PROYECTO
: "CONSTRUCION DE LA RED MATRIZ DE ALCANTARILLADO Y EMPALME DE AGUA POTABLE A LA RED EXISTENTE PARA EL
SECTOR SAN MARTIN - PREDIO PARCELA N21, DISTRITO DE PISCO, PROVINICA DE PISCO, DEPARTAMENTO DE ICA"
UBICACIN
FECHA
ITEM
02.01
DESCRIPCION
UND
METRADO
PRECIO S/,
PARCIAL S/,
TRABAJOS PRELIMINARES
02,01,01
ML
355.88
1.62
576.53
02,01,02
ML
355.88
1.77
629.91
02,01,03
ML
355.88
2.17
772.26
02,01,04
ML
355.88
1.46
519.58
02.02
MOVIMIENTO DE TIERRAS
02,02,01
ML
204.00
19.21
3,918.84
02,02,02
ML
141.38
29.95
4,234.33
02,02,03
ML
141.38
32.99
4,664.13
ML
345.38
6.36
2,196.62
ML
345.38
7.01
2,421.11
02.03
02,03,01
02.04
02,04,01
02.05
CAMA DE APOYO
Cama de Apoyo (Grava) E=0.10M Zanja P/TUB. PVC-UF
RELLENO DE ZANJA
02,05,01
ML
204.00
51.91
10,589.64
02,05,02
ML
141.38
62.20
8,793.84
M3
145.23
17.49
2,540.10
02.06
02,06,01
0.00
02.07
BUZONES
0.00
02,07,01
UND
7.00
2,585.03
18,095.21
02,07,02
UND
7.00
2,896.46
20,275.22
02,07,03
UND
1.00
71.69
71.69
0.00
02.08
0.00
02,08,01
Tuberias P.V.C U.F. Desague U.F ISO 44335 S25 200mm Suministro
ML.
345.38
27.04
9,339.08
02,08,02
Bombeo de Agua
ML.
345.38
10.79
3,726.65
02,08,03
ML.
345.38
4.73
1,633.65
02,08,04
ML.
345.38
3.01
1,039.59
COSTO DIRECTO
GASTOS GENERALES
10%
S/.
96,037.97
S/.
9,603.80
S/.
4,801.90
SUBTOTAL
S/.
110,443.67
S/.
19,879.86
TOTAL PRESUPUESTO
S/.
130,323.53
UTILIDAD
5%