Project:

IB THERMAL POWER STATION 2x660 MW

Date:

Subject:

Comments on Method Statement for 400 KV Switch Yard


Structural Installation
BGRE/PPD/0208/ELEC/MS/0816 Rev-01

BGRE Ref: BOP-LT- 7179

Document:

11th Mar 2015

OPGC Comments on Method Statement for 400 KV Switch Yard Structural Installation
No

OPGC Comments

1.

BGRE shall include in 6.7.3 that Final tightness must be check by


torque wrench.
Please revise and resubmit.

2.
3.

4.

5.
6.

BGRE shall include in S.no 5, theodolite or TS.


Please revise and resubmit
BGRE shall inspect verticality of tower with theodolite or TS.
Please revise and resubmit
BGRE Shall include following points in S.no-8
Check the tightness of all nuts using torque wrench.
Check for any missing of member & hole. Unused hole must be
sealed.
The joints shall be painted with zinc paint on all contact surfaces
during the course of erection.
Please revise and resubmit
The following Additional point shall be include
BGRE shall ensure installation of earth protection grid in the switchyard
along with earth pits before taking up tower erection.
BGRE shall provide modification method statement on GI members in
event of any mismatch of prefabrication members.

BGRE Comments
Incorporated

Incorporated
Incorporated
Incorporated may please ref 8.4,8.5 &8.6 of MS.
However Application of zinc painting is envisaged
for welded joints but the same may not be
required for bolted joints unless until the loss of
zinc coating (due to site handling) is observed in
member contact surface

Incorporated

After trail assembly verification at manufacturer


works only the angle members are accepted,
Page 1 of 2

hence the complete modification of angle


members involving fabrication at site is not
envisaged except adjustments pertaining to
alignment which will decided by site engineer with
prior approval from OPGC

7.

BGRE shall provide lightening/earthing protection during erection of


tower.

8.

BGRE shall submit the HIRA for switch yard structural installation for
OPGC review and approval.

Lightning and earthing system will installed as per


approved drg and Method statement.
Furnished

Page 2 of 2