


L1 to Wire E12 of MCB Q130
L2 to Wire E32 of MCB Q130
L3 to Wire E52 of MCB Q130
N to Ground Pad

Note: Q130 MCB is switch to OFF

Connect SMRT Current Output A:


L1 to
L2 to
L3 to
N to

Note
Connect SMRT Binary Inputs (BI):
BI:1 to Relay Output(E2 & F2) for Trip 236
BI:3 to Relay Output(E4 & F4) for Healthy 205 along with isolation by making Q205 MCB to
OFF position.
BI:4 to Relay Output(F5 & F6) for Alarm 194 along with isolation by making Q190 MCB to OFF
position.
BI:5 to Relay Output(F7 & E8) for Trip 245 along with isolation by making Q245 MCB to OFF
position.

BI:6 to Relay Output(F8 & F9) for Warning OK 280 along with isolation by making Q261 MCB
to OFF position.
BI:7 to Relay Output(E11 & F10) for Trip OK 281 along with isolation by making Q261 MCB to
OFF position.